This document contains questions and responses related to Solicitation Number FA527023R0006 for the Okinawa SABER. The solicitation is for indefinite-delivery/indefinite-quantity construction contracts to be awarded by the Department of the Air Force Pacific Air Forces. Key details include: responses clarified the revised task order statement of work and cost estimate attachments; confirmed material requirements and pricing methodology for non-priced tasks; and extended the phase II proposal due date to September 20, 2023. The 214% sustainment area cost factor applies to projects on Kadena Air Base in Okinawa, Japan for the base period and optional years' task orders.

View the file

Other files

File Type Posted
Solicitation Amendment FA527023R00060003 SF 30 CO Signed.pdf PDF
Attachment 1 - Section L Inst Cond and Notice to Offerors Rev 15 Sep 23.pdf PDF
Attachment 3 - Master Statement of Work Revised 15 Sep 23.pdf PDF
Attachment 8 - Cost Estimate Breakdown.xlsx XLSX spreadsheet
Attachment 7 -Seed Project - Revised Task Order Statement of Work.pdf PDF
After RFI Cutoff Government Response Okinawa SABER.xlsx XLSX spreadsheet
AF3052_LXEZ211015 Construct Bicycle and Motorcycle Shelter B177 (KTR).xlsx XLSX spreadsheet
Attachment 5 - Request for Information Form Government Response Phase II.xlsx XLSX spreadsheet
Solicitation Amendment FA527023R00060002 SF 30.pdf PDF
Solicitation Amendment - FA527023R00060002.pdf PDF
Attachment 1 - Section L - Instructions Conditions and Notices to Offerors Revised 10 Aug 23.pdf PDF
Attachment 3 - Master Statement of Work Revised 10 Aug 23.pdf PDF
Attachment 2 - Section M - Evaluation Factors for Award Revised 10 Aug 23.pdf PDF
Attachment 5 - Request for Information Form Government Response.xlsx XLSX spreadsheet
Solicitation Amendment - FA527023R00060001.pdf PDF
Solicitation Amendment FA527023R00060001 SF 30.pdf PDF
Attachment 7 - Seed Project - Attachment 1 - Site Location Map.pdf PDF
Attachment 7 - Seed Project - Attachment 2 - As-Built Site And Utility Plan.pdf PDF
Attachment 7 - Seed Project - Attachment 4 - B177 Shelter Site Plan.pdf PDF
Attachment I - 718 CES Environmental Specifications.pdf PDF
Attachment 7 -Seed Project - Task Order Statement of Work.pdf PDF
Attachment II - Section 01560 Environmental Protection.pdf PDF
Attachment 1 - Section L - Instructions Conditions and Notices to Offerors.pdf PDF
Attachment 4 - Master Specification.pdf PDF
Attachment 2 - Section M - Evaluation Factors for Award.pdf PDF
Attachment 7 - Seed Project - Attachment 3 - B760 Shelter Photos.pdf PDF
Solicitation - FA527023R0006.pdf PDF
Attachment 6 - Past Performance Questionnaire.docx DOCX document
Exhibit A - Price Schedule.xlsx XLSX spreadsheet
Attachment 3 - Master Statement of Work.pdf PDF
Attachment 5 - Request for Information Form.xlsx XLSX spreadsheet
Attachment III - 718 CES UFGS Division 01 Supplement.pdf PDF
Attachment IV - Kadena Design Guide.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table 1

FA527023R0006

Attachment 5

SOLICITATION NUMBER AND TITLE:

FA527023R0006

KADENA SABER IDIQ

No.Reference
(Sect/Para/Page)QuestionResponse
1responses to PPI 2 questions #1, 3 & 9KTRs are in receipt of attachment 7 - 'Seed Project Task Order Statement of Work - rev. 1, 17 May 2022' issued via original RFP only.

Was another version (revision) of the TO SOW meant to be issued with PPI 2 responses but missing?

