Attach H2_Specs.pdf
PDF 3 MB Posted
- Solicitation number
- HHS0016014v2
- Issued by
- Taylor County, Texas
About this file
Summary
This is a comprehensive project specifications document prepared by ACR Engineering, Inc. for the Texas Health and Human Services Commission (HHSC) regarding generator replacement work at the Abilene State Supported Living Center located at 2501 Maple Street in Abilene, Texas (HHS Project No. 25-101-ABL). The project requires a General Contractor to furnish all labor, materials, equipment, supervision, quality control, and services necessary to replace emergency generators across 24 buildings in the base bid, with additional alternate work in Buildings 547, 656, 659, 641, 665, and 664. The scope encompasses demolition of existing generators, installation of new emergency generators with complete electrical systems including conduits, breakers, disconnects, automatic transfer switches (ATS), fire alarm modifications, fencing, docking stations, power panels, and utility connections as shown on contract drawings. The phasing plan requires installation to be performed in a specific 14-phase sequence with minimal power interruptions to maintain facility operations during construction. Contractors must attend a mandatory site visit on December 8 or 9, 2025, at 10:00 a.m. Central Time, with an optional pre-proposal webinar on December 4, 2025. Proposal submissions are due January 8, 2026, at 10:30 a.m. Central Time, with public proposal opening scheduled for January 13, 2026. The anticipated Notice of Award is February 2026, with a projected contract start date in March 2026.
The estimated project value is approximately $14,000,000 under a fixed-price contract with no renewal options. Awards will be determined using best value selection methodology with evaluation criteria including Relevant Construction Services Ability and Experience (30%), Quality and Safety Programs (5%), Proposed Methodology (25%), and Pricing (40%). Contractors must demonstrate a minimum of five years in business or have principals with equivalent ownership or executive management experience in similar construction services. A Historically Underutilized Business (HUB) Subcontracting Plan is required due to the contract value exceeding $100,000. Respondents must submit three project references of comparable scope and complexity, a letter of intent from a surety company demonstrating financial solvency and bonding capacity, and a security bond of at least 5 percent of the total proposed cost. For contracts valued at $1 million or more, a Disclosure of Interested Parties form (TEC Form 1295) must be submitted. Winners must be currently authorized to do business in Texas and maintain good standing certification from the Texas Comptroller's Office. The work schedule operates between 8:00 a.m. and 5:00 p.m., excluding Saturdays, Sundays, and state holidays, and all work must be completed within a specified calendar period from the Notice to Proceed.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment H-2 Project Specifications
GENERATOR REPLACEMENT
PROJECT
ABILENE STATE SUPPORTED LIVING CENTER
2501 MAPLE ST,
ABILENE, TX 79602
HHS PROJECT NO. 25-101-ABL
10/13/25
Prepared by:
ACR Engineering, Inc
3001 S Lamar Blvd, Ste 210
Austin, Texas 78704
HHS Project No. 25-101-ABL
Generator Replacement
Page I of I
TABLE OF CONTENTS
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
DIVISION 01 – GENERAL REQUIREMENTS
01 0000 SPECIAL CONDITIONS
01 3000 SUBMITTALS, SHOP DRAWINGS/SAMPLES & SCHEDULES
A. CONTRACT PROGRESS SCHEDULE
B. SHOP DRAWINGS LOG
C. SCHEDULE OF VALUES
01 4000 REFERENCE STANDARDS AND CODES
01 5000 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
01 7000 CLOSEOUT
DIVISION 02 – NOT USED
DIVISION 03 – CONCRETE
03 1000 CONCRETE FORMING
03 2000 CONCRETE REINFORCING
03 3000 CONCRETE CAST-IN PLACE
DIVISION 04 THRU 25 – NOT USED
DIVISION 26 – ELECTRICAL
260010 SUMMARY OF ELECTRICAL WORK
260500 COMMON WORK RESULTS FOR ELECTRICAL
260523 CABLE, WIRE, AND CONNECTORS, 600 VOLT OR LESS
260526 GROUNDING
260533 RACEWAYS, CONDUITS, AND BOXES
260534 THROUGH PENETRATION FIRESTOPPING FOR ELECTRICAL SYSTEMS
261219 TRANSFORMER, PAD MOUNT (OIL COOLED)
262413 SWITCHBOARDS, 600 VOLT AND LESS
262416.11 DISTRIBUTION PANELBOARDS
262416.12 BRANCH CIRCUIT PANELBOARDS
262553 ELECTRICAL IDENTIFICATION
262726 WIRING DEVICES AND FLOOR BOXES
263213.13 ENGINE GENERATOR SYSTEM
263240 DOCKING STATION
263600 AUTOMATIC TRANSFER SWITCH
DIVISION 28 – electronic safety ad security
284600 FIRE ALARM AND SMOKE DETECTION SYSTEM
Special Conditions
Abilene State Supported Living Center
Abilene, TX 79602
October 13, 2025
01 00 00 - 1 of 16
SECTION 01 00 00
SPECIAL CONDITIONS
1.01 SCOPE:
A. The work covered by this project consists of the Contractor furnishing all layout, survey, plant, labor, supervision, quality control, materials, equipment, machines, tools, appliances, services, supplies, and incidentals and of performing all operations in connection with this project for each generator replacement, in strict accordance with these plans, specifications, and the contract documents.
