Project 25-101-ABL - Generator Replacements at Abilene State Supported Living Center
Solicitation number
HHS0016014v2
Issued by
Taylor County, Texas

About this file

This is a project specification document and technical submittal requirements package for the Texas Health and Human Services Commission's generator replacement project at Abilene State Supported Living Center in Abilene, Texas. The project, designated HHS Project No. 25-101-ABL, requires a general contractor to furnish all labor, materials, equipment, supervision, and services for the complete replacement of emergency generator systems across 24 buildings in the base bid scope, with additional alternate bids for five additional buildings. The work encompasses removal of existing generators, installation of new emergency generators with all required components, electrical installations, wiring, conduits, breakers, disconnects, fire alarm modifications and re-certifications, fencing, docking stations, power panels, integrated power centers, and utility connections. The contract must be performed with the facility fully occupied and operational throughout the construction period, with scheduled power shutdowns limited to no more than 8 hours between 8:00 a.m. and 5:00 p.m. The contractor must submit detailed phasing plans, progress schedules using Critical Path Method, shop drawings, submittals, and schedules of values prior to commencing work. Mobilization submittals must be approved before on-site work begins, and technical submittals marked for approval must be reviewed by the architect/engineer and owner. The project requires adherence to multiple technical standards, codes, and facility-specific working conditions including speed limits of 15 mph, vehicle security protocols, identification badges for all personnel, coordination with facility maintenance departments, and strict adherence to infection control and safety requirements.

The contract specifications establish comprehensive requirements for waste management, utility coordination, safety protocols compliant with OSHA standards, and fire protection system modifications according to NFPA standards. All removed generators and automatic transfer switches must be salvaged and returned to the owner, with boilers and domestic water storage tanks also designated for salvage at the facility's discretion. The contractor is responsible for all testing costs and must maintain as-built drawings with red-line notations throughout the project, providing electronic AutoCAD files to the architect/engineer upon completion. Operation and maintenance manuals must be provided in three copies with tabs, indices, wiring diagrams, and parts lists, with all manufacturer warranties transferred to the facility upon final acceptance. A notarized certificate confirming no asbestos-containing materials were incorporated into the work must be submitted. The project establishes specific facility-focused requirements including sign-in procedures at the plant manager's office, protection of residents through debris prevention protocols addressing pica concerns, prohibition of photography of residents, restrictions on contact with facility individuals, and reporting of accidents to security and the superintendent. Working hours are normally 8:00 a.m. to 5:00 p.m., Monday through Friday, excluding state holidays, with provisions for temporary generator provision to maintain emergency power during utility outages and scheduled power shutdowns.

View the file

Other files

File Type Posted
Attach I_Negotiated Modifications to the Proposal.pdf PDF
ESBD_466898_1768246884488_HHS0016014v2 Addendum No. 3 Acknowledgement.pdf PDF
Attach B_Texas UGCs (Version 2.2).pdf PDF
Exhibit A_Affs_and_Solicitation_Acceptance_AE_V. 2.3.pdf PDF
Attach D_Facility Specific Policies and Proc.pdf PDF
Attach J_HHS UTCs - Vendor v 3.4 Nov 2023.pdf PDF
Exhibit H - Site Map.pdf PDF
Exhibit B_HSP.pdf PDF
ESBD_466898_1769197882841_HHS0016014v2 RFP Revised per Addendum No. 4.pdf PDF
ESBD_466898_1767191884134_HHS0016014v2 Addendum No. 2.pdf PDF
Attach G_HSP (Large HSP).pdf PDF
Attach H2_Specs.pdf PDF
Exhibit D_Exceptions Form.pdf PDF
Attach H1_Drawings.pdf PDF
Attach F_Signed Pricing Proposal (Cover Page).pdf PDF
Exhibit C_Draft General Construction Services Contract.pdf PDF
ESBD_466898_1769197858368_HHS0016014v2 HHS Responses to Questions _Addendum 4.pdf PDF
Attach A_Affs v2.2.pdf PDF
Exhibit E_Respondent's Information, Disclosures, and Financial Form.pdf PDF
Attach E_Prevailing Wage Rates.pdf PDF
Exhibit F_Respondent's Pricing Form.pdf PDF
ESBD_466898_1765569303116_HHS0016014v2 Addendum No. 1 Acknowledgement.pdf PDF
Attach C_Project Special Conditions.pdf PDF
ESBD_466898_1769197882842_Attachment H-1 Project Drawings Revised per Addendum No. 4.pdf PDF
ESBD_466898_1769197794585_HHS0016014v2 Addendum No. 4 Acknowledgement.pdf PDF
Exhibit G_Evaluation Tool_GC RFP Template_v1_7_12-10-2024.pdf PDF
ESBD_466898_1764098657326_HHS0016014v2 Exhibits.zip ZIP file
ESBD_466898_1764098640004_HHS0016014v2 RFP.pdf PDF
HHS0016014v2 Attachments.zip ZIP file
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment H-2 Project Specifications

