This document is an attachment (G.O) for the Ellington Air Force Base (AFB) in Houston, Texas, dated 21 May 2024, detailing requirements for starting of systems, demonstration, instructions, and testing for a construction or renovation project. The attachment outlines comprehensive procedures for system start-up, including coordinating schedules, notifying the Project Manager seven days prior to start-up, verifying equipment conditions, executing start-ups under contractor supervision, and demonstrating equipment operation to Owner's personnel. It requires contractors to provide manufacturer representatives for equipment inspections, perform detailed operational demonstrations, and submit written reports on system functionality.
The General Contractor is responsible for hiring an independent firm to perform testing, adjusting, and balancing services, working closely with the Project Manager to conduct performance evaluations. The independent firm must submit reports to the Project Manager documenting test observations and indicating compliance or non-compliance with contract documents. The attachment specifies that instruction time for each equipment and system will be as defined in individual specification sections, and requires comprehensive demonstration of start-up, operation, control, adjustment, troubleshooting, servicing, maintenance, and shutdown procedures for all equipment at a designated location.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT G.O - ELLINGTON AFB (EF) STARTING OF SYSTEMS
PART 1 – GENERAL
1. SUMMARY
A. This Section includes:
a. Starting systems.
b. Demonstration and instructions.
c. Testing, adjusting, and balancing.
d. Third party testing, adjusting, and balancing.
2. RELATED SECTIONS
A. Solicitation Section C Statement of Work.
B. Attachment G.G - Ellington AFB (EF) Quality Control.
C. Attachment G.P - Ellington AFB (EF) Contract Closeout.
3. STARTING OF SYSTEMS
A. Coordinate schedule for start-up of various equipment and systems.
B. Notify the Project Manager in writing seven days prior to start-up of each item.
C. Verify that each piece of equipment or system has been checked for proper lubrication, drive rotation, belt tension, control sequence, or for other conditions which may cause damage.
D. Verify that tests, meter readings, and specified electrical characteristics agree with those re- quired by the equipment or system manufacturer.
E. Verify wiring and support components for equipment are complete and tested.
F. Execute start-up under supervision of applicable Contractors' personnel in accordance with manufacturers' instructions.
G. When specified in individual specification Sections, require manufacturer to provide authorized representative to be present at site to inspect, check, and approve equipment or system installation prior to start-up, and to supervise placing equipment or system in operation.
H. Submit a written report in accordance with Section 01400 that equipment or system has been properly installed and is functioning correctly.
4. DEMONSTRATION AND INSTRUCTIONS
A. Demonstrate operation and maintenance of Products to Owner's personnel prior to final payment.
B. For equipment or systems requiring seasonal operation, perform demonstration for other sea- son within six months.
C. Utilize operation and maintenance manuals as basis for instruction. Review contents of manual with Owners' personnel in detail to explain all aspects of operation and maintenance.
D. Demonstrate start-up, operation, control, adjustment, troubleshooting, servicing, maintenance, and shutdown of each item of equipment at scheduled time at designated location.
E. Prepare and insert additional data in operations and maintenance manuals when need for additional data becomes apparent during instruction.
ELLINGTON FIELD, HOUSTON, TX 21 May 2024
F. The amount of time required for instruction on each item of equipment and system is that specified in individual sections.
5. TESTING, ADJUSTING, AND BALANCING
A. General Contractor shall pay for (Hire) for services of an independent firm to perform testing, adjusting, and balancing. The independent firm shall work with the Project
Manager in conducting operations of the performance.
B. Reports will be submitted by the independent firm to the Project Manager indicating observations and results of tests and indicating compliance or non-compliance with the requirements of the Contract Documents.