Exhibit E -SWPPP review 2023 check sheet.pdf

PDF 830 KB Posted

Attached to
Fort Sill MATOC - Solicitation Federal contract opportunity
Solicitation number
W9124L-23-B-0001
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command Fort Eustis

About this file

This document contains a Stormwater Pollution Prevention Plan (SWPPP) checklist for a federal contract opportunity. The contract is a Multiple Award Task Order Contract (MATOC) through the Department of the Army Materiel Command Mission and Installation Contracting Command Fort Eustis for maintenance, repair, demolition, and construction services at Fort Sill. Work may include multiple construction disciplines such as HVAC, civil, structural, mechanical, painting, roofing and paving. The SWPPP checklist provides requirements for items that must be included in any SWPPP submitted for covered construction activities, such as contact information, site descriptions, drainage plans, inspection procedures, training records, and certifications to prevent stormwater pollution.

View the file

Other files for this federal contract opportunity

Other files attached to Fort Sill MATOC - Solicitation, newest first.
File Type Posted
Amendment W9124L23B0001-0006 4-25-2023.pdf PDF
Attachment 2 - Fort Sill MATOC Base Specifications - Rev 2-4-25-2023.pdf PDF
Solicitation W9124L23B0001-0006 MATOC 4-25-2023.pdf PDF
Solicitation W9124L23B0001-0005 MATOC 4-24-2023.pdf PDF
Attachment 19 - Fort Sill MATOC QA Technical.pdf PDF
Amendment W9124L23B0001-0005 4-24-2023.pdf PDF
Solicitation W9124L23B0001-0004 MATOC.pdf PDF
Amendment W9124L23B0001-0004 MATOC.pdf PDF
Attachment 18 - Fort Sill MATOC QA Technical.pdf PDF
Attachment 15-Asbestos Inspection Report -1-17-2013.pdf PDF
Attachment 13- Fort Sill MATOC QA Technical.pdf PDF
Amendment W9124L23B0001-0003 MATOC.pdf PDF
Attachment 9- SEED Project Drawings 4702-Revised 0003.pdf PDF
Attachment 10-TOC 21-007 SUBMITTAL REGISTER-Rev1-4-6-2023.pdf PDF
Attachment 17 Ft Sill Mechanical Design Guide R03-14-2023.pdf PDF
Solicitation W9124L23B0001-0003 MATOC.pdf PDF
Attachment 16-Ft Sill Air Cooled Chiller Options R07-22-2022.pdf PDF
Attachment 14- AS BUILTS 4-6-2023.pdf PDF
Attachment 8 - SEED Project SOW - Specifications-Rev1-4-6-2023.pdf PDF
Attachment 2 - Fort Sill MATOC Base Specifications-Rev1-4-6-2023.pdf PDF
Attachment 12 - Fort Sill MATOC QA MICC.pdf PDF
Exhibit G - Fort Sill OK Contractor Weather Report Submittal.pdf PDF
Amendment 2 - W9124L23B0001 0002.pdf PDF
Exhibit H - Fort Sill OK Contractor Material Delay Time Extension Request.pdf PDF
Solicitation - W9124L23B0001 0002.pdf PDF
Amendment 1 - W9124L23B0001 0001.pdf PDF
Solicitation - W9124L23B0001 0001.pdf PDF
Attachment 11 - Site Visit Attendees 3.8.2023_Redacted.pdf PDF
Attachment 10 - TOC 21-007 SUBMITTAL REGISTER.pdf PDF
Attachment 5 - General Decision Number OK20230043 - Building - dated 02.10.2023.pdf PDF
Solicitation W9124L23B0001-2-24-2023.pdf PDF
Exhibit B - ContractorsQualityControlDailyReport.pdf PDF
Exhibit C-FS_Form_4025.pdf PDF
Exhibit D -SF1413.pdf PDF
Attachment 9 - Seed Project Drawings 4702.pdf PDF
Attachment 7 - ODOT 2019 -FULL-SPEC-Web-Version.pdf PDF
Attachment 6 - General Decision Number OK20230077 - Residential - dated 01.06.2023.pdf PDF
Exhibit F - FS Form 94_PAYMENT ESTIMATE - CONTRACT PERFORMANCE.pdf PDF
Exhibit A -ContractProgressReport.pdf PDF
Attachment 4 - General Decision Number OK20230023 - Heavy - dated 01.06.2023.pdf PDF
Attachment 2 - Fort Sill MATOC Base Specifications.pdf PDF
Attachment 1 - SOW MATOC SILL-Rev3-2-14-2023.pdf PDF
Attachment 8 - SEED Project SOW Specifications.pdf PDF
Attachment 3 - General Decision Number OK20230014 - Highway - dated 01.06.2023.pdf PDF
Show all 44

