This document is an Attachment G.N for Manufacturers' Services at Ellington Field (EF) in Houston, Texas, dated 21 May 2024. The specification outlines comprehensive requirements for manufacturer representatives' involvement during equipment installation, training, and operational support. Key requirements include submitting training schedules and plans at least 21 days prior to equipment installation, providing qualified manufacturer representatives who are factory-trained and experienced in technical applications, and delivering detailed training services for Ellington Field personnel. The document specifies that manufacturer representatives must assist with product installation, perform inspections and adjustments, resolve installation problems, support functional and performance testing, and provide comprehensive training on operation and maintenance of specified systems and equipment.

The manufacturers' services will be tracked using "person-days", defined as one person working eight hours within regular contractor working hours. The Project Manager must approve all manufacturer service days, and representatives must be prepared to revisit the site as needed to correct problems until installation and operation are acceptable. Training plans must include detailed information such as course objectives, schedules, attendee prerequisites, course descriptions, formats, and instructor resumes. Pre-startup training must be completed at least 14 days before actual startup, with potential for post-startup training as specified in individual project specifications. A Manufacturer's Certificate of Proper Installation is required, which will document the proper installation and testing of equipment.

View the file

Other files

File Type Posted
ESBD_449777_1756395940409_ATTACHMENT G.G - Ellington AFB (EF) Quality Control.pdf PDF
ESBD_449777_1756396090980_ATTACHMENT G.O - Ellington Field (EF) Starting Of Systems.pdf PDF
ESBD_449777_1756395679126_ATTACHMENT G.8 HUB Subcontracting Plan (HSP).pdf PDF
ESBD_449777_1756396128110_ATTACHMENT G.Q - Ellington AFB (EF) Cutting And Patching.pdf PDF
ESBD_449777_1756395845858_ATTACHMENT G.D - Ellington AFB (EF) Field Engineering.pdf PDF
ESBD_449777_1756396081512_ATTACHMENT G.N.1 - Ellington Field (EF) Manufacturer’s Certificate Of Proper Installation.pdf PDF
ESBD_449777_1756396291938_ATTACHMENT G.X - Ellington AFB (EF) AF3000.pdf PDF
ESBD_449777_1756395875686_ATTACHMENT G.F.1 - Ellington AFB (EF) Contractor Hazardous Material Usage Data.pdf PDF
ESBD_449777_1756501479663_Addendum 1 - TMD25-ANG-WJ-24150007.pdf PDF
ESBD_449777_1756395865813_ATTACHMENT G.F - Ellington Field (EF) EMS Hazardous Material Procedures.pdf PDF
ESBD_449777_1756396053573_ATTACHMENT G.L - Ellington Field JRB Final Asbestos Abatement Report Template.pdf PDF
ESBD_449777_1756396168631_ATTACHMENT G.U - Ellington Field (EF) Sustainable Design Requirements.pdf PDF
ESBD_449777_1756395856125_ATTACHMENT G.E - Ellington Field (EF) Safety Policies And Procedures.pdf PDF
ESBD_449777_1756396139089_ATTACHMENT G.R - Ellington Field (EF) EMS Construction Waste Management And Disposal Part 1 - General.pdf PDF
ESBD_449777_1756395651552_ATTACHMENT G.7 Project Map-Hush House Map.pdf PDF
ESBD_449777_1756396062076_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf PDF
ESBD_449777_1756395719417_ATTACHMENT G.1 Direct Deposit Authorization Form 74-176 (Rev.9-2121).pdf PDF
ESBD_449777_1756395836697_ATTACHMENT G.C - Ellington AFB (EF) Project Coordination.pdf PDF
ESBD_449777_1756395731444_ATTACHMENT G.2 Application for Texas Identification Number AP-152.pdf PDF
ESBD_449777_1756396279811_ATTACHMENT G.W - Ellington AFB (EF) AF103_REV.pdf PDF
ESBD_449777_1756395817373_ATTACHMENT G.B - Ellington Field (EF) Coordination And Meetings.pdf PDF
ESBD_449777_1756395968488_ATTACHMENT G.I - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Cultural Materials.pdf PDF
ESBD_449777_1756396311373_ATTACHMENT G.V - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Unmarked Burials.pdf PDF
ESBD_449777_1756396148437_ATTACHMENT G.S - Ellington AFB (EF) Substitutions Request Form.pdf PDF
ESBD_449777_1756395957039_ATTACHMENT G.H - Ellington Field (EF) EMS Environmental Protection.pdf PDF
ESBD_449777_1756395630851_ATTACHMENT G.5 Photo of Hush House Transformer.pdf PDF
ESBD_449777_1756396042129_ATTACHMENT G.K - Ellington AFB (EF) Construction Facilities And Temporary Controls.pdf PDF
ESBD_449777_1756395641216_ATTACHMENT G.6 ALAMO Transformer Schematic.pdf PDF
ESBD_449777_1756396157692_ATTACHMENT G.T - Ellington Field (EF) Post Award Submittals.pdf PDF
ESBD_449777_1756395887888_ATTACHMENT G.F.2 - Ellington AFB (EF) Contractor Hazardous Material Identification Form Close-Out Procedures.pdf PDF
ESBD_449777_1756395807712_ATTACHMENT G.A - Ellington Field (EF) General Requirements.pdf PDF
ESBD_449777_1756395616803_TMD25-ANG-WJ-24150007v2 Transformer Replacement Rebid.pdf PDF
ESBD_449777_1756395988780_ATTACHMENT G.J.1 - Ellington AFB (EF) Maintenance Summary Form.pdf PDF
ESBD_449777_1756395783572_ATTACHMENT G.3 Texas Military Department Standard Terms and Conditions Revision 6.pdf PDF
ESBD_449777_1756396100710_ATTACHMENT G.P - Ellington Field (EF) Contract Closeout.pdf PDF
ESBD_449777_1756501514709_TMD25-ANG-WJ-24150007v2 Update1 Transformer Replacement Rebid.pdf PDF
ESBD_449777_1756395598194_ATTACHMENT G.4 Mandatory Pricing Schedule.xlsx XLSX spreadsheet
ESBD_449777_1756395978869_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT G.N - ELLINGTON AFB (EF) MANUFACTURERS’

