ESBD_401277_1748872599840_AT8DD5~1.PDF

PDF 147 KB Posted

Attached to
HEAT PUMP AND BOILER AND BOILER FLUE REPLACEMENTS
Solicitation number
TMD25-ANG-WJ-24150004_5_6_B1057_1363_1377
Issued by
Harris County, Texas

About this file

This document is a contract closeout attachment for a construction project at Ellington Field in Houston, Texas, involving the United States government. The attachment outlines comprehensive procedures for project completion, including pre-final and final inspections, training requirements, and closeout documentation. The project involves final acceptance processes, systematic documentation of work completed, and detailed requirements for record keeping, including submission of operation and maintenance manuals, warranties, and as-built drawings.

The document specifies rigorous administrative requirements for project completion, including final cleaning procedures, submittal of certified subcontractor lists with lien waivers, and preparation of comprehensive project documentation. Key administrative requirements include maintaining project record documents, creating operation and maintenance data binders, executing warranty documents, and delivering spare parts and maintenance materials. The contract includes provisions for potential liquidated damages if project completion extends beyond the contracted timeline, with specific emphasis on thorough documentation and systematic verification of all project elements before final acceptance.

View the file

Other files

File Type Posted
ESBD_401277_1748872677255_ATB408~1.PDF PDF
ESBD_401277_1748872520449_ATF409~1.PDF PDF
ESBD_401277_1748872644533_ATAC97~1.PDF PDF
ESBD_401277_1748872655152_ATBB18~1.PDF PDF
ESBD_401277_1748872126186_ATTACHMENT G.1 Direct Deposit 74-176.pdf PDF
ESBD_401277_1748872207683_ATTACHMENT G.8 B1377 System.pdf PDF
ESBD_401277_1748872139337_ATTACHMENT G.2 Application for Texas ID #_AP_152.pdf PDF
ESBD_401277_1748872577160_ATCD32~1.PDF PDF
ESBD_401277_1748872472153_AT7BBC~1.PDF PDF
ESBD_401277_1748872566336_AT04E2~1.PDF PDF
ESBD_401277_1748872162925_ATTACHMENT G.4 Mandatory Pricing Schedule.xlsx XLSX spreadsheet
ESBD_401277_1748872431050_AT9E6E~1.PDF PDF
ESBD_401277_1748872553365_ATCF02~1.PDF PDF
ESBD_401277_1748872309609_ATTACHMENT G.5 Site Location.pdf PDF
ESBD_401277_1748872197790_ATTACHMENT G.7 B1363 System.pdf PDF
ESBD_401277_1748872632942_ATC8C2~1.PDF PDF
ESBD_401277_1748872531990_ATE6CA~1.PDF PDF
ESBD_401277_1748872665557_ATTACHMENT G.W - Ellington AFB (EF) AF103_REV.pdf PDF
ESBD_401277_1748872371253_AT6F64~1.PDF PDF
ESBD_401277_1748872415459_ATFC65~1.PDF PDF
ESBD_401277_1748872621894_AT9546~1.PDF PDF
ESBD_401277_1748872396937_AT909E~1.PDF PDF
ESBD_401277_1748872497677_AT5BF6~1.PDF PDF
ESBD_401277_1748872186497_ATTACHMENT G.6 B1057 System.pdf PDF
ESBD_401277_1748872588788_ATC871~1.PDF PDF
ESBD_401277_1748872543207_ATF572~1.PDF PDF
ESBD_401277_1748872611679_ATE420~1.PDF PDF
ESBD_401277_1748872342568_ATTACHMENT G.9 HUB Subcontracting Plan (HSP).pdf PDF
ESBD_401277_1748872104631_TMD25-~1.PDF PDF
ESBD_401277_1748872509961_ATF9DE~1.PDF PDF
ESBD_401277_1748872487237_ATF70F~1.PDF PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT G.P - ELLINGTON AFB (EF) CONTRACT CLOSEOUT

PART 1 – GENERAL

1. SUMMARY

A. This Section includes:

a. Procedures for final acceptance of the Project.

b. Closeout procedures.

c. Final cleaning.

d. Adjusting.

e. Project record documents.

f. Operation and maintenance data.

g. Warranties.

h. Spare parts and maintenance materials.