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SWPPP review guide

• POC information The contractor is the permit holder. Provide Company name, address, and point(s) of contact, Phone, cell, and Email address. Identify who will be the qualified inspector, who will be responsible for insuring deficiencies are corrected. Identify any subcontractors.

• Project location information

Project name contract number, County, Site address or various locations as shown on drawing XXX

• A description of the nature of the construction activity (e.g., low density residential, shopping mall, highway, etc.) Estimates of the total area of the site and the total area of the site that is expected to be disturbed;

Provide one or two sentence description.

• A description of the intended sequence of major activities that disturb soils for major portions of the site, with approximate dates.

Include a more detailed description of each activity (e.g., stormwater runoff controls, grubbing, stockpiling, excavation, grading, sodding, sewer lines, swales, utilities, etc.)

• A legible site map, showing the entire site, indicating the following:

drainage patterns and approximate slopes anticipated after major grading activities; areas of soil disturbance; areas that will not be disturbed;

locations of major structural and nonstructural controls identified in the SWP3; locations where stabilization practices are expected to occur;

locations of off-site material, waste, borrow, or equipment storage areas;

location of all surface waters (including wetlands); locations where storm water discharges to a surface water, any areas to be protected, discharge locations..

• Marked up construction drawings with enough detail to implement BMP’s. Add statement on plans that “Additional BMPs will be added if existing BMPs prove ineffective.” Or when specific locations are not practical. State “silt fence or other suitable barriers shall be place down slope of all bare soil areas, and maintained until stabilized”

• A general location map

Must have enough detail to identify the location of your construction site and the receiving waters within one mile of the site.

• 4.5.1.H. The name of the receiving water(s) and the areal extent and description of wetlands or other special aquatic sites at or near the site that will be disturbed or that will receive discharges from disturbed areas of the project;

e.g. “Discharge from the site is to various stormwater conveyances to Sitting bear Creek which is a tributary of East Cache Creek. There are no wetlands in the vicinity of this project, or they are depicted on the site map or location map.” Only East Cache Creek upstream of the Wastewater treatment plant is listed as impaired.

Exhibit E - SWPPP review 2023 check sheet W9124L-23-B-0001 Fort Sill MATOC

• Identify all potential pollutants that you expect to be found at your site.

Diesel fuel, paints, sealants. All storage and fueling will be away from storm drains and ditches.

• A copy of the permit requirements

A copy of the OKR10 permit and of the signed copy of the NOI must be included in your

SWP3.

• Documentation of measures to protect endangered or threatened species

• Documentation of Federal, State or local historic preservation laws

• Documentation of Water Quality-Impaired Waters

Add the following statements, or similar statements to cover those items:

“Impact on Endangered Species The site has been evaluated by the Fort Sill Natural Resources Manager through the NEPA process for federal projects. The project area does not drain to any Sensitive Rivers or Watersheds listed in Addendum A of OKR10 or any impaired waterway. No adverse effect on endangered or threatened species or habitats were identified.”