Revised per Addendum No. 4

GENERATOR REPLACEMENT

PROJECT

ABILENE STATE SUPPORTED LIVING CENTER

2501 MAPLE ST,

ABILENE, TX 79602

HHS PROJECT NO. 25-101-ABL

02/28/25

Prepared by:

ACR Engineering, Inc 3001 S Lamar Blvd, Ste 210

Austin, Texas 78704

02/28/2025

HHS Project No. 25-101-ABL Generator Replacement

Page I of I

TABLE OF CONTENTS

DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS

DIVISION 01 – GENERAL REQUIREMENTS

01 0000 SPECIAL CONDITIONS

01 3000 SUBMITTALS, SHOP DRAWINGS/SAMPLES & SCHEDULES

A. CONTRACT PROGRESS SCHEDULE

B. SHOP DRAWINGS LOG

C. SCHEDULE OF VALUES

01 4000 REFERENCE STANDARDS AND CODES

01 5000 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

01 7000 CLOSEOUT

DIVISION 02 – NOT USED

DIVISION 03 – CONCRETE

03 1000 CONCRETE FORMING

03 2000 CONCRETE REINFORCING

03 3000 CONCRETE CAST-IN PLACE

DIVISION 04 THRU 25 – NOT USED

DIVISION 26 – ELECTRICAL

260500 COMMON WORK RESULTS FOR ELECTRICAL

260523 CABLE, WIRE, AND CONNECTORS, 600 VOLT OR LESS

260526 GROUNDING

260533 RACEWAYS, CONDUITS, AND BOXES

260534 THROUGH PENETRATION FIRESTOPPING FOR ELECTRICAL SYSTEMS

261219 TRANSFORMER, PAD MOUNT (OIL COOLED)

262413 SWITCHBOARDS, 600 VOLT AND LESS

262416.11 DISTRIBUTION PANELBOARDS

262416.12 BRANCH CIRCUIT PANELBOARDS

262553 ELECTRICAL IDENTIFICATION

262726 WIRING DEVICES AND FLOOR BOXES

263213.13 ENGINE GENERATOR SYSTEM

263240 DOCKING STATION

263600 AUTOMATIC TRANSFER SWITCH

DIVISION 28 – electronic safety ad security

284600 FIRE ALARM AND SMOKE DETECTION SYSTEM

Special Conditions

Abilene State Supported Living Center

Abilene, TX 79602

October 13, 2025

01 00 00 - 1 of 16

SECTION 01 00 00

SPECIAL CONDITIONS

1.01 SCOPE:

A. The work covered by this project consists of the Contractor furnishing all layout, survey, plant, labor, supervision, quality control, materials, equipment, machines, tools, appliances, services, supplies, and incidentals and of performing all operations in connection with this project for each generator replacement, in strict accordance with these plans, specifications, and the contract documents.

BASE BID:

Item A: Remove and replace existing generators in Buildings 596, 633, 634, 635, 636, 645, 646, 648, 650, 651, 637, 638, 639, 640, 597, 652, 669, 670, 671, 672, 673, 674, 675, and 676.

The work included in this Bid includes furnishing all labor and materials for the removal of existing emergency generators and installation of new emergency generators in same location. Installation of additional new generators will be indicated on the contract drawings. Installation shall include all components, complete with all tests and certifications required for operational emergency generators. Scope shall include demolition, electrical installation, wiring, conduits, breakers, disconnects, fire alarm modifications and re-certifications, fencing, docking stations, power panels, integrated power centers, utility connections, etc. as shown on contract drawings.

ADD ALTERNATE:

Building 664 The work included in this Bid includes furnishing all labor and materials for the installation of relocated existing emergency generator and all piping etc. as shown.

Installation shall include all components, complete with all tests and certifications required for operational emergency generators. Scope shall include demolition, electrical installation, wiring, conduits, breakers, disconnects, fire alarm modifications and re-certifications, fencing, concrete pads, docking stations, power panels, integrated power centers, utility connections, etc. as shown on contract drawings.

Buildings 547, 656, 659, 641 and 665.

The work in this bid includes furnishing all labor and materials for the installation of new emergency generator and accessories, etc. Installation shall include all components, complete with all tests and certifications required for operational emergency generators.

Scope shall include demolition, electrical installation, wiring, conduits, breakers, disconnects, fire alarm modifications and re-certifications, fencing, concrete pads, docking station, power panels, utility connections, etc as shown on Contract Drawings.

PHASING

Installation shall be performed according to Preliminary Schedule with minimal impact and all construction complete within the submitted calendar days from date of Notice to Proceed. Schedule will be evaluated as part of the contractor’s proposal. Final scheduling shall be as scheduled with HHS and Abilene Facility based on availability of scheduled building.

Abilene State Supported Living Center

Abilene, TX 79602

October 13, 2025

HHS Project No. 25-101-ABL

01 00 00 - 2 of 16

1. Phasing Plan: The Facility will be fully occupied and in operation for the duration of the contract performance period. The Contractor shall submit for approval a detailed phasing plan to minimize duration of power interruption. All buildings shall run on utility power during construction, including those that are to be provided with temporary emergency generator as outlined in section below. Temporary emergency generator is provided to back up building in case of utility power outage.

