ESBD_449777_1756396062076_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf

PDF 63 KB Posted

Attached to
Transformer Replacement Rebid
Solicitation number
TMD25-ANG-WJ-24150007v2
Issued by
Harris County, Texas

About this file

This document is an Attachment G.M for Material Equipment at Ellington Air Force Base (AFB) in Houston, Texas, dated 21 May 2024. The attachment provides comprehensive guidelines for transportation, handling, storage, and protection of products, as well as procedures for product options and substitutions during the project. It outlines specific requirements for contractors regarding product inspection, storage methods, and the process for requesting product substitutions, with the Project Manager having the authority to approve or reject such requests during the submittal phase.

The document emphasizes that payment for stored materials will only be made when an inventory and supplier invoices are submitted, and compensation will be limited to the actual cost of materials. Contractors must follow strict protocols for product handling, including maintaining manufacturer's instructions, preventing damage, and ensuring proper storage conditions. The attachment also stipulates that if a substitution request is not accepted by the government, the contractor remains responsible for supplying the originally specified item or an acceptable alternative without additional cost to the owner.

View the file

Other files

File Type Posted
ESBD_449777_1756395940409_ATTACHMENT G.G - Ellington AFB (EF) Quality Control.pdf PDF
ESBD_449777_1756396090980_ATTACHMENT G.O - Ellington Field (EF) Starting Of Systems.pdf PDF
ESBD_449777_1756395679126_ATTACHMENT G.8 HUB Subcontracting Plan (HSP).pdf PDF
ESBD_449777_1756396128110_ATTACHMENT G.Q - Ellington AFB (EF) Cutting And Patching.pdf PDF
ESBD_449777_1756395845858_ATTACHMENT G.D - Ellington AFB (EF) Field Engineering.pdf PDF
ESBD_449777_1756396081512_ATTACHMENT G.N.1 - Ellington Field (EF) Manufacturer’s Certificate Of Proper Installation.pdf PDF
ESBD_449777_1756396291938_ATTACHMENT G.X - Ellington AFB (EF) AF3000.pdf PDF
ESBD_449777_1756395875686_ATTACHMENT G.F.1 - Ellington AFB (EF) Contractor Hazardous Material Usage Data.pdf PDF
ESBD_449777_1756501479663_Addendum 1 - TMD25-ANG-WJ-24150007.pdf PDF
ESBD_449777_1756395865813_ATTACHMENT G.F - Ellington Field (EF) EMS Hazardous Material Procedures.pdf PDF
ESBD_449777_1756396053573_ATTACHMENT G.L - Ellington Field JRB Final Asbestos Abatement Report Template.pdf PDF
ESBD_449777_1756396168631_ATTACHMENT G.U - Ellington Field (EF) Sustainable Design Requirements.pdf PDF
ESBD_449777_1756395856125_ATTACHMENT G.E - Ellington Field (EF) Safety Policies And Procedures.pdf PDF
ESBD_449777_1756396139089_ATTACHMENT G.R - Ellington Field (EF) EMS Construction Waste Management And Disposal Part 1 - General.pdf PDF
ESBD_449777_1756395651552_ATTACHMENT G.7 Project Map-Hush House Map.pdf PDF
ESBD_449777_1756395719417_ATTACHMENT G.1 Direct Deposit Authorization Form 74-176 (Rev.9-2121).pdf PDF
ESBD_449777_1756395836697_ATTACHMENT G.C - Ellington AFB (EF) Project Coordination.pdf PDF
ESBD_449777_1756395731444_ATTACHMENT G.2 Application for Texas Identification Number AP-152.pdf PDF
ESBD_449777_1756396279811_ATTACHMENT G.W - Ellington AFB (EF) AF103_REV.pdf PDF
ESBD_449777_1756395817373_ATTACHMENT G.B - Ellington Field (EF) Coordination And Meetings.pdf PDF
ESBD_449777_1756395968488_ATTACHMENT G.I - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Cultural Materials.pdf PDF
ESBD_449777_1756396311373_ATTACHMENT G.V - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Unmarked Burials.pdf PDF
ESBD_449777_1756396148437_ATTACHMENT G.S - Ellington AFB (EF) Substitutions Request Form.pdf PDF
ESBD_449777_1756395957039_ATTACHMENT G.H - Ellington Field (EF) EMS Environmental Protection.pdf PDF
ESBD_449777_1756395630851_ATTACHMENT G.5 Photo of Hush House Transformer.pdf PDF
ESBD_449777_1756396042129_ATTACHMENT G.K - Ellington AFB (EF) Construction Facilities And Temporary Controls.pdf PDF
ESBD_449777_1756395641216_ATTACHMENT G.6 ALAMO Transformer Schematic.pdf PDF
ESBD_449777_1756396157692_ATTACHMENT G.T - Ellington Field (EF) Post Award Submittals.pdf PDF
ESBD_449777_1756395887888_ATTACHMENT G.F.2 - Ellington AFB (EF) Contractor Hazardous Material Identification Form Close-Out Procedures.pdf PDF
ESBD_449777_1756395807712_ATTACHMENT G.A - Ellington Field (EF) General Requirements.pdf PDF
ESBD_449777_1756395616803_TMD25-ANG-WJ-24150007v2 Transformer Replacement Rebid.pdf PDF
ESBD_449777_1756395988780_ATTACHMENT G.J.1 - Ellington AFB (EF) Maintenance Summary Form.pdf PDF
ESBD_449777_1756395783572_ATTACHMENT G.3 Texas Military Department Standard Terms and Conditions Revision 6.pdf PDF
ESBD_449777_1756396100710_ATTACHMENT G.P - Ellington Field (EF) Contract Closeout.pdf PDF
ESBD_449777_1756396072107_ATTACHMENT G.N - Ellington Field (EF) Manufacturers’ Services.pdf PDF
ESBD_449777_1756501514709_TMD25-ANG-WJ-24150007v2 Update1 Transformer Replacement Rebid.pdf PDF
ESBD_449777_1756395598194_ATTACHMENT G.4 Mandatory Pricing Schedule.xlsx XLSX spreadsheet
ESBD_449777_1756395978869_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT G.M - ELLINGTON AFB (EF) MATERIAL EQUIPMENT