Clarify PPI response and/or provide a copy of missing document.A revised Attachment 7 Seed Project - Task Order Statement of Work has been posted along with this RFI.
2responses to PPI 2 questions #2 & 16Government responses to PPIs #2 & 16 do not address the procurement and constructibility issues raised by bidders.
Confirm our understanding USG is willing to exercise flexibility with each TO construction timeframes, based on actual procurement lead times.Revised Task Order SOW answers this question; procurement time and construction time was updated in the revised TO SOW.
3responses to PPI 2 questions #2, 4, 16 and RFP attachment 4 (Master Specification) Section C para 2.0 & 3.0The Kadena Design Guide references the Japan District Design Guide (JDDG) published by the USACE Japan District for 718 CES Task Orders.
Advise if KTR would also be allowed to use JDDG criteria on DPW Task Orders for JIS equivalent material.Yes, KTR is allowed to use JIS equivalent for DPW TO's. Please note that JIS equivalent materials procured locally will be NPI and Area Cost factor will not be applied for these materials. Please refer to blank AF3052 for better understanding of the cost estimate structure. Included on SAM along with this RFI response.
4responses to PPI 2 questions #3, 4 & 9Confirm NEMA4X SST (316) requirement applicable to the disconnect switch also applies to the new panelboard enclosure and provide missing revised TO SOW.
Yes, See revised TO SOW; 'Attachment 7 -Seed Project - Revised Task Order Statement of Work'
5SOW Section 2Per Section 2.2, Task Order Pricing, the value of all Non Pre-Priced Tasks are direct cost only and co-efficient is not included in calculation. This is believed to be a significant error, as co-efficient cost should be applied to all costs. It is understood that applicable cost factors related to RS means would not apply since costs direct from suppliers is considered for Non Pre-Priced items; however, coefficient should apply to all items included in a Task Order Proposal. Please confirm the correct calculation method for Non Pre-Priced items?***Amended as of 15 Sep 2023***Non-Pre-Priced tasks will be priced in the same manner as priced tasks. Adherance to Exhibit A Pricing schedule will allow conformance to the soliciation requirements.
6AF3052_LXEZ211015+Construct+Bicycle+and+Motorcycle+Shelter+B177+(KTR)Are we only going to use the Cost Estimate Breakdown-KTR to price the SEED project or we can add/remove item?The contractor shall utlize the cost estimate breakdown Attachment 8 or a document substantially similar.
7AF3052_LXEZ211015+Construct+Bicycle+and+Motorcycle+Shelter+B177+(KTR)Is the SACF of 214% a standard and the KTR will only input value for SABER COFFICIENT & CONDITION?For new construction of real property, the Contractor must use the USACE Area Cost Factor (ACF). For repair and alteration of real property the Contractor must use the USACE Sustainment Area Cost Factor(SACF). The SACF for the seed project is 214% because the project takes place on Kadena AB Okinawa, Japan. The appropriate Sustainment Area Cost Factor (SACF) should be used based on the location the project is to take place. Sustainment Area Cost Factor (SACF) applies to base cost. Contractor is responsible for inputting Coefficient and Condition.
8AF3052_LXEZ211015+Construct+Bicycle+and+Motorcycle+Shelter+B177+(KTR)We need time to gather quotes for NPI items identified in the Cost Estimate Breakdown-KTR sheet. Can the Govt consider extending the proposal due date?The Government intends to extend the phase II proposal due date to 1100 HRS JST Wednesday 20 Sep 2023
9AF3052_LXEZ211015+Construct+Bicycle+and+Motorcycle+Shelter+B177+(KTR)Is the 214% SACF applicable for the full 5 years or is it only for the base period? If so, what is the SACF for the optional years?Currently the 214% SACF applies to any project on Kadena AB Okinawa, Japan. To apply the Cost Factor, the appropriate Cost Factor is applied to total bare direct cost calculated in the UPG to adjust the cost to location-specific cost reflecting Japanese local market conditions in accordance with Unified Facilities Criteria (UFC) 3-701-01;DoD Facilities Pricing Guide. All applicable ACF’s andSACF’s can be found in Chapter 1-4;Data Tables, Related Materials;Data Tables, Tab 4-1; OCONUS. Works conducted under this SABER must utilize the most current Cost Factor cited for the appropriate Site Code.