2. Expected shutdowns outlined below shall be no longer than 8 hours at the time during 8am to 5pm.

3. All removed generators and ATSs shall be salvaged and returned to the Owner.

4. Contractor shall always maintain emergency power available to the buildings where specified below. Contractor can work simultaneously in as many buildings associated with a single emergency generator as possible as long as this requirement is met.

5. Proposed phasing plan is described below, and shall be conducted in the numbering order as follows:

1. – Generator #5. Buildings 650 and 651.

a. Prior to release of submittals for review, Contractor shall field verify generator #5 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of existing conditions that might adversely impact the project phasing and schedule.

b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that openings and dimensions are correct, and product(s) match approved submittals.

c. Remove fencing as indicated.

d. Remove existing generator #5 and turn over to Owner.

e. Deenergize and terminate existing generator cables and conduits.

f. Power new generator concrete pad and prepare conduit stub-ups.

g. Install new generator at location as indicated.

The work described below can happen simultaneously at buildings 650 and 651, or one at the time:

h. Install new underground wiring, conduits and pullboxes to the extent possible

i. Shut down emergency power, only. Buildings shall be running on utility power through the existing ATSs but without emergency power. Connect new wiring to generator and new ATSs. Verify proper phasing, terminate, torque, and provide ground connections.

Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).

j. Start up new generator and load bank test.

k. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized

l. Conduct new Life Safety/Critical Panel rework indicated in drawings to the extent possible prior to utility power shut down.

m. Shutdown utility power to the building and switch over from existing to new ATSs.

Power shutdown to building 651 shall be minimized to the extent possible since it is an active certified home.

n. Finalize Life Safety/Critical Panel Rework indicated in drawings.

o. Operate ATSs manually to bring back utility power to the building.

1 ADDENDUM 4

1/13/2026

Abilene State Supported Living Center

Abilene, TX 79602

October 13, 2025

01 00 00 - 3 of 16

p. Remove existing ATSs and turn over to Owner.

q. Schedule ATSs startup as soon as possible after successful installation.

r. Install new fencing.

2. – Generator #6. Buildings 637, 638, 639 and 640.

a. Prior to release of submittals for review, Contractor shall field verify generator #6 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of existing conditions that might adversely impact the project phasing and schedule.

b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that openings and dimensions are correct, and product(s) match approved submittals.

c. Remove fencing as indicated.

d. Remove existing generator #6 and mount on a trailer (this generator shall be reused as a mobile generator to feed temporary emergency power to this and buildings served by generators 1, 3, 4, 7, 10, 15, 16 & 17. Turn over generator to Owner once it is no longer needed for temporary power).

e. Terminate temporary power and control cables from mobile generator to existing Emergency Panel #2 adjacent to existing generator to maintain emergency power connection to all buildings.

f. Install new generator at location of existing pad, as indicated. Prior to installation, coordinate stub-up locations is adequate for new generator, and make necessary modifications on pad for proper installation of generator.

The work described below can happen simultaneously in buildings 637, 638, 639 and 640, or one at the time:

g. Install new underground wiring, conduits and pullboxes to the extent possible.

h. Shut down emergency power, only. Buildings shall be running on utility power through the existing ATSs but without emergency power. Connect new wiring to generator and new ATSs. Verify proper phasing, terminate, torque, and provide ground connections.

Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).

i. Install new Electrical Distribution Panel EDP-6 and make connections to generator and buildings feeders.

j. Start up new generator and load bank test.

k. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized.

l. Coordinate ahead of time with the utility company for installation of new utility pole and associated feeders to the extent possible in parallel with the work performed to this point without disrupting power to the buildings.

m. Install new building Main Distribution Panels “MDP-637, 638, 639 & 640 and associated scope including conduit and conductors to the extent possible prior to utility power shut down.

n. Shutdown utility power to the building(s) and switch over from existing to new ATS(s). Power shutdown to building 638 and 640 shall be minimized to the extent possible since it is an active certified home.

o. Finalize installation of new building Main Distribution Panels “MDP-637, 638, 639 & 640 and associated conduit and conductors.

Abilene State Supported Living Center

Abilene, TX 79602

October 13, 2025

01 00 00 - 4 of 16

p. Finalize installation of new utility service.

q. Operate ATSs manually to bring back utility power to the building.

r. Remove existing ATSs and turn over to Owner.

s. Schedule ATSs startup as soon as possible after successful installation.

t. Install new fencing.

3. – Generator #3. Buildings 633, 634, 635 and 636.

a. Prior to release of submittals for review, Contractor shall field verify generator #3 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of existing conditions that might adversely impact the project phasing and schedule.

b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that openings and dimensions are correct, and product(s) match approved submittals.

c. Remove fencing as indicated.

d. Bring mobile generator #6 and terminate temporary power and control cables from it to existing ATS adjacent to existing generator to maintain emergency power connection to all buildings.

e. Install new generator at location of existing pad, as indicated. Prior to installation, coordinate stub-up locations is adequate for new generator, and make necessary modifications on pad for proper installation of generator.