PART 1 – GENERAL

1. RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and

Supplementary Conditions, apply to this Section.

2. SUMMARY

A. This Section includes:

a. Transportation and handling

b. Storage and protection

c. Product options

d. Substitutions

3. TRANSPORTATION AND HANDLING

A. Transport and handle Products in accordance with manufacturer's instructions.

B. Promptly inspect shipments to ensure that Products comply with requirements, quantities are correct, and Products are undamaged.

C. Provide equipment and personnel to handle Products by methods to prevent soiling, disfigurement, or damage.

4. STORAGE AND PROTECTION

A. Store and protect Products in accordance with manufacturers' instructions, with seals and labels intact and legible.

B. Store sensitive Products in weather tight, climate-controlled enclosures.

C. For exterior storage of fabricated Products, place on sloped supports, above ground.

D. Provide bonded off-site storage and protection when site does not permit on-site storage or protection.

E. Cover Products subject to deterioration with impervious sheet covering. Provide ventilation to avoid condensation or potential degradation of Product.

F. Store loose granular materials on solid flat surfaces in a well-drained area. Prevent mixing with foreign matter.

G. Provide equipment and personnel to store Products by methods to prevent soiling, disfigurement, or damage.

H. Arrange storage of Products to permit access for inspection. Periodically inspect to verify Products are undamaged and are maintained in acceptable condition.

I. Payment for materials stored on site will be made only when the request is accompanied by an inventory of stored materials along with copies of the supplier invoices for the stored materials. Only actual cost of the materials stored will be compensated.

5. PRODUCT OPTIONS

A. Products Specified by Reference Standards or by Description Only: Any Product meeting those standards or description.

B. Products Specified by Naming One or More Manufacturers: Products of manufacturers named and meeting specifications, no options or substitutions allowed.

C. Products Specified by Naming One or More Manufacturers with a Provision for

ELLINGTON FIELD, HOUSTON, TX 21 May 2024

Substitutions: Submit a request for substitution for any manufacturer not named in accordance with the following article.

6. SUBSTITUTIONS

A. Project Manager will consider requests for Substitutions during the submittal phase of the project.

B. Substitutions may be considered when a Product becomes unavailable through no fault of the Contractor.

C. Document each request with complete data substantiating compliance of proposed

Substitution with Contract Documents.

D. A request constitutes a representation that the Contractor:

a. Has investigated proposed Product and determined that it meets or exceeds the quality level of the specified Product.

b. Will provide the same warranty for the Substitution as for the specified

Product.

c. Will coordinate installation and make changes to other Work which may be required for the Work to be complete with no additional cost to Owner.

d. Waives claims for additional costs or time extension which may subsequently become apparent.

E. Substitutions will not be considered when they are indicated or implied on shop drawing or product data submittals, without separate written request, or when acceptance will require revision to the Contract Documents.

F. Substitution Submittal Procedure:

a. Submit three copies of request for Substitution for consideration on

Substitution Request Form attached to this section. Limit each Substitution

Request Form to one proposed Substitution.

b. Submit shop drawings, product data, and certified test results attesting to the proposed Product equivalence.

c. The Project Manager will notify Contractor in writing of decision to accept or reject re- quest.

G. If request for substitution is not accepted by the government, Contractor is responsible for sup- plying item as originally specified or an acceptable substitution without additional cost to the Owner.