BASE BID:
Item A: Remove and replace existing generators in Buildings 596, 633, 634, 635, 636, 645, 646, 648, 650, 651, 637, 638, 639, 640, 597, 652, 669, 670, 671, 672, 673, 674, 675, and 676.
The work included in this Bid includes furnishing all labor and materials for the removal of existing emergency generators and installation of new emergency generators in same location. Installation of additional new generators will be indicated on the contract drawings. Installation shall include all components, complete with all tests and certifications required for operational emergency generators. Scope shall include demolition, electrical installation, wiring, conduits, breakers, disconnects, fire alarm modifications and re-certifications, fencing, docking stations, power panels, integrated power centers, utility connections, etc. as shown on contract drawings.
ADD ALTERNATE:
Building 664 The work included in this Bid includes furnishing all labor and materials for the installation of relocated existing emergency generator and all piping etc. as shown.
Installation shall include all components, complete with all tests and certifications required for operational emergency generators. Scope shall include demolition, electrical installation, wiring, conduits, breakers, disconnects, fire alarm modifications and re-certifications, fencing, concrete pads, docking stations, power panels, integrated power centers, utility connections, etc. as shown on contract drawings.
Buildings 547, 656, 659, 641 and 665.
The work in this bid includes furnishing all labor and materials for the installation of new emergency generator and accessories, etc. Installation shall include all components, complete with all tests and certifications required for operational emergency generators.
Scope shall include demolition, electrical installation, wiring, conduits, breakers, disconnects, fire alarm modifications and re-certifications, fencing, concrete pads, docking station, power panels, utility connections, etc as shown on Contract Drawings.
PHASING
Installation shall be performed according to Preliminary Schedule with minimal impact and all construction complete within the submitted calendar days from date of Notice to Proceed. Schedule will be evaluated as part of the contractor’s proposal. Final scheduling shall be as scheduled with HHS and Abilene Facility based on availability of scheduled building.
Abilene State Supported Living Center
Abilene, TX 79602
October 13, 2025
01 00 00 - 2 of 16
1. Phasing Plan: The Facility will be fully occupied and in operation for the duration of the contract performance period. The Contractor shall submit for approval a detailed phasing plan to minimize duration of power interruption. Proposed phasing plan is described below, and shall be conducted in the numbering order as follows:
1. – Generator #5. Buildings 650 and 651.
a. Prior to release of submittals for review, Contractor shall field verify generator #5 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of existing conditions that might adversely impact the project phasing and schedule.
b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that openings and dimensions are correct, and product(s) match approved submittals.
c. Remove fencing as indicated.
d. Remove existing generator #5 and turn over to Owner.
e. Deenergize and terminate existing generator cables and conduits.
f. Power new generator concrete pad and prepare conduit stub-ups.
g. Install new generator at location as indicated.
The work described below can happen simultaneously at buildings 650 and 651, or one at the time:
h. Install new underground wiring, conduits and pullboxes to the extent possible
i. Shut down emergency power, only. Buildings shall be running on utility power through the existing ATSs but without emergency power. Connect new wiring to generator and new ATSs. Verify proper phasing, terminate, torque, and provide ground connections.
Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).
j. Start up new generator and load bank test.
k. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized
l. Conduct new Life Safety/Critical Panel rework indicated in drawings to the extent possible prior to utility power shut down.
m. Shutdown utility power to the building and switch over from existing to new ATSs.
Power shutdown to building 651 shall be minimized to the extent possible since it is an active certified home.
n. Finalize Life Safety/Critical Panel Rework indicated in drawings.
o. Operate ATSs manually to bring back utility power to the building.
p. Remove existing ATSs and turn over to Owner.
q. Schedule ATSs startup as soon as possible after successful installation.
r. Install new fencing.
2. – Generator #6. Buildings 637, 638, 639 and 640.
a. Prior to release of submittals for review, Contractor shall field verify generator #6 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of existing conditions that might adversely impact the project phasing and schedule.
Abilene State Supported Living Center
Abilene, TX 79602
October 13, 2025
01 00 00 - 3 of 16
b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that openings and dimensions are correct, and product(s) match approved submittals.
c. Remove fencing as indicated.
d. Remove existing generator #6 and mount on a trailer (this generator shall be reused as a mobile generator to feed temporary emergency power to this and buildings served by generators 1, 3, 4, 7, 10, 15, 16 & 17. Turn over generator to Owner once it is no longer needed for temporary power).
e. Terminate temporary power and control cables from mobile generator to existing Emergency Panel #2 adjacent to existing generator to maintain emergency power connection to all buildings.
f. Install new generator at location of existing pad, as indicated. Prior to installation, coordinate stub-up locations is adequate for new generator, and make necessary modifications on pad for proper installation of generator.
