Responses___2_to_Questions_for__MACC_Solicitation-5_July_14.docx

DOCX document 21 KB Posted

Attached to
MACC Solicitation # FA5685-14-R-0013
Solicitation number
FA5685-14-R-0013
Issued by

About this file

See Attachment for Responses to Questions for MACC Solicitatin FA5685-14-R-0013.

View the file

Other files

File Type Posted
FA5685-14-R-0013-0015.doc DOC document
Bldg._475_Drawings.pdf PDF
Revised_Bldg._____475_SOW_______01_Aug_14.docx DOCX document
FA5685-14-R-0013-0014.doc DOC document
FA5685-14-R-0013-0012.doc DOC document
RESPONSE___8_MACC_Solicitation_FA5685-14-R-0013.docx DOCX document
Attachment___31.docx DOCX document
Response___7-Solicitation___FA5685-14-R-0013.docx DOCX document
Attachement___32.pdf PDF
FA5685-14-R-0013-0011.doc DOC document
RESPONSE___6_MACC_Solicitation_FA5685-14-R-0013.docx DOCX document
RESPONSE___5_MACC_Solicitation_FA5685-14-R-0013.docx DOCX document
FA5685-14-R-0013-0010.doc DOC document
Questions___4_Response_to_MACC_Solicitation-FA5685-14-R-0013.docx DOCX document
Attachment___30_Gypsumboard_Wall_Detail.pdf PDF
FA5685-14-R-0013-0009.doc DOC document
Attachment___29_MACC_CIVIL-STRUCTURAL_DRAWINGS_____1.PDF PDF
Attachement___28_MACC_CIVIL-STRUCTURAL_DRAWINGS.PDF PDF
Response___3_to_MACC_Questions-FA5685-14-R-0013.docx DOCX document
FA5685-14-R-0013-0008.doc DOC document
Attachment___26_Section_H-4.docx DOCX document
Attachement___27_Supplement_to_2014_MACC_General_Specifications.docx DOCX document
FA5685-14-R-0013-0007.doc DOC document
INC-1104_Design_Review_Checklist.doc DOC document
Past_Performance_Questionnarie__PPQ.docx DOCX document
PPL_Jun_2014.xls XLS spreadsheet
FA5685-14-R-0013-00005.doc DOC document
RESPONSES_TO_QUESTIONS_FOR_MACC-SOLICITATION-FA5685-14-R-0013_-4_July_14.rtf RTF text file
FA5685-14-R-0013-0004.doc DOC document
FA5685-14-R-0013-0001.doc DOC document
Attachment___11_SOW_LJYC_10-1081.pdf PDF
Attachment___23_INC-1101_KTR_Cost_Estimate.xlsx XLSX spreadsheet
Attachment___7_INC-1101_Cost_Estimate.xlsx XLSX spreadsheet
Attachment___25_INC-1108_Design_Review_Checklist.xlsx XLSX spreadsheet
Attachment___5_Site_Visit_Reservation_Form3_FA5685-14-R-0013.docx DOCX document
Attachment___15_LJYC___1081_PPL__Feb_2012.xls XLS spreadsheet
Attachment___14_Drawings_LJYC_10-1081.pdf PDF
Attachment___6_SOW_LJYC_10-1052.pdf PDF
Attachment___24_INC-1106_Schedule_of_Material_Submittals.xls XLS spreadsheet
Attachment___8_LJYC_10-1052_INC_1106.xls XLS spreadsheet
Attachement___2_MACC_Design_Guide_2014.docx DOCX document
Attachment___3__Past_Performance_Questionnaire.docx DOCX document
Attachment___22_SOS_for_MOCK_Project_Ren_B_444.doc DOC document
Attachment___10_PPL_Feb_2012.xls XLS spreadsheet
Attachment___19_INC-1106_Schedule_of_Material_Submittals.xls XLS spreadsheet
Attachment___17_LJYC_11-1009_Repair_Roof_Bldg..pdf PDF
Attachment___16_Asbestos_Register_List.pdf PDF
Attachment___18_INC-1101_Cost_Price_Breakdown.xlsx XLSX spreadsheet
Attachment___21_LJYC___11-1009.xls XLS spreadsheet
Attachment___13_LJYC_10-1081_INC-1101.xlsx XLSX spreadsheet
Show 40 more

Latest 50 of 56 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Response # 2-5 July 2014-TO QUESTIONS FOR MACC “FA5685‐14‐R‐0013” SOLICITATION

Q # 1. According to the E6 (Sheet 18 of 20), the MDP of facility #444 is powered with 3x95 50 mm2 NYCY cable. Is it true?