SERVICES

PART 1 – GENERAL

1. DEFINITIONS

Person-Day: One person for eight (8) hours within regular Contractor working hours.

2. SUBMITTALS

A. Training Schedule: Submit not less than twenty-one (21) days prior to start of equipment installation and revise as necessary for acceptance.

B. Preliminary Training Plan: Submit within sixty (60) days after Notice to Proceed for approval by the Project Manager.

C. Final Training Plan: Submit after training coordination meeting.

D. Training Materials:

a. Submit written outlines of proposed training sessions not less than twenty-one

(21) days prior to scheduled training to be approved by the Project Manager.

b. Furnish complete training materials, to include operation and maintenance data as required in this section to be retained by each trainee.

E. Quality Control Submittals: When specified in the individual Specifications, submit:

a. Qualifications of Manufacturer’s Representative performing specified services.

b. Manufacturer’s Certificate of Proper Installation: On form appended to this section.

3. QUALIFICATION OF MANUFACTURER’S REPRESENTATIVE

A. Authorized representative of the manufacturer shall be factory trained and experienced in the technical applications, installation, operation, and maintenance of respective equipment, subsystem, or system. Additional qualifications may be specified elsewhere.

B. Manufacturer’s Representative subject to acceptance by the Project Manager. No substitute representatives will be allowed unless prior written approval by the Project

Manager has been given.

4. FULFILLMENT OF SPECIFIED MINIMUM SERVICES

A. Where manufacturers’ services are specified, furnish manufacturer’s qualified representative. Where time is necessary in excess of that stated in the Specifications for manufacturers’ services, additional time required to perform the specified services shall be considered incidental work.