The work described below can happen simultaneously in buildings 633, 634, 635 and 636, or one at the time:

f. Install new underground wiring, conduits and pullboxes to the extent possible.

g. Shut down emergency power, only. Buildings shall be running on utility power through the existing ATSs but without emergency power. Connect new wiring to generator and new ATSs. Verify proper phasing, terminate, torque, and provide ground connections.

Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).

h. Install new Electrical Distribution Panel EDP-3 and make connections to generator and buildings feeders.

i. Start up new generator and load bank test.

j. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized.

k. Coordinate ahead of time with the utility company for installation of new feeders to the extent possible in parallel with the work performed to this point without disrupting power to the buildings.

l. Install new building Main Distribution Panels “MDP-633, 634, 635 and 636 and associated scope including conduit and conductors to the extent possible prior to utility power shut down.

m. Shutdown utility power to the building(s) and switch over from existing to new ATS(s). Power shutdown to building 633, 635 and 636 shall be minimized to the extent possible since it is an active certified home.

n. Finalize installation of new building Main Distribution Panels “MDP-633, 634, 635 and 636 and associated conduit and conductors.

o. Finalize installation of new utility service.

p. Operate ATSs manually to bring back utility power to the building.

Abilene State Supported Living Center

Abilene, TX 79602

October 13, 2025

01 00 00 - 5 of 16

q. Remove existing ATSs and turn over to Owner.

r. Schedule ATSs startup as soon as possible after successful installation.

s. Install new fencing.

4. – Generator #11. Buildings 669, 670, 671, 672, 67., 674, 675 and 676

a. Prior to release of submittals for review, Contractor shall field verify generator #11 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of existing conditions that might adversely impact the project phasing and schedule.

b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that openings and dimensions are correct, and product(s) match approved submittals.

c. Remove fencing as indicated.

d. Remove existing generator #11 and mount on a trailer to feed temporary emergency power to this building. Turn over generator to Owner once work is complete.

e. Replace existing generator structural pad with new and install new generator. Prior to installation, coordinate stub-up locations is adequate for new generator, and make necessary modifications on pad for proper installation of generator.

The work described below can happen simultaneously in buildings 669, 670, 671, 672, 67., 674, 675 and 676, or one at the time:

the existing ATSs but without emergency power. Connect new wiring to generator and new ATSs. Verify proper phasing, terminate, torque, and provide ground connections.

Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).

h. Install new Electrical Distribution Panel EDP-11 and make connections to generator and buildings feeders.

i. Start up new generator and load bank test.

j. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized.

k. Shutdown utility power to the building(s) and switch over from existing to new

ATS(s). Power shutdown to all buildings shall be minimized to the extent possible, with building 670 being the less critical.

l. Operate ATSs manually to bring back utility power to the building.

m. Remove existing ATSs and turn over to Owner.

n. Schedule ATSs startup as soon as possible after successful installation.

o. Install new fencing.

5. – Generator #4. Buildings 645, 646 and 648

a. Prior to release of submittals for review, Contractor shall field verify generator #4 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of existing conditions that might adversely impact the project phasing and schedule.

b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that

Abilene State Supported Living Center

Abilene, TX 79602

October 13, 2025

01 00 00 - 6 of 16 openings and dimensions are correct, and product(s) match approved submittals.

c. Remove fencing as indicated.

d. Bring mobile generator #6 and terminate temporary power and control cables from it to existing ATS adjacent to existing generator to maintain emergency power connection to all buildings.

e. Replace existing generator structural pad with new and install new generator and docking station. Prior to installation, coordinate stub-up locations is adequate for new generator, and make necessary modifications on pad for proper installation of generator.

The work described below can happen simultaneously in buildings 645, 646 and 648, or one at the time:

the existing ATSs but without emergency power. Connect new wiring to generator and new ATSs. Verify proper phasing, terminate, torque, and provide ground connections.

Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).

h. Install new Electrical Distribution Panel EDP-4 and make connections to generator and buildings feeders.

i. Start up new generator and load bank test.

j. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized.

k. Conduct new Life Safety/Critical Panel rework indicated in drawings to the extent possible prior to utility power shut down.

l. Shutdown utility power to the building(s) and switch over from existing to new

ATS(s). Power shutdown to all buildings shall be minimized to the extent possible.

m. Finalize Life Safety/Critical Panel rework indicated in drawings.

n. Operate ATSs manually to bring back utility power to the building.

o. Remove existing ATSs and turn over to Owner.

p. Schedule ATSs startup as soon as possible after successful installation.

q. Install new fencing.