The work described below can happen simultaneously in buildings 637, 638, 639 and 640, or one at the time:
g. Install new underground wiring, conduits and pullboxes to the extent possible.
h. Shut down emergency power, only. Buildings shall be running on utility power through the existing ATSs but without emergency power. Connect new wiring to generator and new ATSs. Verify proper phasing, terminate, torque, and provide ground connections.
Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).
i. Install new Electrical Distribution Panel EDP-6 and make connections to generator and buildings feeders.
j. Start up new generator and load bank test.
k. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized.
l. Coordinate ahead of time with the utility company for installation of new utility pole and associated feeders to the extent possible in parallel with the work performed to this point without disrupting power to the buildings.
m. Install new building Main Distribution Panels “MDP-637, 638, 639 & 640 and associated scope including conduit and conductors to the extent possible prior to utility power shut down.
n. Shutdown utility power to the building(s) and switch over from existing to new ATS(s). Power shutdown to building 638 and 640 shall be minimized to the extent possible since it is an active certified home.
o. Finalize installation of new building Main Distribution Panels “MDP-637, 638, 639 & 640 and associated conduit and conductors.
p. Finalize installation of new utility service.
q. Operate ATSs manually to bring back utility power to the building.
r. Remove existing ATSs and turn over to Owner.
s. Schedule ATSs startup as soon as possible after successful installation.
t. Install new fencing.
3. – Generator #3. Buildings 633, 634, 635 and 636.
a. Prior to release of submittals for review, Contractor shall field verify generator #3 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, Abilene State Supported Living Center
Abilene, TX 79602
October 13, 2025
01 00 00 - 4 of 16
b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that openings and dimensions are correct, and product(s) match approved submittals.
c. Remove fencing as indicated.
d. Bring mobile generator #6 and terminate temporary power and control cables from it to existing ATS adjacent to existing generator to maintain emergency power connection to all buildings.
e. Install new generator at location of existing pad, as indicated. Prior to installation, coordinate stub-up locations is adequate for new generator, and make necessary
The work described below can happen simultaneously in buildings 633, 634, 635 and 636, or one at the time:
f. Install new underground wiring, conduits and pullboxes to the extent possible.
g. Shut down emergency power, only. Buildings shall be running on utility power through the existing ATSs but without emergency power. Connect new wiring to generator and new ATSs. Verify proper phasing, terminate, torque, and provide ground connections.
Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).
h. Install new Electrical Distribution Panel EDP-3 and make connections to generator and buildings feeders.
i. Start up new generator and load bank test.
j. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized.
k. Coordinate ahead of time with the utility company for installation of new feeders to the extent possible in parallel with the work performed to this point without disrupting power to the buildings.
l. Install new building Main Distribution Panels “MDP-633, 634, 635 and 636 and associated scope including conduit and conductors to the extent possible prior to utility power shut down.
m. Shutdown utility power to the building(s) and switch over from existing to new ATS(s). Power shutdown to building 633, 635 and 636 shall be minimized to the extent possible since it is an active certified home.
n. Finalize installation of new building Main Distribution Panels “MDP-633, 634, 635 and 636 and associated conduit and conductors.
o. Finalize installation of new utility service.
p. Operate ATSs manually to bring back utility power to the building.
q. Remove existing ATSs and turn over to Owner.
r. Schedule ATSs startup as soon as possible after successful installation.
s. Install new fencing.
4. – Generator #11. Buildings 669, 670, 671, 672, 67., 674, 675 and 676
a. Prior to release of submittals for review, Contractor shall field verify generator #11 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, Abilene State Supported Living Center
Abilene, TX 79602
October 13, 2025
01 00 00 - 5 of 16
b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that openings and dimensions are correct, and product(s) match approved submittals.
c. Remove fencing as indicated.
d. Remove existing generator #11 and mount on a trailer to feed temporary emergency power to this building. Turn over generator to Owner once work is complete.
e. Replace existing generator structural pad with new and install new generator. Prior to installation, coordinate stub-up locations is adequate for new generator, and make necessary modifications on pad for proper installation of generator.
The work described below can happen simultaneously in buildings 669, 670, 671, 672, 67., 674, 675 and 676, or one at the time:
the existing ATSs but without emergency power. Connect new wiring to generator and new ATSs. Verify proper phasing, terminate, torque, and provide ground connections.
Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).
h. Install new Electrical Distribution Panel EDP-11 and make connections to generator and buildings feeders.
i. Start up new generator and load bank test.
j. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized.
k. Shutdown utility power to the building(s) and switch over from existing to new
ATS(s). Power shutdown to all buildings shall be minimized to the extent possible, with building 670 being the less critical.
l. Operate ATSs manually to bring back utility power to the building.
m. Remove existing ATSs and turn over to Owner.
n. Schedule ATSs startup as soon as possible after successful installation.
o. Install new fencing.
5. – Generator #4. Buildings 645, 646 and 648
a. Prior to release of submittals for review, Contractor shall field verify generator #4 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of existing conditions that might adversely impact the project phasing and schedule.
b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that openings and dimensions are correct, and product(s) match approved submittals.
c. Remove fencing as indicated.
d. Bring mobile generator #6 and terminate temporary power and control cables from it to existing ATS adjacent to existing generator to maintain emergency power connection to all buildings.
e. Replace existing generator structural pad with new and install new generator and docking station. Prior to installation, coordinate stub-up locations is adequate for new generator, and make necessary modifications on pad for proper installation of generator.
Abilene State Supported Living Center
Abilene, TX 79602
October 13, 2025
01 00 00 - 6 of 16
The work described below can happen simultaneously in buildings 645, 646 and 648, or one at the time:
the existing ATSs but without emergency power. Connect new wiring to generator and new ATSs. Verify proper phasing, terminate, torque, and provide ground connections.
Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).
h. Install new Electrical Distribution Panel EDP-4 and make connections to generator and buildings feeders.
i. Start up new generator and load bank test.
j. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized.
k. Conduct new Life Safety/Critical Panel rework indicated in drawings to the extent possible prior to utility power shut down.
l. Shutdown utility power to the building(s) and switch over from existing to new
ATS(s). Power shutdown to all buildings shall be minimized to the extent possible.
m. Finalize Life Safety/Critical Panel rework indicated in drawings.
n. Operate ATSs manually to bring back utility power to the building.
o. Remove existing ATSs and turn over to Owner.
p. Schedule ATSs startup as soon as possible after successful installation.
q. Install new fencing.
6. – Generator #1. Building 596
a. Prior to release of submittals for review, Contractor shall field verify generator #1 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of existing conditions that might adversely impact the project phasing and schedule.
b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that openings and dimensions are correct, and product(s) match approved submittals.
c. Remove fencing as indicated.
d. Bring mobile generator #6 and terminate temporary power and control cables from it to existing ATS adjacent to existing generator to maintain emergency power connection to building.
e. Replace existing generator structural pad with new and install new generator and docking station. Prior to installation, coordinate stub-up locations is adequate for new generator, and make necessary modifications on pad for proper installation of generator.
f. Install new underground wiring, conduits and pullboxes to the extent possible.
g. Shut down emergency power, only. Building shall be running on utility power through the existing ATSs but without emergency power. Connect new wiring to generator and new ATS. Verify proper phasing, terminate, torque, and provide ground connections.
Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).
h. Start up new generator and load bank test.
i. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized.
Abilene State Supported Living Center
Abilene, TX 79602
October 13, 2025
01 00 00 - 7 of 16
j. Conduct new Life Safety/Critical Panel rework indicated in drawings to the extent possible prior to utility power shut down.
k. Shutdown utility power to the building and switch over from existing to new ATS.
Power shutdown to building shall be minimized to the extent possible.
l. Finalize installation of Life Safety/Critical Panel rework.
m. Operate ATS manually to bring back utility power to the building.
n. Remove existing ATS and turn over to Owner.
o. Schedule ATS startup as soon as possible after successful installation.
p. Install new fencing.
7. – Generator #7. Building 597
a. Prior to release of submittals for review, Contractor shall field verify generator #7 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of existing conditions that might adversely impact the project phasing and schedule.
b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that openings and dimensions are correct, and product(s) match approved submittals.
c. Remove fencing as indicated.
d. Bring mobile generator #6 and terminate temporary power and control cables from it to existing ATS adjacent to existing generator to maintain emergency power connection to building.
e. Replace existing generator structural pad with new and install new generator and safety switch. Prior to installation, coordinate stub-up locations is adequate for new generator, and make necessary modifications on pad for proper installation of generator.
f. Install new underground wiring, conduits and pullboxes to the extent possible.
g. Shut down emergency power, only. Building shall be running on utility power through the existing ATSs but without emergency power. Connect new wiring to generator and new ATS. Verify proper phasing, terminate, torque, and provide ground connections.
Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).
h. Start up new generator and load bank test.
i. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized.
j. Conduct new Life Safety/Critical Panel rework indicated in drawings to the extent possible prior to utility power shut down.
k. Shutdown utility power to the building and switch over from existing to new ATS.