B. Schedule manufacturer’s services to avoid conflicting with other onsite testing or other manufacturer’s onsite services.

a. Determine that all conditions necessary to allow successful testing have been met before scheduling services.

C. Only those days of service approved by the Project Manager will be credited to fulfill the specified minimum services.

D. If specified, manufacturer’s onsite services shall include as a minimum:

a. Assistance during product (system, subsystem, or component) installation to

ELLINGTON FIELD, HOUSTON, TX 21 May 2024 include observation, guidance, instruction of Contractor’s assembly, erection, installation or application procedures.

b. Inspection, checking, and adjustment as required for product (system, subsystem, or component) to function as warranted by manufacturer and necessary to furnish written approval of installation.

c. Revisiting the site as required to correct problems and until installation and operation are acceptable to the Project Manager.

d. Resolution of assembly or installation problems attributable to, or associated with, respective manufacturer’s products and systems.

e. Assistance during functional and performance testing and startup demonstration, and until product acceptance by the Project Manager.

f. Training of EF personnel in the operation and maintenance of respective product as required.

g. Completion of Manufacturer’s Certificate of Proper Installation (form enclosed at end of this section) with applicable certificates for proper installation and initial, interim, and final test or service.

h. Additional requirements as may be specified elsewhere.

5. TRAINING SCHEDULE

A. List specified equipment and systems with respective manufacturers that require training services of manufacturers’ representatives and show:

a. Estimated dates for installation completion.

b. Estimated training dates to allow for multiple sessions when several shifts are involved.

B. Adjust training schedule to ensure training of appropriate personnel as deemed necessary by the Project Manager, and to allow full participation by manufacturers’ representatives. Adjust schedule for interruptions in operability of equipment.

6. TRAINING PLAN

A. Preliminary Training Plan: If specified, and within sixty (60) days after Notice to

Proceed, submit for each proposed course to be approved by the Project Manager:

a. Title and objectives.

b. Training schedule.

c. Prerequisite training and experience of attendees.

d. Recommended types of attendees (e.g., managers, engineers, operators, maintenance).

e. Course description and outline of course content.

f. Duration.

g. Location (e.g., training center or site).

h. Format (e.g., lecture, self-study, demonstration, hands-on).

i. Instruction materials and equipment requirements.

j. Final Training Plan: Submit the following after training coordination meeting, if specified.

k. Updated versions of course descriptions from preliminary training plan.

l. Personnel who will attend each course.

ELLINGTON FIELD, HOUSTON, TX 21 May 2024

m. Schedule of training courses including dates, durations, and locations of each class.

n. Detailed course schedule for each day showing time allocated to each topic.

o. Resumes of instructors providing the training.

7. TRAINING BASE PERSONNEL

A. Furnish trained, articulate personnel to coordinate and expedite training, to be present during training coordination meetings with EF Personnel, and familiar with operation and maintenance manual information specified in Division 1 Section, “Operation and

Maintenance Data”.

B. Furnish manufacturers’ representatives for detailed classroom and hands-on training to EF personnel on operation and maintenance of specified product (system, subsystem, component) and as may be required in applicable Specifications.

a. Manufacturer’s Representative: Familiar with facility operation and maintenance requirements as well as with specified equipment.

C. Prestart up Training:

a. Coordinate training sessions with EF operating personnel and manufacturers’ representatives, and with submission of operation and maintenance manuals in accordance with Division 1 Section “Operation and Maintenance Data”.

b. Complete at least fourteen (14) days prior to actual startup.

D. Post-Startup Training: If required in Specifications, furnish and coordinate training of

EF operating personnel by respective manufacturer’s representatives.

8. SUPPLEMENTS

A. The supplements listed below, following “END OF SECTION,” are part of this

Specification.

a. Forms: Manufacturer’s Certificate of Proper Installation.