6. – Generator #1. Building 596

a. Prior to release of submittals for review, Contractor shall field verify generator #1 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of existing conditions that might adversely impact the project phasing and schedule.

b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that openings and dimensions are correct, and product(s) match approved submittals.

c. Remove fencing as indicated.

d. Bring mobile generator #6 and terminate temporary power and control cables from it to existing ATS adjacent to existing generator to maintain emergency power connection to building.

e. Replace existing generator structural pad with new and install new generator and docking station. Prior to installation, coordinate stub-up locations is adequate for new generator, and make necessary modifications on pad for proper installation of

Abilene State Supported Living Center

Abilene, TX 79602

October 13, 2025

01 00 00 - 7 of 16 generator.

g. Shut down emergency power, only. Building shall be running on utility power through the existing ATSs but without emergency power. Connect new wiring to generator and new ATS. Verify proper phasing, terminate, torque, and provide ground connections.

Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).

h. Start up new generator and load bank test.

i. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized.

j. Conduct new Life Safety/Critical Panel rework indicated in drawings to the extent possible prior to utility power shut down.

k. Shutdown utility power to the building and switch over from existing to new ATS.

Power shutdown to building shall be minimized to the extent possible.

l. Finalize installation of Life Safety/Critical Panel rework.

m. Operate ATS manually to bring back utility power to the building.

n. Remove existing ATS and turn over to Owner.

o. Schedule ATS startup as soon as possible after successful installation.

p. Install new fencing.

7. – Generator #7. Building 597

a. Prior to release of submittals for review, Contractor shall field verify generator #7 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of existing conditions that might adversely impact the project phasing and schedule.

b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that openings and dimensions are correct, and product(s) match approved submittals.

c. Remove fencing as indicated.

d. Bring mobile generator #6 and terminate temporary power and control cables from it to existing ATS adjacent to existing generator to maintain emergency power connection to building.

e. Replace existing generator structural pad with new and install new generator and safety switch. Prior to installation, coordinate stub-up locations is adequate for new generator, and make necessary modifications on pad for proper installation of generator.

f. Install new underground wiring, conduits and pullboxes to the extent possible.

g. Shut down emergency power, only. Building shall be running on utility power through the existing ATSs but without emergency power. Connect new wiring to generator and new ATS. Verify proper phasing, terminate, torque, and provide ground connections.

Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).

h. Start up new generator and load bank test.

i. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized.

j. Conduct new Life Safety/Critical Panel rework indicated in drawings to the extent possible prior to utility power shut down.

k. Shutdown utility power to the building and switch over from existing to new ATS.

Power shutdown to building shall be minimized to the extent possible.

Abilene State Supported Living Center

Abilene, TX 79602

October 13, 2025

01 00 00 - 8 of 16

l. Finalize installation of Life Safety/Critical Panel rework.

m. Operate ATS manually to bring back utility power to the building.

n. Remove existing ATS and turn over to Owner.

o. Schedule ATS startup as soon as possible after successful installation.

p. Install new fencing.

8. – Generator #9. Building 652

a. Prior to release of submittals for review, Contractor shall field verify generator #9 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of existing conditions that might adversely impact the project phasing and schedule.

b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that openings and dimensions are correct, and product(s) match approved submittals.

c. Remove fencing as indicated.

d. Remove existing generator #9 and mount on a trailer and use as emergency power to this building. Generator #9 shall be relocated in add alternate and become generator #17 as indicated.

e. Replace existing generator structural pad with new and install new generator and docking station. Prior to installation, coordinate stub-up locations is adequate for new generator, and make necessary modifications on pad for proper installation of generator.

f. Install new underground wiring, conduits and pullboxes to the extent possible.

g. Shut down emergency power, only. Building shall be running on utility power through the existing ATSs but without emergency power. Connect new wiring to generator and new ATS. Verify proper phasing, terminate, torque, and provide ground connections.

Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).

h. Install new Electrical Distribution Panel EDP-9, step down transformer and associated safety disconnect switches and make connections to generator and building feeders.

i. Start up new generator and load bank test.

j. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized.

k. Conduct installation work associated with installation of MDP 652-1 & 2 indicated in drawings to the extent possible prior to utility power shut down.

l. Shutdown utility power to the building and switch over from existing to new ATS.

Power shutdown to building shall be minimized to the extent possible.

m. Finalize installation of MDP 652-1 & 2 work.

n. Operate ATS manually to bring back utility power to the building.

o. Remove existing ATS and turn over to Owner.

p. Schedule ATS startup as soon as possible after successful installation.

q. Install new fencing.

9. – Generator #10. Building 659 (add alt scope)

a. Prior to release of submittals for review, Contractor shall field verify generator #10 and existing ATSs configuration, conduit penetrations through slab and gear, condition and

Abilene State Supported Living Center

Abilene, TX 79602

October 13, 2025

01 00 00 - 9 of 16 location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of existing conditions that might adversely impact the project phasing and schedule.

b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that openings and dimensions are correct, and product(s) match approved submittals.

c. Install new generator and docking station on new structural pads. Prior to installation, coordinate stub-up locations is adequate for new generator, and make necessary modifications on pad for proper installation of generator.

d. Install new underground wiring, conduits and pullboxes to the extent possible.

e. Connect new wiring to generator and new ATS. Verify proper phasing, terminate, torque, and provide ground connections. Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).

f. Start up new generator and load bank test.

g. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized.

h. Shutdown utility power to the building and switch over from existing to new ATS.

