Exhibit B - ContractorsQualityControlDailyReport.pdf

PDF 1 MB Posted

Attached to
Fort Sill MATOC - Solicitation Federal contract opportunity
Solicitation number
W9124L-23-B-0001
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command Fort Eustis

About this file

This document contains a template for a daily quality control report for federal construction contracts. The template requires reporting of contract details including number, specifications, name, contractor, notice to proceed and start dates, weather, work description with location, employees and equipment by trade, hours, instructions, difficulties, inspections, safety, and percentage complete. The related federal contract opportunity is a solicitation for maintenance and repair services at Fort Sill, Oklahoma under an indefinite-delivery/indefinite-quantity multiple award task order contract. Services include general construction categories such as demolition, repair, alteration, HVAC, civil, structural, mechanical, painting, roofing and paving incidental work. The contracting agency is the Department of the Army Mission and Installation Contracting Command at Fort Eustis.

View the file

Other files for this federal contract opportunity

Other files attached to Fort Sill MATOC - Solicitation, newest first.
File Type Posted
Solicitation W9124L23B0001-0006 MATOC 4-25-2023.pdf PDF
Amendment W9124L23B0001-0006 4-25-2023.pdf PDF
Attachment 2 - Fort Sill MATOC Base Specifications - Rev 2-4-25-2023.pdf PDF
Attachment 19 - Fort Sill MATOC QA Technical.pdf PDF
Amendment W9124L23B0001-0005 4-24-2023.pdf PDF
Solicitation W9124L23B0001-0005 MATOC 4-24-2023.pdf PDF
Amendment W9124L23B0001-0004 MATOC.pdf PDF
Attachment 18 - Fort Sill MATOC QA Technical.pdf PDF
Solicitation W9124L23B0001-0004 MATOC.pdf PDF
Attachment 17 Ft Sill Mechanical Design Guide R03-14-2023.pdf PDF
Solicitation W9124L23B0001-0003 MATOC.pdf PDF
Attachment 16-Ft Sill Air Cooled Chiller Options R07-22-2022.pdf PDF
Attachment 14- AS BUILTS 4-6-2023.pdf PDF
Attachment 8 - SEED Project SOW - Specifications-Rev1-4-6-2023.pdf PDF
Attachment 2 - Fort Sill MATOC Base Specifications-Rev1-4-6-2023.pdf PDF
Attachment 15-Asbestos Inspection Report -1-17-2013.pdf PDF
Attachment 13- Fort Sill MATOC QA Technical.pdf PDF
Amendment W9124L23B0001-0003 MATOC.pdf PDF
Attachment 9- SEED Project Drawings 4702-Revised 0003.pdf PDF
Attachment 10-TOC 21-007 SUBMITTAL REGISTER-Rev1-4-6-2023.pdf PDF
Exhibit G - Fort Sill OK Contractor Weather Report Submittal.pdf PDF
Amendment 2 - W9124L23B0001 0002.pdf PDF
Exhibit H - Fort Sill OK Contractor Material Delay Time Extension Request.pdf PDF
Solicitation - W9124L23B0001 0002.pdf PDF
Attachment 12 - Fort Sill MATOC QA MICC.pdf PDF
Solicitation - W9124L23B0001 0001.pdf PDF
Attachment 11 - Site Visit Attendees 3.8.2023_Redacted.pdf PDF
Amendment 1 - W9124L23B0001 0001.pdf PDF
Exhibit C-FS_Form_4025.pdf PDF
Exhibit D -SF1413.pdf PDF
Attachment 9 - Seed Project Drawings 4702.pdf PDF
Attachment 7 - ODOT 2019 -FULL-SPEC-Web-Version.pdf PDF
Attachment 6 - General Decision Number OK20230077 - Residential - dated 01.06.2023.pdf PDF
Exhibit F - FS Form 94_PAYMENT ESTIMATE - CONTRACT PERFORMANCE.pdf PDF
Exhibit A -ContractProgressReport.pdf PDF
Attachment 4 - General Decision Number OK20230023 - Heavy - dated 01.06.2023.pdf PDF
Attachment 2 - Fort Sill MATOC Base Specifications.pdf PDF
Attachment 1 - SOW MATOC SILL-Rev3-2-14-2023.pdf PDF
Attachment 8 - SEED Project SOW Specifications.pdf PDF
Attachment 3 - General Decision Number OK20230014 - Highway - dated 01.06.2023.pdf PDF
Exhibit E -SWPPP review 2023 check sheet.pdf PDF
Attachment 10 - TOC 21-007 SUBMITTAL REGISTER.pdf PDF
Attachment 5 - General Decision Number OK20230043 - Building - dated 02.10.2023.pdf PDF
Solicitation W9124L23B0001-2-24-2023.pdf PDF
Show all 44

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACTOR'S QUALITY CONTROL DAILY REPORT

REPORT NO. _________ SHEET 1 OF _________

PROJECT

CONTRACT NO.

