Exhibit C-FS_Form_4025.pdf

PDF 1 MB Posted

Attached to
Fort Sill MATOC - Solicitation Federal contract opportunity
Solicitation number
W9124L-23-B-0001
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command Fort Eustis

About this file

This document is a transmittal form used by contractors to submit shop drawings, equipment data, material samples, or manufacturer's certificates of compliance to the Directorate of Public Works at Fort Sill for approval. The form requires contractors to provide key details such as the transmittal and specification numbers, contract document references, descriptions of submittal items, quantities, and codes indicating whether the items comply with contract requirements or require a variation. Contractors must sign the form to certify details are correct and in conformance with contract drawings and specifications before the Directorate of Public Works takes approval action. The approving authority then signs and dates the form upon completion of review, returning any enclosures with comments as needed. This transmittal form facilitates the review and approval process between contractors and the Directorate of Public Works for submittals required under construction contracts at Fort Sill.

View the file

Other files for this federal contract opportunity

Other files attached to Fort Sill MATOC - Solicitation, newest first.
File Type Posted
Solicitation W9124L23B0001-0006 MATOC 4-25-2023.pdf PDF
Amendment W9124L23B0001-0006 4-25-2023.pdf PDF
Attachment 2 - Fort Sill MATOC Base Specifications - Rev 2-4-25-2023.pdf PDF
Attachment 19 - Fort Sill MATOC QA Technical.pdf PDF
Amendment W9124L23B0001-0005 4-24-2023.pdf PDF
Solicitation W9124L23B0001-0005 MATOC 4-24-2023.pdf PDF
Amendment W9124L23B0001-0004 MATOC.pdf PDF
Attachment 18 - Fort Sill MATOC QA Technical.pdf PDF
Solicitation W9124L23B0001-0004 MATOC.pdf PDF
Attachment 17 Ft Sill Mechanical Design Guide R03-14-2023.pdf PDF
Solicitation W9124L23B0001-0003 MATOC.pdf PDF
Attachment 16-Ft Sill Air Cooled Chiller Options R07-22-2022.pdf PDF
Attachment 14- AS BUILTS 4-6-2023.pdf PDF
Attachment 8 - SEED Project SOW - Specifications-Rev1-4-6-2023.pdf PDF
Attachment 2 - Fort Sill MATOC Base Specifications-Rev1-4-6-2023.pdf PDF
Attachment 15-Asbestos Inspection Report -1-17-2013.pdf PDF
Attachment 13- Fort Sill MATOC QA Technical.pdf PDF
Amendment W9124L23B0001-0003 MATOC.pdf PDF
Attachment 9- SEED Project Drawings 4702-Revised 0003.pdf PDF
Attachment 10-TOC 21-007 SUBMITTAL REGISTER-Rev1-4-6-2023.pdf PDF
Exhibit G - Fort Sill OK Contractor Weather Report Submittal.pdf PDF
Amendment 2 - W9124L23B0001 0002.pdf PDF
Exhibit H - Fort Sill OK Contractor Material Delay Time Extension Request.pdf PDF
Solicitation - W9124L23B0001 0002.pdf PDF
Attachment 12 - Fort Sill MATOC QA MICC.pdf PDF
Solicitation - W9124L23B0001 0001.pdf PDF
Attachment 11 - Site Visit Attendees 3.8.2023_Redacted.pdf PDF
Amendment 1 - W9124L23B0001 0001.pdf PDF
Exhibit B - ContractorsQualityControlDailyReport.pdf PDF
Exhibit D -SF1413.pdf PDF
Attachment 9 - Seed Project Drawings 4702.pdf PDF
Attachment 7 - ODOT 2019 -FULL-SPEC-Web-Version.pdf PDF
Attachment 6 - General Decision Number OK20230077 - Residential - dated 01.06.2023.pdf PDF
Exhibit F - FS Form 94_PAYMENT ESTIMATE - CONTRACT PERFORMANCE.pdf PDF
Exhibit A -ContractProgressReport.pdf PDF
Attachment 4 - General Decision Number OK20230023 - Heavy - dated 01.06.2023.pdf PDF
Attachment 2 - Fort Sill MATOC Base Specifications.pdf PDF
Attachment 1 - SOW MATOC SILL-Rev3-2-14-2023.pdf PDF
Attachment 8 - SEED Project SOW Specifications.pdf PDF
Attachment 3 - General Decision Number OK20230014 - Highway - dated 01.06.2023.pdf PDF
Exhibit E -SWPPP review 2023 check sheet.pdf PDF
Attachment 10 - TOC 21-007 SUBMITTAL REGISTER.pdf PDF
Attachment 5 - General Decision Number OK20230043 - Building - dated 02.10.2023.pdf PDF
Solicitation W9124L23B0001-2-24-2023.pdf PDF
Show all 44

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Please wait...

If this message is not eventually replaced by the proper contents of the document, your PDF viewer may not be able to display this type of document.

You can upgrade to the latest version of Adobe Reader for Windows®, Mac, or Linux® by visiting http://www.adobe.com/go/reader_download.