Power shutdown to building shall be minimized to the extent possible.

i. Operate ATS manually to bring back utility power to the building.

j. Schedule ATS startup as soon as possible after successful installation.

k. Install new fencing.

10. – Generator #14. Building 656 (add alt scope)

a. Prior to release of submittals for review, Contractor shall field verify generator #14 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of existing conditions that might adversely impact the project phasing and schedule.

b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that openings and dimensions are correct, and product(s) match approved submittals.

c. Install new generator and docking station on new structural pads. Prior to installation, coordinate stub-up locations is adequate for new generator, and make necessary modifications on pad for proper installation of generator.

d. Install new underground wiring, conduits and pullboxes to the extent possible.

e. Connect new wiring to generator and new ATS. Verify proper phasing, terminate, torque, and provide ground connections. Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).

f. Start up new generator and load bank test.

g. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized.

h. Coordinate ahead of time with the utility company for installation of new power pole, rack, transformer and feeders to the extent possible in parallel with the work performed to this point without disrupting power to the buildings.

i. Shutdown utility power to the building and switch over from existing to new ATS.

Power shutdown to building shall be minimized to the extent possible.

j. Finalize installation of utility power.

k. Operate ATS manually to bring back utility power to the building.

Abilene State Supported Living Center

Abilene, TX 79602

October 13, 2025

01 00 00 - 10 of 16

l. Schedule ATS startup as soon as possible after successful installation.

m. Install new fencing.

11. – Generator #12. Buildings 547 (add alt scope)

a. Prior to release of submittals for review, Contractor shall field verify generator #12 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of existing conditions that might adversely impact the project phasing and schedule.

b. Remove existing generator #12 and turn over to Owner.

c. Existing ATS shall remain in place.

d. Existing utility power to the building shall remain.

e. Extend underground electrical service feeder from Generator #14.

f. Modify and rework existing ATS controls as required to activate new Generator #14 on loss of normal power.

12. – Generator #15. Building 641 (add alt scope)

a. Prior to release of submittals for review, Contractor shall field verify generator #15 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of existing conditions that might adversely impact the project phasing and schedule.

b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that openings and dimensions are correct, and product(s) match approved submittals.

c. Install new generator and docking station on new structural pads. Prior to installation, coordinate stub-up locations is adequate for new generator, and make necessary modifications on pad for proper installation of generator.

d. Install new underground wiring, conduits and pullboxes to the extent possible.

e. Connect new wiring to generator and new ATS. Verify proper phasing, terminate, torque, and provide ground connections. Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).

f. Start up new generator and load bank test.

g. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized.

h. Shutdown utility power to the building and switch over from existing to new ATS.

Power shutdown to building shall be minimized to the extent possible.

i. Operate ATS manually to bring back utility power to the building.

13. – Generator #16. Building 665 (add alt scope)

a. Prior to release of submittals for review, Contractor shall field verify generator #16 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of existing conditions that might adversely impact the project phasing and schedule.

b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that

Abilene State Supported Living Center

Abilene, TX 79602

October 13, 2025

01 00 00 - 11 of 16 openings and dimensions are correct, and product(s) match approved submittals.

c. Install new generator and docking station on new structural pads. Prior to installation, coordinate stub-up locations is adequate for new generator, and make necessary modifications on pad for proper installation of generator.

d. Install new underground wiring, conduits and pullboxes to the extent possible.

e. Connect new wiring to generator and new ATS. Verify proper phasing, terminate, torque, and provide ground connections. Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).

f. Start up new generator and load bank test.

g. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized.

h. Provide portable generator to maintain freezer and refrigerator on during power shutdown at all times. Coordinate with owner on any additional loads that might need to be kept on.

i. Shutdown utility power to the building and switch over from existing to new ATS.

Power shutdown to building shall be minimized to the extent possible.

j. Operate ATS manually to bring back utility power to the building.

k. Schedule ATS startup as soon as possible after successful installation.

l. Install new fencing.

14. – Generator #17. Building 664 (add alt scope)

a. Prior to release of submittals for review, Contractor shall field verify generator #17 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of existing conditions that might adversely impact the project phasing and schedule.

b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that openings and dimensions are correct, and product(s) match approved submittals.

c. Install generator (previously serving building 652 as generator #9) and docking station on new structural pads. Prior to installation, coordinate stub-up locations is adequate for new generator, and make necessary modifications on pad for proper installation of generator.

d. Install new underground wiring, conduits and pullboxes to the extent possible.

e. Connect new wiring to generator and new ATS. Verify proper phasing, terminate, torque, and provide ground connections. Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).

f. Start up new generator and load bank test.

g. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized.

h. Shutdown utility power to the building and switch over from existing to new ATS.

Power shutdown to building shall be minimized to the extent possible.

i. Operate ATS manually to bring back utility power to the building.