DATE

PARK

CONTRACTOR'S REPRESENTATIVE ON THE JOB

WEATHER (Rain, Snow, Cloudy, Windy, etc.)

RAINFALL

Inches

TEMPERATURE GROUND CONDITIONS (Dry, Damp, Wet, Frozen, etc.)

MAX.

MIN.

1. PRIME CONTRACTOR

NO. EMPLOYEES BY JOB CATEGORIES Hours HEAVY EQUIPMENT ON

JOB

NO.

UNITS

HRS. WORKING

YES NO Comments

WORK PERFORMED BY PRIME CONTRACTOR:

MATERIALS DELIVERED OFFICIAL VISITORS TO SITE

2A. SUBCONTRACTOR, _____________________________________________: (If more than one subcontractor use copies of following page.)

NO. EMPLOYEES BY JOB CATEGORIES Hours HEAVY EQUIPMENT ON

JOB

NO.

UNITS

WORK PERFORMED BY SUBCONTRACTOR:

3. SPECIFIC INSPECTIONS: (Inspections performed, results, and corrective actions)

4. TESTING: 1 Check if any testing was performed today. (Complete and attach Test Report Information Sheets.)

Type and Location of Testing: ____________________________________________________________________________________

5. VERBAL INSTRUCTION RECEIVED FROM GOVERNMENT ON CONSTRUCTION DEFICIENCIES OR RE-TESTING

REQUIRED:

6. REMARKS:

7. CERTIFICATION:

I certify that the above report is complete and correct and that I, or my authorized representative, have inspected all work performed this day by the prime contractor and each subcontractor and determined that all materials, equipment, and workmanship are in strict compliance with the plans and specifications except as may be noted above. ____________________________________________________________ Contractor's Quality Control Representative

Exhibit B - Contractor's Quality Control Daily Report W9124L-23-B-0001 Fort Sill MATOC

SUBCONTRACTOR WORK CONTINUED:

CONTRACT NO. REPORT NO. _______

SHEET ____ OF ____

2 SUBCONTRACTOR,

NO. EMPLOYEES BY JOB CATEGORIES Hours HEAVY EQUIPMENT ON

JOB

NO.

UNITS

2 SUBCONTRACTOR,

JOB

NO.

UNITS

JOB

NO.

UNITS

JOB

NO.

UNITS

YES NO COMMENTS

Exhibit B - Contractor's Quality Control Daily Report

1. CONTRACT NUMBER

2. SPECIFICATION NUMBER

Task Order #

5. NOTICE TO PROCEED DATE

6. ACTUAL DATE STARTED

Company #Emp Trade Total Hours

Equipment Data O / R Hours Used Hours Standby HRS THIS DATE

PREVIOUS HRS

TOTAL HOURS

8b. NUMBER OF WORKERS ON JOB

11.GOVERNMENT REPRESENTATIVE COMMENTS (comments to items 8,9, and 10) Was site inspection performed of any work? Date of inspection.________________ No NA

13. CONTRACT COMPLETION DATE

19. DATE OF REPORT (S)

REV. 11-22-05

AM

Work Performed

14. PERCENT COMPLETE

8c. NAME OF CONTRACTOR'S REPRESENTATIVE

15. QUALITY CONTROL SIGNATURE AND DATE

(i.e. materials received, off site activities, three phase meetings-inspections) 9. CONTRACTOR INSTRUCTIONS GIVEN/RECEIVED

12. SAFETY OBSERVATIONS

Contractor Verification: The above report is complete and correct. All material, equipment used, and work performed

16. QUALITY ASSURANCE SIGNATURE AND DATE

during this reporting period are in compliance with the contract documents except as noted above.

10. CONTRACTOR DESCRIBE DIFFICULTIES ENCOUNTERED (INCLUDE DELAYS, DESCRIBE WORK NOT PERFORMED IN ACCORDANCE WITH SPECIFICATIONS, CORRECTIVE ACTIONS Etc.)

17. PROJECT MANAGER REVIEW

18. CONTRACTING ADMINISTRATOR'S SIGNATURE AND DATE 20. REPORT SERIAL NUMBER

4. NAME OF CONTRACTOR (COMPANY NAME)

7. WEATHER AND TEMPERATURE

8a. CONTRACTOR DESCRIBE WORK BEING PERFORMED (INCLUDE LOCATION OF WORK)

PM

3. ABBREVIATED CONTRACT NAME

Exhibit B - Contractor's Quality Control Daily Report

Block 1 Government contract number (Stays the same for all remaining reports).

Block 2 Government Task Order number (Stays the same for all remaining reports).

Block 3 Contract name (shorten with abbreviations if needed and Stays the same for all remaining reports).

Block 4 General Contractor Name (Stays the same for all remaining reports).

Block 5 Notice to proceed date (Stays the same for all remaining reports).

Block 6 should stay blank until the first day of site work then that date (Stays the same for all remaining reports).