Power shutdown to building shall be minimized to the extent possible.
l. Finalize installation of Life Safety/Critical Panel rework.
m. Operate ATS manually to bring back utility power to the building.
n. Remove existing ATS and turn over to Owner.
o. Schedule ATS startup as soon as possible after successful installation.
p. Install new fencing.
8. – Generator #9. Building 652
a. Prior to release of submittals for review, Contractor shall field verify generator #9 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, Abilene State Supported Living Center
Abilene, TX 79602
October 13, 2025
01 00 00 - 8 of 16
b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that openings and dimensions are correct, and product(s) match approved submittals.
c. Remove fencing as indicated.
d. Remove existing generator #9 and mount on a trailer and use as emergency power to this building. Generator #9 shall be relocated in add alternate and become generator #17 as indicated.
e. Replace existing generator structural pad with new and install new generator and docking station. Prior to installation, coordinate stub-up locations is adequate for new generator, and make necessary modifications on pad for proper installation of generator.
f. Install new underground wiring, conduits and pullboxes to the extent possible.
g. Shut down emergency power, only. Building shall be running on utility power through the existing ATSs but without emergency power. Connect new wiring to generator and new ATS. Verify proper phasing, terminate, torque, and provide ground connections.
Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).
h. Install new Electrical Distribution Panel EDP-9, step down transformer and associated safety disconnect switches and make connections to generator and building feeders.
i. Start up new generator and load bank test.
j. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized.
k. Conduct installation work associated with installation of MDP 652-1 & 2 indicated in drawings to the extent possible prior to utility power shut down.
l. Shutdown utility power to the building and switch over from existing to new ATS.
Power shutdown to building shall be minimized to the extent possible.
m. Finalize installation of MDP 652-1 & 2 work.
n. Operate ATS manually to bring back utility power to the building.
o. Remove existing ATS and turn over to Owner.
p. Schedule ATS startup as soon as possible after successful installation.
q. Install new fencing.
9. – Generator #10. Building 659 (add alt scope)
a. Prior to release of submittals for review, Contractor shall field verify generator #10 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of existing conditions that might adversely impact the project phasing and schedule.
b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that openings and dimensions are correct, and product(s) match approved submittals.
c. Install new generator and docking station on new structural pads. Prior to installation, coordinate stub-up locations is adequate for new generator, and make necessary
d. Install new underground wiring, conduits and pullboxes to the extent possible.
Abilene State Supported Living Center
Abilene, TX 79602
October 13, 2025
01 00 00 - 9 of 16
e. Connect new wiring to generator and new ATS. Verify proper phasing, terminate, torque, and provide ground connections. Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).
f. Start up new generator and load bank test.
g. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized.
h. Shutdown utility power to the building and switch over from existing to new ATS.
Power shutdown to building shall be minimized to the extent possible.
i. Operate ATS manually to bring back utility power to the building.
j. Schedule ATS startup as soon as possible after successful installation.
k. Install new fencing.
10. – Generator #14. Building 656 (add alt scope)
a. Prior to release of submittals for review, Contractor shall field verify generator #14 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of existing conditions that might adversely impact the project phasing and schedule.
b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that openings and dimensions are correct, and product(s) match approved submittals.
c. Install new generator and docking station on new structural pads. Prior to installation, coordinate stub-up locations is adequate for new generator, and make necessary modifications on pad for proper installation of generator.
d. Install new underground wiring, conduits and pullboxes to the extent possible.
e. Connect new wiring to generator and new ATS. Verify proper phasing, terminate, torque, and provide ground connections. Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).
f. Start up new generator and load bank test.
g. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized.
h. Coordinate ahead of time with the utility company for installation of new power pole, rack, transformer and feeders to the extent possible in parallel with the work performed to this point without disrupting power to the buildings.
i. Shutdown utility power to the building and switch over from existing to new ATS.
Power shutdown to building shall be minimized to the extent possible.
j. Finalize installation of utility power.
k. Operate ATS manually to bring back utility power to the building.
l. Schedule ATS startup as soon as possible after successful installation.
m. Install new fencing.
11. – Generator #12. Buildings 547 (add alt scope)
a. Prior to release of submittals for review, Contractor shall field verify generator #12 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of
b. Remove existing generator #12 and turn over to Owner.
Abilene State Supported Living Center
Abilene, TX 79602
October 13, 2025
01 00 00 - 10 of 16
c. Existing ATS shall remain in place.
d. Existing utility power to the building shall remain.
e. Extend underground electrical service feeder from Generator #14.
f. Modify and rework existing ATS controls as required to activate new Generator #14 on loss of normal power.
12. – Generator #15. Building 641 (add alt scope)
a. Prior to release of submittals for review, Contractor shall field verify generator #15 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of existing conditions that might adversely impact the project phasing and schedule.
b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that openings and dimensions are correct, and product(s) match approved submittals.
c. Install new generator and docking station on new structural pads. Prior to installation, coordinate stub-up locations is adequate for new generator, and make necessary modifications on pad for proper installation of generator.
d. Install new underground wiring, conduits and pullboxes to the extent possible.
e. Connect new wiring to generator and new ATS. Verify proper phasing, terminate, torque, and provide ground connections. Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).
f. Start up new generator and load bank test.
g. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized.
h. Shutdown utility power to the building and switch over from existing to new ATS.
