This document provides questions and answers related to an Air Force operational commercial solutions opening solicitation for a wet wing defueling system. The solicitation seeks proposals for a modular wet wing defueling system to service C-130 and C-17 aircraft with 4-inch male cam-lock and SPR connections. The system must meet filtration standards in T.O. 42B1-1 and include two static reels with 75 feet of plastic-coated grounding cable and clamps. It must also have upstream and downstream sample ports per UFC 3-460-01. Additive injection and pump requirements are not applicable as separate systems will be utilized if needed. Grounding must follow T.O. 00-25-172, including one bonding and one grounding reel with grounding rod.
View the file
Other files
Show all 50
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Air Force Operational Commercial Solutions Opening
FA4484-20-S-C002
Amendment A00003 Questions & Answers AOI 009 27 July 2020
Q: Provide interface requirements for Wet Wing Defuel from C-130 and C-17. Note: TLC typically supply their commercial space launch clients with modular end-connections, so they are able to adapt and exchange fittings as needed.
A: 4” male Cam-lock and Single Point Pressure Fuel Servicing Adapter (SPR) connection (Adding both will provide ability to receive from FARP/WWD or commercial) IAW T.O. 37A-1-101, Para 4.1.15
Q: Provide additive injection requirements in the event additives are needed (e.g., contracted fuel) to incorporate into design.
A: Separate system will be utilized and determined in the pre-planning stage if needed (Mendez Cart or dope procedures) N/A
Q: Provide fuel filter requirements to incorporate into design.
A: EI 1581, 6th Edition filtration standards required IAW T.O. 42B1-1, Para 3.4 (3)
Q: Assess Diesel America West DPL100-3MFC pump/performance curve to determine whether pump meets pressure control requirements. If not, provide pump/PSI regulation requirements to incorporate into design.
A: Need to know primary pressure relief/bypass of pump (not specified on pump spec sheet) N/A
Q: Provide any specific grounding requirements to incorporate into design.
A: Requires two (2) Static Reels, spring rewind w/75 ft. of plastic-coated cable w/military-style ground clamp (1-bonding; 1-grounding with grounding rod) IAW T.O. 00-25-172, Para 2.12
Q: Provide sampling port requirements to incorporate into design.
A: Requires Gammon type sample ports plumbed downstream and upstream of filter separator. IAW UFC 3-460-01, Para 7-5 (l)