Block 7 add approximate temp to description and you are good, nothing needed on no work days unless the weather is the cause for the no work.

Blocks 8a – 8c covers Number of workers and company they work for, plus equipment on site and hours, (note check your contract and umbrella contract for required information).

Block 11 is for government comments.

Block 12 I think you understand.

Block 13 is the Legal completion date for the contract, and can change if there is an extension to the contract by the contracting officer.

Block 14 percent complete based on entire contract; please note contracts can have multiple jobs (Contract Line Item Number, CLIN percentage is based on entire task order).

Block 15 is your QC signature (who checks them and sends them to the Government QAR, please check them completely to avoid revised reports).

Blocks 16-18 is for government use.

Block 19 is the date of the report being filed.

Block 20 is the serial number of the reports for the project.

Exhibit B - Contractor's Quality Control Daily Report W9124L-23-B-0001 Fort Sill MATOC peter.subitch Typewritten Text When completed print to a PDF prior to sending the daily to your QAR and only send the now non-fillable version.

peter.subitch Typewritten Text

Exhibit-4-Sample Daily Contract Inspection Report.pdf
PWDAYL
1 CONTRACT NUMBERRow1:
2 SPECIFICATION NUMBER:
Task Order:
3 ABBREVIATED CONTRACT NAMERow1:
4 NAME OF CONTRACTOR COMPANY NAMERow1:
7 WEATHER AND TEMPERATURE:
5 NOTICE TO PROCEED DATERow1:
6 ACTUAL DATE STARTEDRow1:
AM:
PM:
8a CONTRACTOR DESCRIBE WORK BEING PERFORMED INCLUDE LOCATION OF WORK:
CompanyRow1:
EmpRow1:
TradeRow1:
Total HoursRow1:
Work PerformedRow1:
CompanyRow2:
EmpRow2:
TradeRow2:
Total HoursRow2:
Work PerformedRow2:
CompanyRow3:
EmpRow3:
TradeRow3:
Total HoursRow3:
Work PerformedRow3:
CompanyRow4:
EmpRow4:
TradeRow4:
Total HoursRow4:
Work PerformedRow4:
CompanyRow5:
EmpRow5:
TradeRow5:
Total HoursRow5:
Work PerformedRow5:
CompanyRow6:
EmpRow6:
TradeRow6:
Total HoursRow6:
Work PerformedRow6:
CompanyRow7:
EmpRow7:
TradeRow7:
Total HoursRow7:
Work PerformedRow7:
CompanyRow8:
EmpRow8:
TradeRow8:
Total HoursRow8:
Work PerformedRow8:
CompanyRow9:
EmpRow9:
TradeRow9:
Total HoursRow9:
Work PerformedRow9:
CompanyRow10:
EmpRow10:
TradeRow10:
Total HoursRow10:
Work PerformedRow10:
CompanyRow11:
EmpRow11:
TradeRow11:
Total HoursRow11:
Work PerformedRow11:
Work PerformedHours Standby:
Equipment DataRow1:
O RRow1:
Hours UsedRow1:
Hours StandbyRow1:
Work PerformedRow13:
Equipment DataRow2:
O RRow2:
Hours UsedRow2:
Hours StandbyRow2:
Work PerformedRow14:
Equipment DataRow3:
O RRow3:
Hours UsedRow3:
Hours StandbyRow3:
Equipment DataRow4:
O RRow4:
Hours UsedRow4:
Hours StandbyRow4:
8b NUMBER OF WORKERS ON JOBRow1:
8c NAME OF CONTRACTOR S REPRESENTATIVERow1:
ie materials received off site activities three phase meetingsinspections 9 CONTRACTOR INSTRUCTIONS GIVENRECEIVEDRow1:
10 CONTRACTOR DESCRIBE DIFFICULTIES ENCOUNTERED INCLUDE DELAYS DESCRIBE WORK NOT PERFORMED IN ACCORDANCE WITH SPECIFICATIONS CORRECTIVE ACTIONS EtcRow1:
11GOVERNMENT REPRESENTATIVE COMMENTS comments to items 89 and 10 Was site inspection performed of any work Date of inspection No NA:
Date of inspection:
undefined: Off
No: Off
NA: Off
12 SAFETY OBSERVATIONS Contractor Verification The above report is complete and correct All material equipment used and work performed during this reporting period are in compliance with the contract documents except as noted above:
13 CONTRACT COMPLETION DATERow1:
14 PERCENT COMPLETERow1:
15 QUALITY CONTROL SIGNATURE AND DATERow1:
16 QUALITY ASSURANCE SIGNATURE AND DATE:
17 PROJECT MANAGER REVIEW:
18 CONTRACTING ADMINISTRATORS SIGNATURE AND DATERow1:
19 DATE OF REPORT SRow1:
20 REPORT SERIAL NUMBERRow1:

File details come from the government source that posted it. Updated .