“Impact on Historical Places. The site has been evaluated by the Fort Sill Cultural Resources Manager through the NEPA process for federal projects. Fort Sill’s consultation process did not identify any known cultural or historic resources. Workers shall stop work immediately and notify the Fort Sill Environmental Quality office upon discovery of items with potential historical significance including but not limited to:

arrowheads, bones, old bottles or building materials, building foundations, and suspected gravesites.

• Stormwater Control Measures e.g.

*Straw or hay bales are no longer allowed as BMPs* Silt fences to be placed down slope of exposed areas Straw wattles downslope of stock piles Gravel bags around curb inlets Erosion control blankets on steep slopes Street sweeping daily to remove sediment on roadways Policing of litter on site All controls will be installed and maintained in accordance with the manufacturer’s specifications and good engineering practices.

• Stabilization Practices Gravel or sod to match surrounding use for permanent stabilization.

Hay mulch or erosion blankets for temporary stabilization.

• Structural Practices Rip-rap at drainage outlets, diversion berms, construction entrances, check dams etc that are being used. Sediment basins for sites over 10 acres.

Exhibit E - SWPPP review 2023 check sheet

• Spill Prevention Response

We will maintain suitable spill response equipment on site for potential accidental release of fuel, oil, or chemicals, and store materials away from storm drains and waterways.

"For large spills or a spill emergency the Fort Sill fire department will be notified via 911 system. Post emergency response, the fire department notifies the Fort Sill Environmental Quality Division who makes a determination if further State or Federal notifications are required.

The contractor notifies the contracting officer or contracting officer’s representative who can then coordinate with Fort Sill Environmental Quality Division on any further required cleanup actions. Fort Sill Environmental Quality Division will make any required notifications to regulatory agencies."

• Waste Management Dumpsters, trash containers, hauled to Fort Sill landfill. Port-a-johns

• Inspections to be performed and documented weekly and post half inch rainfall events. a copy of all inspection reports will be at the site or at an easily accessible location.

Include a copy of the inspection form. (sample insp. Form below)

• Corrective actions are performed and documented for each identified deficiency or maintenance requirement on the inspection report. Corrective actions are completed within 7 calendar days.

Include a copy of the corrective action form. (Sample insp. Form below) if the corrective action changes the swppp it must be updated within 7 calendar days.

• Staff Training Requirements: Personnel will be trained to understand the scope of their stormwater related job duties including the location of all stormwater controls on the site required by this permit, and how they are installed and maintained.

• Log of major earth disturbing activities.

(can reference other contract required daily reports if they can be readily produced)

• Non-Storm Water Discharges that are combined with storm water discharges associated with construction activity must be identified in the SWP3.

List any below that might happen.

1. Fire hydrant flushings;

2. Waters used to wash vehicles where detergents are not used;

3. Water used to control dust in accordance with Part 4.5.2.C.2;

4. Potable water, including waterline flushing and initial pressure tests of newly constructed piping where the piping is clean and chemical agents have not been added to the test water or applied to the pipes;

5. Routine external building wash down which does not use detergents;

Exhibit E - SWPPP review 2023 check sheet

6. Pavement wash waters where spills or leaks of toxic or hazardous materials have not occurred (unless all spilled material has been removed) and where detergents are not used;

7. Uncontaminated air conditioning or compressor condensate;

8. Uncontaminated ground water or spring water;

9. Foundation or footing drains where flows are not contaminated with process materials such as solvents;

10. Landscape irrigation

11. Discharge or flows from emergency fire fighting activities;

12. Uncontaminated flows from excavation dewatering activities will be allowed if operational and structural controls are used to reduce any pollutant releases in order to avoid or minimize the impacts on water quality. These controls must be included in your SWP3.

• Certification statement signed by the company owner/ president.

Must be exact language

“I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage this system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations.”

• A copy of the permit requirements A copy of the OKR10 (Sept 2012), a signed copy of the NOI, and Permit certificate must be included in your SWP3.

