ESBD_449777_1756395817373_ATTACHMENT G.B - Ellington Field (EF) Coordination And Meetings.pdf

PDF 56 KB Posted

Attached to
Transformer Replacement Rebid
Solicitation number
TMD25-ANG-WJ-24150007v2
Issued by
Harris County, Texas

About this file

This document is an attachment (G.B) for coordination and meetings related to a construction project at Ellington Air Force Base (AFB) in Houston, Texas, dated 21 May 2024. The attachment outlines comprehensive meeting and coordination protocols for the project, including preconstruction, progress, and pre-installation meetings. Key requirements include scheduling monthly (or preferably bi-weekly) progress meetings, preparing detailed agendas, documenting meeting minutes within 3 working days, and ensuring attendance of job superintendents, major subcontractors, and project managers.

The document specifies detailed coordination responsibilities, such as aligning scheduling and submittals, verifying utility requirements, coordinating mechanical and electrical work, and ensuring efficient space utilization. Additional requirements include concealing pipes and ducts in finished areas, coordinating work completion and cleanup, and managing post-occupancy site access for corrections. The attachment also provides guidelines for site examination, including verifying existing site conditions, substrate surfaces, and utility services, as well as preparation procedures like cleaning surfaces, sealing cracks, and applying manufacturer-recommended primers or sealants.

View the file

Other files

File Type Posted
ESBD_449777_1756395940409_ATTACHMENT G.G - Ellington AFB (EF) Quality Control.pdf PDF
ESBD_449777_1756396090980_ATTACHMENT G.O - Ellington Field (EF) Starting Of Systems.pdf PDF
ESBD_449777_1756395679126_ATTACHMENT G.8 HUB Subcontracting Plan (HSP).pdf PDF
ESBD_449777_1756396128110_ATTACHMENT G.Q - Ellington AFB (EF) Cutting And Patching.pdf PDF
ESBD_449777_1756395845858_ATTACHMENT G.D - Ellington AFB (EF) Field Engineering.pdf PDF
ESBD_449777_1756396081512_ATTACHMENT G.N.1 - Ellington Field (EF) Manufacturer’s Certificate Of Proper Installation.pdf PDF
ESBD_449777_1756396291938_ATTACHMENT G.X - Ellington AFB (EF) AF3000.pdf PDF
ESBD_449777_1756395875686_ATTACHMENT G.F.1 - Ellington AFB (EF) Contractor Hazardous Material Usage Data.pdf PDF
ESBD_449777_1756501479663_Addendum 1 - TMD25-ANG-WJ-24150007.pdf PDF
ESBD_449777_1756395865813_ATTACHMENT G.F - Ellington Field (EF) EMS Hazardous Material Procedures.pdf PDF
ESBD_449777_1756396053573_ATTACHMENT G.L - Ellington Field JRB Final Asbestos Abatement Report Template.pdf PDF
ESBD_449777_1756396168631_ATTACHMENT G.U - Ellington Field (EF) Sustainable Design Requirements.pdf PDF
ESBD_449777_1756395856125_ATTACHMENT G.E - Ellington Field (EF) Safety Policies And Procedures.pdf PDF
ESBD_449777_1756396139089_ATTACHMENT G.R - Ellington Field (EF) EMS Construction Waste Management And Disposal Part 1 - General.pdf PDF
ESBD_449777_1756395651552_ATTACHMENT G.7 Project Map-Hush House Map.pdf PDF
ESBD_449777_1756396062076_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf PDF
ESBD_449777_1756395719417_ATTACHMENT G.1 Direct Deposit Authorization Form 74-176 (Rev.9-2121).pdf PDF
ESBD_449777_1756395836697_ATTACHMENT G.C - Ellington AFB (EF) Project Coordination.pdf PDF
ESBD_449777_1756395731444_ATTACHMENT G.2 Application for Texas Identification Number AP-152.pdf PDF
ESBD_449777_1756396279811_ATTACHMENT G.W - Ellington AFB (EF) AF103_REV.pdf PDF
ESBD_449777_1756395968488_ATTACHMENT G.I - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Cultural Materials.pdf PDF
ESBD_449777_1756396311373_ATTACHMENT G.V - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Unmarked Burials.pdf PDF
ESBD_449777_1756396148437_ATTACHMENT G.S - Ellington AFB (EF) Substitutions Request Form.pdf PDF
ESBD_449777_1756395957039_ATTACHMENT G.H - Ellington Field (EF) EMS Environmental Protection.pdf PDF
ESBD_449777_1756395630851_ATTACHMENT G.5 Photo of Hush House Transformer.pdf PDF
ESBD_449777_1756396042129_ATTACHMENT G.K - Ellington AFB (EF) Construction Facilities And Temporary Controls.pdf PDF
ESBD_449777_1756395641216_ATTACHMENT G.6 ALAMO Transformer Schematic.pdf PDF
ESBD_449777_1756396157692_ATTACHMENT G.T - Ellington Field (EF) Post Award Submittals.pdf PDF
ESBD_449777_1756395887888_ATTACHMENT G.F.2 - Ellington AFB (EF) Contractor Hazardous Material Identification Form Close-Out Procedures.pdf PDF
ESBD_449777_1756395807712_ATTACHMENT G.A - Ellington Field (EF) General Requirements.pdf PDF
ESBD_449777_1756395616803_TMD25-ANG-WJ-24150007v2 Transformer Replacement Rebid.pdf PDF
ESBD_449777_1756395988780_ATTACHMENT G.J.1 - Ellington AFB (EF) Maintenance Summary Form.pdf PDF
ESBD_449777_1756395783572_ATTACHMENT G.3 Texas Military Department Standard Terms and Conditions Revision 6.pdf PDF
ESBD_449777_1756396100710_ATTACHMENT G.P - Ellington Field (EF) Contract Closeout.pdf PDF
ESBD_449777_1756396072107_ATTACHMENT G.N - Ellington Field (EF) Manufacturers’ Services.pdf PDF
ESBD_449777_1756501514709_TMD25-ANG-WJ-24150007v2 Update1 Transformer Replacement Rebid.pdf PDF
ESBD_449777_1756395598194_ATTACHMENT G.4 Mandatory Pricing Schedule.xlsx XLSX spreadsheet
ESBD_449777_1756395978869_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT G.B - ELLINGTON AFB (EF) COORDINATION AND