1.02 WORKING CONDITIONS

Abilene State Supported Living Center

Abilene, TX 79602

October 13, 2025

01 00 00 - 12 of 16

A. Work in buildings shall be as follows: To be coordinated and addressed by the Facility.

1.03 SPECIFIC SITE USE CONDITIONS

A. Use of the Site: Limit use of the premises to work in the buildings (according to the approved schedule) and storage and operations to the area designated for the Contractor.

Confine operations to areas within contract limits indicated. Do not disturb portions of the site beyond the areas in which the Work is indicated. Any areas sustaining damage during the project shall be restored, patched and/or repaired by the Contractor at the Contractor’s expense.

1. Owner Occupancy: Each building will be occupied during construction. The Facility will schedule Contractors access to those buildings.

2. The Contractor shall coordinate the use of the premises under the direction of the Facility.

3. Driveways and Entrances: Keep driveways and entrances serving the premises clear and available to the Owner, the Owner’s employees and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Vehicles are strictly prohibited on grass areas. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site. Contractor shall provide written schedule and notices must be made within five (5) days of any expected delivery that could interrupt the facility’s operations.

4. Contractor shall be responsible for the protection and safekeeping of products under this contract stored at the site.

B. Use of the Existing Building: Maintain the existing building in a weathertight condition throughout the construction period. Repair damage caused by construction operations.

Take all precautions necessary to protect the building during the construction period.

C. Full Owner Occupancy: Cooperate with the Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the work so as not to interfere with the Owner’s operations.

D. Clean and Repair:

1. The Contractor shall follow Owner’s clean work policy and shall include the removal of trash and demolished material from the building or work area at the end of each day and removal from the site once a week.

2. The Contractor shall be responsible for repairing adjacent construction and finishes damaged during demolition and/or modification.

1.04 WORK SCHEDULE:

A. Working hours for the Contractor will normally be between the hours of 8:00 a.m. and 5:00 p.m. excluding Saturdays, Sundays, and State holidays.

Abilene State Supported Living Center

Abilene, TX 79602

October 13, 2025

01 00 00 - 13 of 16

1.05 UTILITIES:

A. IDENTIFICATION: The Facility does not know the exact location of all utilities in the work area. The Contractor shall take reasonable precautions in determining the exact location of all existing utilities within the contract work area prior to any excavating, trenching, backfilling or disturbance. Upon request by the Contractor, the Facility will furnish all available information in its possession concerning utilities in the contract work area and assist the Contractor with location. However, the accuracy of the information provided by the Facility is not guaranteed and is only intended to provide some measure of assistance to the Contractor. In the event the Contractor identifies and/or uncovers unknown, un-shown utilities in the contract work area, which interfere with the newly proposed construction, the A/E and ODR shall be immediately notified for disposition. The Contractor shall furnish to the A/E red-lined as-built drawings clearly identifying the exact location of all utilities identified in the work area prior to project substantial completion inspection.

1. Any removal/relocation/reconnection of any communication or Cable TV device shall be coordinated in advance with the Facility. Communications and Cable TV devices to remain shall be protected as required when work proximity dictates. Contractor must exercise extreme caution and perform thorough coordination with the Facility when working around fiber and fiber networks to prevent damage as local resources are not available to make repairs.

B. INTERRUPTIONS: Planned Utility Outages: The Contractor shall coordinate all requests for utility outages with the Facility seven (7) calendar days prior to date of requested outage.

HVAC and electrical outages shall be held to a maximum duration of 2 hours unless otherwise approved in writing.

1. Unplanned Utility Outages (Accidental Disruption of Utilities): In the event of accidental disruption of any utility, the Contractor shall immediately notify the Facility of the unplanned outage. The Contractor shall immediately take every reasonable step to repair the damage in a manner acceptable to the Owner and shall restore the utility to full use as soon as practicable.

2. For all drinking water disruptions, the Contractor shall adhere to 30 TAC 290

Subchapter D paragraph 290.46(g). Submit a “Drinking Water Customer Service Inspection Checklist” prior to restoring drinking water service.

3. Any planned interruption of electrical power shall be addressed by the Contractor by providing temporary generator or generators as required by the building being worked on where interruption occurs. Emergency power shall be maintained to all owner occupied buildings.

C. USE AND AVAILABILITY: All reasonable quantities of existing utilities will be made available to the Contractor without charge. Proposed temporary connections must be coordinated with the Facility in advance of any connection. Any temporary connections or lines required shall be installed, maintained, and removed at the Contractor’s expense. Any damage associated with the use of these utilities shall be repaired and/or replaced in a manner satisfactory to the Owner at the Contractor's expense. Contractor shall always strive to conserve the electric, natural gas and water utilities at the Facility.

1. Prior to using any fire hydrant at the Facility, the Contractor must first request and coordinate, then furnish and install an approved Class III Back Flow Preventer (reduced pressure principle device) and screw type globe valve to be attached to the hydrant. The

Abilene State Supported Living Center

Abilene, TX 79602

October 13, 2025

01 00 00 - 14 of 16 backflow device and valve shall be properly supported to prevent damage to fire hydrant threads.