2. RELATED SECTIONS

A. Attachment G.O - Ellington AFB (EF) Starting Of Systems: Progress cleaning.

B. Attachment G.O - Ellington AFB (EF) Starting Of Systems: System start-up, testing, adjusting, and balancing.

3. PROCEDURES FOR FINAL ACCEPTANCE OF THE PROJECT

A. Pre-final inspection:

a. When the Construction Contractor has completed all work and is satisfied the project is fully in compliance with the contract documents; he will notify the

Project Manager, in writing, that the project is complete and ready for inspection. The Project Manager will arrange for and conduct an inspection of the project by the Project Manager, the Project Manager 's Representatives, and the Construction Contractor. The Project Manager will be provided a reasonable time to arrange for and conduct an inspection.

b. The Project Manager will document any deficiencies on a written punch list and will arrange a meeting with the Construction Contractor to review the punch list and explain all deficient items. The Construction Contractor shall correct the deficiencies and notify the Project Manager in writing when the project is ready for inspection of the deficient items. The Project Manager will arrange and conduit a re-inspection of the project to review the corrected items.

c. The formal list of deficiencies found shall not be considered a final list of all deficient items. The contractor must correct any deficiencies that are found at any point prior to or after final acceptance of the project.

d. NOTE: LIQUIDATED DAMAGES ON PROJECTS THAT EXTEND

BEYOND THE CONTRACT COMPLETION DATE WILL CONTINUE TO

RUN UNTIL ALL CLOSE-OUT DOCUMENTATION IS SUBMITTED

AND ACCEPTED AND ALL “PUNCH-LIST” WORK IS COMPLETE.

B. Training, Instruction and Demonstration:

a. When the Project Manager has determined that the project is sufficiently complete to allow instruction of the Government’s Representative, the Project

Manager will request, in writing, that the Construction Contractor provide

ELLINGTON FIELD, HOUSTON, TX 21 May 2024 training, instruction and demonstration of the work. This training, instruction and demonstration will not be scheduled until all required operations and maintenance data has been submitted and approved.

b. Upon formal notice from the Project Manager, the Construction Contractor shall then arrange for instruction of the Government’s staff in the operation of the constructed systems. This includes submission of all outstanding record documents, including operating and maintenance manuals (required prior to scheduling instruction meeting), equipment cuts, guarantees, warranties, maintenance contracts, and any additional instructions necessary for the operation of the systems. The Construction Contractor shall acquaint the

Government's staff with acceptance tests, guarantees, warranties, and maintenance manuals. The Construction Contractor and the Project Manager will determine the transfer of responsibility for heat, utilities, security, and insurance. The Construction Contractor shall also obtain a Certificate of

Occupancy (where applicable) or similar releases required to permit the

Owner's occupancy of the project.

c. Should the instruction period find deficiencies, the Project Manager will notify the Construction Contractor in writing of deficient items.

C. Final inspection:

a. Upon completion of the remaining deficiencies the Construction Contractor shall notify the Project Manager in writing, that the project is complete and ready for a final inspection. The Project Manager shall arrange for and conduct a final inspection of the project.

D. Additional inspection:

a. Should the project require inspections beyond inspections noted above, from pre- final through final inspection, the Project Manager will reduce from the

Construction Contractor's final payment those monies necessary to provide for the cost of the additional inspections. The reduction shall not be considered as a part of any "Liquidated Damages" for failure to complete within the specified contract time. The reduction shall not be considered as a penalty to the Construction Contractor; but shall be for the actual cost of monies required for the reimbursement of fees for Architect, Owner Representatives, and other specialist necessary for acceptance of the project.

E. Excessive deficiencies found during inspections:

a. During any inspection of project completion, if it is determined by the Project

Manager, that the Construction Contractor has not sufficiently completed the work in compliance to the contract documents, the owner may declare that the project is not sufficiently complete to continue inspection of the work. Within three (3) working days, of the declaration, the Project Manager will issue in writing, a list of deficiencies found. The deficiency listed shall be understood as only a partial list and that the partial list may or may not represent deficiencies in areas that were not inspected.

4. CLOSEOUT PROCEDURES

A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for the Project Manager’s review.

B. Provide submittals to the Project Manager that are required by governing or other authorities.

C. Submit final Application for Payment identifying total adjusted Contract Sum, previous payments, and sum remaining due.

D. Submit with the final Application for Payment a complete certified list of subcontractors and material suppliers. Accompanying the list shall be a lien waiver signed by each subcontractor and material supplier as documentation verifying that payment has been made for services and materials required for completion of this

Contract. Lien waiver forms are available from the Project Manager.

5. FINAL CLEANING

A. Execute final cleaning prior to final project assessment.

B. Clean interior and exterior glass, surfaces exposed to view; remove temporary labels, stains, and foreign substances, polish transparent and glossy surfaces, vacuum carpeted and soft surfaces.