MEETINGS

PART 1 – GENERAL

1. SUMMARY

A. This Section includes:

a. Coordination

b. Preconstruction meeting

c. Progress meetings

d. Pre-installation meetings

e. Examination

f. Preparation

2. COORDINATION

A. Coordinate scheduling, submittals, and Work of the various sections of the Project

Manual to assure efficient and orderly sequence of installation of interdependent construction elements, [with provisions for accommodating items installed later].

B. Verify utility requirements and characteristics of operating equipment are compatible with building utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service, such equipment.

C. Coordinate space requirements and installation of mechanical and electrical work which are indicated diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduit, as closely as practicable; place runs parallel with line of building.

Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.

D. In finished areas [except as otherwise indicated], conceal pipes, ducts, and wiring within the construction. Coordinate locations of fixtures and outlets with finish elements.

E. Coordinate completion and cleanup of Work of separate sections in preparation for

Substantial Completion.

F. After Owner occupancy of premises, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of Owner's activities.

3. PRE-CONSTRUCTION MEETING

A. The Project Manager will schedule a meeting after Notice of Award.

B. Agenda:

a. Distribution of Contract Documents

b. Submission of list of Subcontractors, list of Products, schedule of values, and proposed construction schedule.

c. Designation of personnel representing the parties in Contract

d. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures

e. Scheduling

f. Safety plan submittal

ELLINGTON FIELD, HOUSTON, TX 21 May 2024

4. PROGRESS MEETINGS

A. The Contractor will in Coordination with the Project Manager:

a. Schedule and administer meetings throughout progress of the Work at maximum monthly intervals, every 2-weeks is preferred.

b. Make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings.

c. Review coordination with related work

d. Provide written documentation of the meeting minutes for review and acceptance by all present within 3 working days of each meeting.

B. Attendance Required: Job superintendent, major Subcontractors and suppliers, the

Project Manager as appropriate to agenda topics for each meeting.

C. Agenda:

a. Review minutes of previous meetings

b. Review of Work progress

c. Field observations, problems, and decisions

d. Identification of problems which impede planned progress.

e. Review of submittals schedule with emphasis on Critical Path Items and status of submittals

f. Review of off-site fabrication and delivery schedules

g. Maintenance of progress schedule

h. Corrective measures to regain projected schedules.

i. Planned progress during succeeding work period.

j. Coordination of projected progress

k. Maintenance of quality and work standards

l. Effect of proposed changes on progress schedule and coordination

m. Other business relating to Work.

5. PRE-INSTALLATION MEETING

A. When required in individual specification sections, convene a pre-installation meeting at work site prior to commencing work of the section.

B. Require attendance of parties directly affecting, or affected by, work of the

C. specific section.

D. Notify the Project Manager four days in advance of meeting date.

E. Contractor will prepare agenda and preside at meeting:

a. Review conditions of installation, preparation, and installation procedures

b. Provide written documentation of the minutes of the meeting within 3 working days of each meeting.

PART 2 – EXECUTION

1. EXAMINATION

A. Verify that existing site conditions and substrate surfaces are acceptable for subsequent Work. Beginning new Work means acceptance of existing conditions.

B. Verify that existing substrate is capable of structural attachment of new Work being applied or attached.

ELLINGTON FIELD, HOUSTON, TX 21 May 2024

C. Examine and verify specific conditions described in individual specification sections.

D. Verify that utility services are available, of the correct characteristics, and in the correct location.

2. PREPARATION

A. Clean substrate surfaces prior to applying next material or substance.

B. Seal cracks or openings of substrate prior to applying next material or substance.

C. Apply any manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying any new material or substance in contact or bond.