1.06 SAFETY AND HEALTH: See Article 7 of the UGCs/SGCs.

A. All Contractor operations shall be conducted and performed in accordance with Department of Labor, OSHA requirements found in 29 CFR 1910 and 29 CFR 1926. The Contractor shall comply with all mandatory requirements for lockout/tag out, hazard communication, fall protection, personnel protection equipment, scaffolding, powered construction equipment, and all project related safety and health requirements.

B. All companies who conduct business within the State of Texas must, in accordance with

Texas Worker’s Compensation laws (Texas House Bill 62), have an approved company safety policy and an Accident Prevention Plan. The plan, approved by the Texas Worker’s Compensation Commission (TWCC), shall be submitted with the mobilization submittal (see Section 01 30 00 of these specifications).

C. Welding, Cutting and Brazing: The Contractor shall provide the appropriate operable fire extinguisher. Fire extinguishers shall comply with NFPA 10. Contractor shall comply with OSHA STD29 CFR 1910.252 Welding, Cutting and Brazing (General Requirements).

D. Infection Control: Refer to the UGCs/SGCs Article 7.8. The Contractor shall complete the

Infection Control Permit for this project and submit with his mobilization submittal. A review of the work involved with this project has determined that it is a Type C Construction Activity affecting a low risk group requiring Class II Construction Precaution.

E. Guardrails, fences, barricades and warning lights or other illumination shall be provided in roadwork construction or near vehicular traffic areas. Fence shall be securely anchored with tension wires and posts as required to prevent sagging and located a minimum of 3 feet from the opening so as to prevent an individual, should they fall across the fencing, from falling into the opening. Holes shall also be covered, when not being worked in, with three quarter inch plywood or a metal grating that will prevent clients from entering the hole. See Article

7.6 of the UGCs/SGCs.

F. Confined Space Entry: All operations involving entry into confined spaces shall meet the requirements of OSHA 29 CFR 1910.146.

G. Personnel performing work shall be licensed by the State of Texas. A copy of the certificate shall be submitted. Prior to performing any work or disconnecting or shutting off any fire alarm, fire sprinkler system or duct system, the Facility shall be notified by the Contractor.

After completing work on any fire protection alarm system, or sprinkler or the proper completion documents and/or inspection and test documents, shall be completed and submitted to the Owner, that comply with NFPA 72, NFPA 13, NFPA 96, and/or NFPA 24 as applicable. Existing fire protection/detection notification devices to remain shall be fully protected during demolition and construction activities.

1.07 DISPOSITION OF WASTE, SALVAGE AND EXCESS MATERIALS:

A. The Contractor shall make waste determinations for all wastes generated in the performance of this contract, in accordance with the provisions set out in 40 Code of Federal Register (CFR) Part 261, at the time and point of generation. The Contractor shall properly sample, analyze, or by use of process knowledge classify all wastes in accordance with Title 30 Texas Administrative Code (TAC), Chapter 335, and

Abilene State Supported Living Center

Abilene, TX 79602

October 13, 2025

01 00 00 - 15 of 16

Subchapter R at no additional cost to the Owner. All non-hazardous wastes, special wastes, and hazardous wastes (including but not limited to construction debris, material containers, material residues and unwanted excess materials) resulting from the performance of work under this contract shall be removed from and disposed of off State property by the Contractor at no additional cost to the Owner and in accordance with all applicable Federal, State, and local laws, rules and regulations. Under no circumstances shall the Contractor dispose of wastes or excess material in trash dumpsters, storm sewers, sanitary sewers, creeks, streams or other property of the State.

B. Dumping/cleaning out of concrete trucks on State property is prohibited. Concrete truck chutes only may be rinsed at the construction site. Wastewater and concrete from this rinse shall be collected in a high-density polyethylene (HDPE) plastic-lined box or pit provided by the Contractor at the site. At the end of pouring operations, the Contractor shall excavate all the waste and liner and properly dispose of same. The pit shall be completely backfilled and the site restored to original conditions.

C. Recycling is highly encouraged and shall be employed to the maximum extent practicable. Facility requests boilers and domestic water storage tanks be salvaged.

Location to be determined by Facility at time of Pre-Construction Meeting.

D. All equipment and materials to be removed from the project site not specifically identified for turn-in to the Owner or as requested by Facility, shall become the property of the Contractor upon issuance of the NTP. The Contractor shall turn-in all materials specifically designated for turn-in to the Owner or as requested by Facility, shall be delivered to a location as designated by the Facility. Following is a list of equipment or materials to be turned-in:

1. Generators as noted

2. ATS

3. Circuit Breakers

4. Electrical Panels

1.08 TESTING:

A. Costs of all tests, both those as listed and those as required by referenced Codes, shall be provided by and at the Contractor's expense, unless specifically indicated as being performed by the Owner elsewhere in the contract documents. The Contractor shall schedule all tests and notify the ODR, the A/E, and the Facility in advance in a timely manner prior to any required testing.