Response: It is considered to be 3x95+50 sqmm NYCY.

Q # 2. Which transformer is feeding this cable and what is the approximately feeder distance?

Response: Approx. 150 meters to TR#70.

Q # 3. What is the capacity of this transformer (KVA) ? Is this dry type transformer ? What is the short-circuit impedance value (uk %) of this transformer ?

Response: 630KVA, dry type, 3.99%

Q # 4. IAW the SOW Seed Project-1, “RPR Replace Roll-up doors” design period 65 days, but total days of item 32 much more than 65 days. Please check once again (MUTLU) Design period is 65 days. Rest of the days on line item#32 do not account in design performance period because design should be completed/approved by government w/final submittal if not corrected final performance period will be the contractor’s fault and do not count on their design performance period.

Response: Design period is 65 days. Rest of the days on line item#32 do not account in design performance period because design should be completed/approved by government w/final submittal if not corrected final performance period will be the contractor’s fault and do not count on their design performance period.

Q # 4. What is the capacity of Wet Chemical Fire Hood Suppression Systems?

Response: Fire suppression system full load type DUAL AGENT WET CHEMICAL (ANSUL PIRANHA 10 OR EQUAL

Q # 5. What is the capacity of Fire Pumps?

Response: 575 GPM 45 PSI -3000 RPM, 20 HP, 380 V, 50 Hz, UL Listed/FM Approved, CLASS F INSULATION.(AURORA or Equal)

Q # 6. What is the capacity of pump controller?

Respopnse: Compatible capacity with fire pump. UL Listed/FM Approved (IAW Pump manufacturer recommendation) (Tornatech or equal)

Q # 7. "MACC_Solicitation___FA5685-14-R-0013-13_June_14" on page 38 of 46, paragraph (c) Subfactor 3- Mock Design requires Design Review Checklist (INC-1104) with the 65% design. Please provide Design Review Checklist (INC-1104) which was not provided with the solicitation documents.

Response: Please refer to each SOW for three (3) seed projects to determine their specific requirements. If statement of work doesn’t require desing efforts, then no design efforts are required for that specific seed project. Design Review Checklist (INC – 1104) has been uploaded.

Q # 8. "MACC_Solicitation___FA5685-14-R-0013-13_June_14" on page 38 of 46, paragraph (c) Subfactor 3- Mock Design requires Design Review Checklist (INC-1104) with the 65% design. Please provide Design Review Checklist (INC-1104) which was not provided with the solicitation documents.

Response: Design Review Checklist (INC – 1104) has been uploaded.

Q # 9. Airfield primary cable size? (DURMUS)

Response: -5 kv, 6 sqmm

Q # 10: Mock design project consist only SOW in solicitation package. Please provide concept drawings and/or as-build drawings for bldg. 444 on all disciplines (Architectural, Structural, Civil, Mechanical and Electrical). (DURMUS WITH MUSTAFA)

Response: Drawings are aviable via announcement in Amendment # 0004 posted on 27 June 14.

Q# 11: IAW the SOW of Mock project, structural part; there is no information regarding the existing bldg. frame and features. What is the Concrete Class, status of existing reinforcement, existing beam, columns and floor dimension?

Response: Given Architectural drawings are on scale. They can take the room floor dimensions, floor height, column sizes from the given drawings. In addition Concrete class is C25, Beam sizes are 35*50 cm, Slab thickness is 12 cm.

Reinforcement ratio is 4%.