FOR SUB-CONTRACTORS

Work performed by ___________________ on ____________________ project, permit number OKR10 ____ issued to _________________________________

Work performed by others on this site shall only be done after a statement is signed by the Contractor, Builder, Hauler or others to certify compliance with the Storm Water Pollution Prevention Plan (SWP3) for the site and accepting responsibility for compliance with OKR10 for their activities on the permitted site. Contractor must also be thoroughly familiar with, and adhere to, the (SWP3) and the Best Management Practices (BMP)

At a minimum the following must be followed on this permitted site:

• Where no sediment controls exist, they shall be provided on all down slope boundaries.

• Dewatering shall be directed to a silt fence or other measure to filter sediment from run-off.

• Activities to restore disturbed areas to their pre-disturbed condition shall be initiated with-in 14 days, and maintained and/or protected until final stabilization is achieved, or responsibility for the area is accepted by the permit holder.

• Any sediment from run-off, tracking or otherwise from responsible areas shall be cleaned up on a daily basis.

Certification

I certify that I understand the terms and conditions of the Oklahoma Pollutant Discharge Elimination System Act (OPDES) General Permit that authorizes storm water discharges associated with construction activity published in the modified OPDES General Permit OKR10 of Month Date, 2007, and the SWP3 and BMPs described pertaining to the construction site identified above.

I agree that as a contractor, builder, regular supplier, or a support service company, I am responsible for installing and/or maintaining the appropriate pollution prevention measures that I am responsible for according to the agreement I have with the permittee.

Company Name_________________________________________________

Title: ______________________________________________________

Name: (print)________________________________________________

Signature:X_________________________________ Date: __________

Corrective action Report DATE _______________ Project______________________ Permit number________

State the Problem

How will it be corrected?

Who will do what?

Identify Deadlines

• Corrective action will be initiated as soon as practicable, but no later than the end of the next working day.

• Failed or modified BMPs will be corrected before the next rain event but no later than 7 days

• Corrective action was not achieved before the next rainfall event because or NA

What changes have been made to the Site map and written SWP3 to prevent reoccurrence?

Follow-up Inspection ( not later than 7 days from initial finding)

DATE____________

Corrective action complete or why not.

Exhibit E - SWPPP review 2023 check sheet

Stormwater Pollution Prevention Plan (SWPPP) inspection

Project Name_________________________________________Permit number_____________

Type of inspection: (circle one) Weekly , After ½” rainfall , Follow-up

For disturbed areas and material storage areas exposed to precipitation:

1. Is sediment or other pollution prevented from leaving the site or entering a drainage system? yes no (circle one) __________________________________________________________

2. Have all new potential pollutant sources been protected? yes no (circle one)

3. Have all erosion control measures been implemented as identified in the SWPPP? yes no

4. Are implemented erosion control measures effective? yes no

5. Are erosion control measures maintained to operate correctly? yes no

6. Is sediment tracking controlled where vehicles enter or exit the site? yes no

7. Does the site have adequate erosion and sedimentation measures in place? yes no

8. Has the SWPPP/map been revised to include added or modified BMPs within 7 days? yes no na ______________________________________________________________

9. Have added or modified BMPs been implemented? yes no na

10. Is a sign posted at the site entrance or prominent place stating permit number, SWPPP location and contact information? yes no _____________________________________

11. Have exposed soil areas to remain inactive for 7 more days, been stabilized within 14 days? yes no ____________________________________________________________

*For items answered no, complete a Corrective Action Report .

Name of Qualified inspector ________________________________ Title______________________

Signature _________________ Date_____________

This report shall be made and retained as part of the SWP3 for at least three years from the date that the site is finally stabilized.

Exhibit E - SWPPP review 2023 check sheet

Follow-up Inspection ( not later than 7 days from initial finding)
DATE____________
Stormwater Pollution Prevention Plan (SWPPP) inspection