Power shutdown to building shall be minimized to the extent possible.
i. Operate ATS manually to bring back utility power to the building.
13. – Generator #16. Building 665 (add alt scope)
a. Prior to release of submittals for review, Contractor shall field verify generator #16 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of existing conditions that might adversely impact the project phasing and schedule.
b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that openings and dimensions are correct, and product(s) match approved submittals.
c. Install new generator and docking station on new structural pads. Prior to installation, coordinate stub-up locations is adequate for new generator, and make necessary modifications on pad for proper installation of generator.
d. Install new underground wiring, conduits and pullboxes to the extent possible.
e. Connect new wiring to generator and new ATS. Verify proper phasing, terminate, torque, and provide ground connections. Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).
f. Start up new generator and load bank test.
Abilene State Supported Living Center
Abilene, TX 79602
October 13, 2025
01 00 00 - 11 of 16
g. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized.
h. Provide portable generator to maintain freezer and refrigerator on during power shutdown at all times. Coordinate with owner on any additional loads that might need to be kept on.
i. Shutdown utility power to the building and switch over from existing to new ATS.
Power shutdown to building shall be minimized to the extent possible.
j. Operate ATS manually to bring back utility power to the building.
k. Schedule ATS startup as soon as possible after successful installation.
l. Install new fencing.
14. – Generator #17. Building 664 (add alt scope)
a. Prior to release of submittals for review, Contractor shall field verify generator #17 and existing ATSs configuration, conduit penetrations through slab and gear, condition and location of pullboxes, access and location and condition of underground circuits, condition and length of feeders to be connected and/or replaced, and any other aspect of existing conditions that might adversely impact the project phasing and schedule.
b. Upon delivery of new electrical gear to the site conduct a detailed inspection to verify that all required components are in place, ampacity and voltage ratings are correct, that openings and dimensions are correct, and product(s) match approved submittals.
c. Install generator (previously serving building 652 as generator #9) and docking station on new structural pads. Prior to installation, coordinate stub-up locations is adequate for new generator, and make necessary modifications on pad for proper installation of generator.
d. Install new underground wiring, conduits and pullboxes to the extent possible.
e. Connect new wiring to generator and new ATS. Verify proper phasing, terminate, torque, and provide ground connections. Fill fuel tank with diesel fuel. Do NOT make any connections to existing building electrical gear yet (main distribution panel, existing ATS, etc.).
f. Start up new generator and load bank test.
g. Request and provide inspection and start-up procedure by manufacturer’s representative to certify that generator is ready to be energized.
h. Shutdown utility power to the building and switch over from existing to new ATS.
Power shutdown to building shall be minimized to the extent possible.
i. Operate ATS manually to bring back utility power to the building.
1.02 WORKING CONDITIONS
A. Work in buildings shall be as follows: To be coordinated and addressed by the Facility.
1.03 SPECIFIC SITE USE CONDITIONS
A. Use of the Site: Limit use of the premises to work in the buildings (according to the approved schedule) and storage and operations to the area designated for the Contractor.
Confine operations to areas within contract limits indicated. Do not disturb portions of the site beyond the areas in which the Work is indicated. Any areas sustaining damage during the project shall be restored, patched and/or repaired by the Contractor at the Contractor’s expense.
Abilene State Supported Living Center
Abilene, TX 79602
October 13, 2025
01 00 00 - 12 of 16
1. Owner Occupancy: Each building will be occupied during construction and as one or two buildings are scheduled for construction work. The Facility will schedule Contractors access to those buildings.
2. The Contractor shall coordinate the use of the premises under the direction of the
Facility.
3. Driveways and Entrances: Keep driveways and entrances serving the premises clear and available to the Owner, the Owner’s employees and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Vehicles are strictly prohibited on grass areas. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site. Contractor shall provide written schedule and notices must be made within five (5) days of any expected delivery that could interrupt the facility’s operations.
4. Contractor shall be responsible for the protection and safekeeping of products under this contract stored at the site.
B. Use of the Existing Building: Maintain the existing building in a weathertight condition throughout the construction period. Repair damage caused by construction operations.
Take all precautions necessary to protect the building during the construction period.
C. Full Owner Occupancy: Cooperate with the Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the work so as not to interfere with the Owner’s operations.
D. Clean and Repair:
1. The Contractor shall follow Owner’s clean work policy and shall include the removal of trash and demolished material from the building or work area at the end of each day and removal from the site once a week.
2. The Contractor shall be responsible for repairing adjacent construction and finishes damaged during demolition and/or modification.