For more assistance with Adobe Reader visit http://www.adobe.com/go/acrreader.

Windows is either a registered trademark or a trademark of Microsoft Corporation in the United States and/or other countries. Mac is a trademark of Apple Inc., registered in the United States and other countries. Linux is the registered trademark of Linus Torvalds in the U.S. and other countries.

david.dold1 10.0.2.20120224.1.869952

DATE:

TRANSMITTAL OF SHOP DRAWINGS, EQUIPMENT DATA, MATERIAL SAMPLES, OR MANUFACTURER'S CERTIFICATES OF COMPLIANCE

TRANSMITTAL NUMBER:

SECTION I - REQUEST FOR APPROVAL OF THE FOLLOWING ITEMS (This section will be initiated by the contractor)

TO: FROM: CONTRACT NUMBER: CHECK ONE:

THIS IS A NEW TRANSMITTAL

THIS IS A RE-SUBMITTAL OF

TRANSMITTAL:

SPECIFICATION DIVISION NUMBER (Cover only one Division with each submittal) PROJECT TITLE & LOCATION THIS TRANSMITTAL IS FOR: (Check one)

FIO

GA

DA

CR

DA/CR

DA/GA

DIRECTORATE OF PUBLIC WORKS

PREVIOUS EDITIONS ARE OBSOLETE

FS FORM 4025, OCT 2015

SECTION II - APPROVAL ACTION

REMARKS:

I certify that the above submitted items had been reviewed in detail and are correct and in strict conformance with the contract drawings and specifications except as otherwise stated.

ITEM

NO.

(See Note 3)

CONTRACT DOCUMENT REFERENCE

DESCRIPTION OF SUBMITTAL ITEM (Type, size, model number etc.)

SUBMITTAL TYPE

CODE (See Note 8)

NO. OF

COPIES

SPEC. NO.

SPEC. PARA.

NO.

DRAWING

SHEET NO.

CONTRACTOR

REVIEW CODE

VARIATION

Enter "Y" if requesting a variation (See Note 6)

FORT SILL DIRECTORATE

OF PUBLIC WORKS

ACTION CODE (Note 9)

a. b. c. d. e. f. g. h. i. j.

NAME OF CONTRACTOR SIGNATURE OF CONTRACTOR

ENCLOSURES RETURNED (List by item No.) NAME AND TITLE OF APPROVING AUTHORITY SIGNATURE OF APPROVING AUTHORITY DATE

PREVIOUS EDITIONS ARE OBSOLETE

DIRECTORATE OF PUBLIC WORKS

FS FORM 4025, OCT 2015

INSTRUCTIONS

1. Section 1 will be initiated by the Contractor in the required number of copies.

2. Each Transmittal shall be numbered consecutively. The Transmittal Number typically includes two parts separated by a dash (-). The first part is the specification section number. The second part is the sequential number for the submittals under that spec section. If the transmittal is a re-submittal, then add a decimal point to the end of the original Transmittal Number and begin numbering the re-submittal packages sequentially after the decimal.

3. The "item No." for each entry on this form will be the same "item No." as indicated on ENG FORM 4288-R.

4. Submittals requiring expeditious handling will be submitted on a separate FS Form 4025.

5. Items transmitted on each transmittal form will be from the same specification division. Do not combine submittal information from different specification division in a single transmittal.

6. If the data submitted are intentionally in variance with the contract requirements, indicate a variation in column i, and enter a statement in the Remarks block describing the detailed reason for the variation.

7. FS Form 4025 is self-transmitting - a - letter of transmittal is not required.

8. When submittal items are transmitted, indicate the "Submittal Type" (SD-01 through SD-11) in column c of Section 1.

9. For each submittal item, the Contractor will assign Submittal Action Codes in column h of Section 1. The Fort Sill Directorate of Public Works approving authority will assign Submittal Action Codes in column j of Section 1. The Submittal Action Codes are:

A-Approved as submitted B-Approved, except as noted. Re-submission not required C-Approved, except as noted. Refer the attached comments. Re-submission required D-Will be returned by separate correspondence E-Disapproved. Refer to attached comments F-Receipt acknowledged X-Receipt acknowledged, does not comply with contract requirement, as noted G-Other action required (Specify) K-Government concurs with intermediate design. (For D-B contracts) R-Design submittal is acceptable for release for construction. (For D-B contracts)

10. Approval of items does not relieve the contractor from complying with all the requirements of the contract.

SD-01 - Pre-construction SD-04 - Samples SD-07 - Certificate SD-10 - O&M Data SD-02 - Shop Drawings SD-05 - Design Data SD-08 - Manufacture's Instructions SD-03 - Product Data SD-06 - Test Report SD-09 - Manufacturer's Field Report SD-11 - Closeout

TRANSMITTAL NO.:
TO::
ENCLOSURES RETURNED (List by item No.):
NAME AND TITLE OF APPROVING AUTHORITY:
DateField1:
CheckBox1:
SignatureField1:

File details come from the government source that posted it. Updated .