Seismic zone: 2, Existing Local Subgrade class: Z2, Importance factor is 1 Behavior Factor: High ductile and R: Level 7

Q # 11: Document "MACC_Solicitation___FA5685-14-R-0013-13_June_14" page 6 of 46 indicates for MACC Option Period #4; Period of Performance is 27 August 2017 thru 26 August 2018. Please confirm that it should be revised as 27 August 2018 thru 26 August 2019.

Response: confirmed. Date should reflect as such: 27 August 2018 thru 26 August 2019.

Q # 12: Document "MACC_Solicitation___FA5685-14-R-0013-13_June_14" page 11 of 46 indicates that for the amount of contract over 500,000.00 USD, the required bank letter of guarantee amount is 15%, not to exceed 100,000.00 USD which seems very low and unreasonable. Please confirm.

Response: Amount will not exceed $100,000.

Q # 13: Could you please provide CAD drawings for the RPR Replace Roll Up Doors,ODC Building#977, (LJYC 10-1052) ?

Response: Drawings are aviable via announcement in Amendment # 0004 posted on 27 June 14.

Q # 14: Could you please provide CAD drawings including section and views for the MOCC projects (Renovate Building#444) ?

Response: Drawings are aviable via announcement in Amendment # 0004 posted on 27 June 14.

Q # 15: Could you please provide CAD drawings including section and views for the Repair Replace Roof at Building#475, (LJC11-1009) ?

Response: Drawings are aviable via announcement in Amendment # 0004 posted on 27 June 14.

Q # 16: The referenced electrical, plumbing ,pumps ,fire protection system and HVAC’s item at the MACC Schedule of Items do not have a clear material description.

Response: Drawings are aviable via announcement in Amendment # 0004 posted on 27 June 14.

Q # 17: The solicitation package stated that submit Attachment 3, Past performance Questionnaire. Who is going to be authorized person to evaluate and sign Attachment 3, Past performance Questionnaire for completed projects with USAFE, 39 CONS/LGCA?

Response: Past performance Questionnaire will be completed by appropriate qaulified government personnel.

Q # 18: The solicitation package section 3.PART IV – PAST PERFORMANCE INFORMATION © states that “Provide any information currently available (letters, metrics, customer surveys, independent surveys, etc.) which demonstrates customer satisfaction with overall job performance and quality of completed product for relevant past efforts/contracts. In addition, explain corrective actions taken in the past, if any, for substandard performance and any current performance problems such as cost overruns, extended performance periods, numerous warranty calls, etc.”.

The page limitation for each past performance is 5 pages. The Attachment 3, Past performance questionnaire is total 4 pages.

Response: Additional information outside of the PPQ is optional. The five (5) page limitation is placed on letters, metrics, customer surveys, independent surveys, etc.

Q # 19: The attachment 3, PPQ document solicitation number is incorrect. Please provide corrected Attachment 3 PPQ document?

Response: Updated PPQ document has been uploaded.

Q # 20: Some of PDF drawings which posted on FBO for seed projects are not readable. Please provide DWG files for all seed project drawings?

Response: Drawings are aviable via announcement in Amendment # 0004 posted on 27 June 14.

Q # 21: Mock design project consist only SOW in solicitation package. Please provide concept drawings and/or as-build drawings for bldg. 444 on all disciplines (Architectural, Structural, Civil, Mechanical and Electrical).

Response: Drawings are aviable via announcement in Amendment # 0004 posted on 27 June 14.

Q # 22: The solicitation package page 32 of 46, Section J List of attachments, states that 2014 MACC General Specifications Guide is 5397 pages. Provided 2014 MACC General Specifications Guide is 7046 pages. Please clarify?

Response: The correct number of pages for the 2014 MACC General Specifications Guide is 7046 pages.

Q # 23: The solicitation package page 32 of 46, Section J List of attachments, states that MACC Design Guide is 38 pages and dated Jan 2014. Provided 2014 MACC Design Guide is 73 pages and July 2014. Please clarify?

Response: The correct numberof pages for the 2014 MACC Design Guide is 74 pages.