1.04 WORK SCHEDULE:
A. Working hours for the Contractor will normally be between the hours of 8:00 a.m. and 5:00 p.m. excluding Saturdays, Sundays, and State holidays.
Abilene State Supported Living Center
Abilene, TX 79602
October 13, 2025
01 00 00 - 13 of 16
1.05 UTILITIES:
A. IDENTIFICATION: The Facility does not know the exact location of all utilities in the work area. The Contractor shall take reasonable precautions in determining the exact location of all existing utilities within the contract work area prior to any excavating, trenching, backfilling or disturbance. Upon request by the Contractor, the Facility will furnish all available information in its possession concerning utilities in the contract work area and assist the Contractor with location. However, the accuracy of the information provided by the Facility is not guaranteed and is only intended to provide some measure of assistance to the Contractor. In the event the Contractor identifies and/or uncovers unknown, un-shown utilities in the contract work area, which interfere with the newly proposed construction, the A/E and ODR shall be immediately notified for disposition. The Contractor shall furnish to the A/E red-lined as-built drawings clearly identifying the exact location of all utilities identified in the work area prior to project substantial completion inspection.
1. Any removal/relocation/reconnection of any communication or Cable TV device shall be coordinated in advance with the Facility. Communications and Cable TV devices to remain shall be protected as required when work proximity dictates. Contractor must exercise extreme caution and perform thorough coordination with the Facility when working around fiber and fiber networks to prevent damage as local resources are not available to make repairs.
B. INTERRUPTIONS: Planned Utility Outages: The Contractor shall coordinate all requests for utility outages with the Facility seven (7) calendar days prior to date of requested outage.
HVAC and electrical outages shall be held to a maximum duration of 2 hours unless otherwise approved in writing.
1. Unplanned Utility Outages (Accidental Disruption of Utilities): In the event of accidental disruption of any utility, the Contractor shall immediately notify the Facility of the unplanned outage. The Contractor shall immediately take every reasonable step to repair the damage in a manner acceptable to the Owner and shall restore the utility to full use as soon as practicable.
2. For all drinking water disruptions, the Contractor shall adhere to 30 TAC 290
Subchapter D paragraph 290.46(g). Submit a “Drinking Water Customer Service Inspection Checklist” prior to restoring drinking water service.
3. Any planned interruption of electrical power shall be addressed by the Contractor by providing temporary generator or generators as required by the building being worked on where interruption occurs. Emergency power shall be maintained to all owner occupied buildings.
C. USE AND AVAILABILITY: All reasonable quantities of existing utilities will be made available to the Contractor without charge. Proposed temporary connections must be coordinated with the Facility in advance of any connection. Any temporary connections or lines required shall be installed, maintained, and removed at the Contractor’s expense. Any damage associated with the use of these utilities shall be repaired and/or replaced in a manner satisfactory to the Owner at the Contractor's expense. Contractor shall always strive to conserve the electric, natural gas and water utilities at the Facility.
1. Prior to using any fire hydrant at the Facility, the Contractor must first request and coordinate, then furnish and install an approved Class III Back Flow Preventer (reduced pressure principle device) and screw type globe valve to be attached to the hydrant. The
Abilene State Supported Living Center
Abilene, TX 79602
October 13, 2025
01 00 00 - 14 of 16 backflow device and valve shall be properly supported to prevent damage to fire hydrant threads.
1.06 SAFETY AND HEALTH: See Article 7 of the UGCs/SGCs.
A. All Contractor operations shall be conducted and performed in accordance with Department of Labor, OSHA requirements found in 29 CFR 1910 and 29 CFR 1926. The Contractor shall comply with all mandatory requirements for lockout/tag out, hazard communication, fall protection, personnel protection equipment, scaffolding, powered construction equipment, and all project related safety and health requirements.
B. All companies who conduct business within the State of Texas must, in accordance with
Texas Worker’s Compensation laws (Texas House Bill 62), have an approved company safety policy and an Accident Prevention Plan. The plan, approved by the Texas Worker’s Compensation Commission (TWCC), shall be submitted with the mobilization submittal (see Section 01 30 00 of these specifications).
C. Welding, Cutting and Brazing: The Contractor shall provide the appropriate operable fire extinguisher. Fire extinguishers shall comply with NFPA 10. Contractor shall comply with OSHA STD29 CFR 1910.252 Welding, Cutting and Brazing (General Requirements).
D. Infection Control: Refer to the UGCs/SGCs Article 7.8. The Contractor shall complete the
Infection Control Permit for this project and submit with his mobilization submittal. A review of the work involved with this project has determined that it is a Type C Construction Activity affecting a low risk group requiring Class II Construction Precaution.