C. Clean equipment and fixtures to a sanitary condition with cleaning materials appropriate to the surface and material being cleaned.

D. Replace filters of operating equipment.

E. Clean debris from roofs, gutters, downspouts, and drainage systems.

F. Clean site, only areas that were used for staging and adjacent areas that may need cleaning due to windblown construction debris; sweep paved areas, rake clean landscaped surfaces.

G. Remove waste and surplus materials, rubbish, and construction facilities from the site.

6. ADJUSTING

A. Adjust operating Products and equipment to ensure smooth and unhindered operation.

7. PROJECT RECORD DOCUMENTS

A. Maintain on site, one set of the following record documents; record actual revisions to the Work:

a. Drawings.

b. Specifications.

c. Addenda.

d. Change Orders and other modifications to the Contract.

e. Reviewed Shop Drawings, Product Data, and Samples.

f. Manufacturer's instruction for assembly, installation, and adjusting.

B. Ensure entries are complete and accurate, enabling future reference by the

Government.

C. Store record documents separate from documents used for construction.

D. Record information concurrent with construction progress.

E. Specifications: Legibly mark and record at each Product section description of actual

Products installed, including the following:

a. Manufacturer's name and product model and number.

b. Product substitutions or alternates utilized.

c. Changes made by Addenda and modifications.

F. Record Documents and Shop Drawings: Legibly mark each item to record actual construction including:

a. Measured depths of foundations in relation to finish first floor datum.

b. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.

c. Measured locations of internal utilities and appurtenances concealed in construction, referenced to visible and accessible features of the Work.

d. Field changes of dimension and detail.

e. Details not on original Contract drawings.

G. Remove Architect title block and seal from all documents.

H. General Contractor shall provide red-lined as-built drawings to the A-E and BCE at the completion of the project. The A-E shall provide as-built drawings in the form of

CAD and pdf versions, upon substantial completion of the project in a format compatible with the geobase system.

8. OPERATION AND MAINTENANCE DATA

A. Submit data bound in 8-1/2 x 11-inch (216 x 279 mm) text pages, three D side ring binders with durable plastic covers.

B. Prepare binder cover with printed title "OPERATION AND MAINTENANCE

INSTRUCTIONS", title of project, and subject matter of binder when multiple binders are required.

C. Internally subdivide the binder contents with permanent page dividers, logically organized as described below; with tab titling clearly printed under reinforced laminated plastic tabs.

D. Contents: Prepare a Table of Contents for each volume, with each Product or system description identified, typed on 24-pound white paper, in three parts as follows:

a. Part 1: Directory, listing names, addresses, and telephone numbers of

Architect, Contractor, Subcontractors, and major equipment suppliers.

b. Part 2: Operation and maintenance instructions, arranged by system and subdivided by specification section. For each category, identify names, addresses, and telephone numbers of Subcontractors and suppliers. Identify the following:

i. Significant design criteria.

ii. List of equipment.

iii. Parts list for each component.

iv. Operating instructions.

v. Maintenance instructions for equipment and systems.

vi. Maintenance instructions for special finishes, including recommended cleaning methods and materials, and special precautions identifying detrimental agents.

c. Part 3: Project documents and certificates, including the following:

i. Shop drawings and product data.

ii. Air and water balance reports.

iii. Certificates.

iv. Photocopies of warranties and bonds.

E. Submit 1 draft copy of completed volumes 15 days prior to final inspection. This copy will be reviewed and returned after final inspection, with the Project Manager’s comments. Revise content of all documents sets as required prior to final submission.

F. Submit three sets of revised final volumes, within 10 days after final inspection.

9. WARRANTIES

A. Provide duplicate notarized copies.

B. Execute and assemble transferable warranty documents from Subcontractors, suppliers, and manufacturers.

C. Provide Table of Contents and assemble in three D side ring binder with durable plastic cover.

D. Prepare binder cover with printed title "WARRANTIES", and title of project.

E. Submit prior to final Application for Payment.

F. For items of Work delayed beyond date of Substantial Completion, provide updated submittal within 10 days after acceptance, listing date of acceptance as start of warranty period.

10. SPARE PARTS AND MAINTENANCE MATERIALS

A. Provide products, spare parts, maintenance and extra materials in quantities specified in individual specification sections.

B. Deliver to Project site and place in location as directed by the Project Manager; obtain receipt prior to final payment.