E. Guardrails, fences, barricades and warning lights or other illumination shall be provided in roadwork construction or near vehicular traffic areas. Fence shall be securely anchored with tension wires and posts as required to prevent sagging and located a minimum of 3 feet from the opening so as to prevent an individual, should they fall across the fencing, from falling into the opening. Holes shall also be covered, when not being worked in, with three quarter inch plywood or a metal grating that will prevent clients from entering the hole. See Article
7.6 of the UGCs/SGCs.
F. Confined Space Entry: All operations involving entry into confined spaces shall meet the requirements of OSHA 29 CFR 1910.146.
G. Personnel performing work shall be licensed by the State of Texas. A copy of the certificate shall be submitted. Prior to performing any work or disconnecting or shutting off any fire alarm, fire sprinkler system or duct system, the Facility shall be notified by the Contractor.
After completing work on any fire protection alarm system, or sprinkler or the proper completion documents and/or inspection and test documents, shall be completed and submitted to the Owner, that comply with NFPA 72, NFPA 13, NFPA 96, and/or NFPA 24 as applicable. Existing fire protection/detection notification devices to remain shall be fully protected during demolition and construction activities.
1.07 DISPOSITION OF WASTE, SALVAGE AND EXCESS MATERIALS:
A. The Contractor shall make waste determinations for all wastes generated in the performance of this contract, in accordance with the provisions set out in 40 Code of Federal Register (CFR) Part 261, at the time and point of generation. The Contractor shall properly sample, analyze, or by use of process knowledge classify all wastes in accordance with Title 30 Texas Administrative Code (TAC), Chapter 335, and
Abilene State Supported Living Center
Abilene, TX 79602
October 13, 2025
01 00 00 - 15 of 16
Subchapter R at no additional cost to the Owner. All non-hazardous wastes, special wastes, and hazardous wastes (including but not limited to construction debris, material containers, material residues and unwanted excess materials) resulting from the performance of work under this contract shall be removed from and disposed of off State property by the Contractor at no additional cost to the Owner and in accordance with all applicable Federal, State, and local laws, rules and regulations. Under no circumstances shall the Contractor dispose of wastes or excess material in trash dumpsters, storm sewers, sanitary sewers, creeks, streams or other property of the State.
B. Dumping/cleaning out of concrete trucks on State property is prohibited. Concrete truck chutes only may be rinsed at the construction site. Wastewater and concrete from this rinse shall be collected in a high-density polyethylene (HDPE) plastic-lined box or pit provided by the Contractor at the site. At the end of pouring operations, the Contractor shall excavate all the waste and liner and properly dispose of same. The pit shall be completely backfilled and the site restored to original conditions.
C. Recycling is highly encouraged and shall be employed to the maximum extent practicable. Facility requests boilers and domestic water storage tanks be salvaged.
Location to be determined by Facility at time of Pre-Construction Meeting.
D. All equipment and materials to be removed from the project site not specifically identified for turn-in to the Owner or as requested by Facility, shall become the property of the Contractor upon issuance of the NTP. The Contractor shall turn-in all materials specifically designated for turn-in to the Owner or as requested by Facility, shall be delivered to a location as designated by the Facility. Following is a list of equipment or materials to be turned-in:
1. Generators as noted
2. ATS
3. Circuit Breakers
4. Electrical Panels
1.08 TESTING:
A. Costs of all tests, both those as listed and those as required by referenced Codes, shall be provided by and at the Contractor's expense, unless specifically indicated as being performed by the Owner elsewhere in the contract documents. The Contractor shall schedule all tests and notify the ODR, the A/E, and the Facility in advance in a timely manner prior to any required testing. At times, Code Compliance Officers from within the ODR’s organization; but located in other areas of the State, are required to witness such tests and timely notices and coordination are paramount to their schedules. All test results shall be submitted with the closeout documents.
1.09 FINAL INSPECTIONS:
A. The Contractor’s attention is directed to Article 12 of the UGCs/SGCs for a comprehensive discussion of the requirements for scheduling, performing and completing the “Substantial”, “Final”, and “Inspection of Completed Final” punch list items.
END OF SECTION
Abilene State Supported Living Center
Abilene, TX 79602
October 13, 2025
01 00 00 - 16 of 16
THIS PAGE INTENTIONALLY LEFT BLANK
INSTRUCTIONS TO CONTRACTORS
1. Prepare Contract Progress Schedule in accordance with these instructions and submit to the Project Manager at the time stated in the Contract or as established by the Project Manager.
2. Block 1 – Enter the Project Number, Title, and Location as shown on the Contract.
3. Blocks 2 & 3 – Enter the Work Order Date and Completion Date as specified by the Project Manager in the Work Order letter executing the time period specified in the Contract.
4. Blocks 4 & 5 – Enter the Calendar Days of Time Extensions and amended Completion Date when applicable as specified in
Change Orders.
5. Blocks 6 & 7 – Enter the Name and Address of your Firm. The Schedule must be dated and signed by the Contractor or an authorized representative of the…