ESBD_401277_1748872588788_ATC871~1.PDF

PDF 61 KB Posted

Attached to
HEAT PUMP AND BOILER AND BOILER FLUE REPLACEMENTS
Solicitation number
TMD25-ANG-WJ-24150004_5_6_B1057_1363_1377
Issued by
Harris County, Texas

About this file

This document is a technical attachment (Attachment G.O) for the Ellington Air Force Base (AFB) project in Houston, Texas, dated 21 May 2024, focusing on system start-up, demonstration, and testing procedures. The attachment outlines comprehensive requirements for initiating and verifying the operational readiness of various equipment and systems, including mandatory coordination with the Project Manager, pre-start-up equipment checks, and verification of electrical and mechanical specifications. Contractors are required to provide written notifications, perform supervised start-ups, and potentially have manufacturer representatives present during initial system activation.

The document specifies detailed protocols for demonstration and instruction, requiring contractors to provide comprehensive training to owner personnel using operation and maintenance manuals, and to conduct demonstrations for both current and seasonal equipment operations. An independent firm will be hired to perform testing, adjusting, and balancing services, with mandatory reporting to the Project Manager on test observations and compliance with contract documentation. The attachment emphasizes thorough documentation, equipment verification, and systematic approach to system implementation, ensuring quality control and proper functional readiness of installed systems at the Ellington AFB facility.

View the file

Other files

File Type Posted
ESBD_401277_1748872677255_ATB408~1.PDF PDF
ESBD_401277_1748872520449_ATF409~1.PDF PDF
ESBD_401277_1748872644533_ATAC97~1.PDF PDF
ESBD_401277_1748872655152_ATBB18~1.PDF PDF
ESBD_401277_1748872126186_ATTACHMENT G.1 Direct Deposit 74-176.pdf PDF
ESBD_401277_1748872207683_ATTACHMENT G.8 B1377 System.pdf PDF
ESBD_401277_1748872139337_ATTACHMENT G.2 Application for Texas ID #_AP_152.pdf PDF
ESBD_401277_1748872577160_ATCD32~1.PDF PDF
ESBD_401277_1748872472153_AT7BBC~1.PDF PDF
ESBD_401277_1748872566336_AT04E2~1.PDF PDF
ESBD_401277_1748872162925_ATTACHMENT G.4 Mandatory Pricing Schedule.xlsx XLSX spreadsheet
ESBD_401277_1748872431050_AT9E6E~1.PDF PDF
ESBD_401277_1748872553365_ATCF02~1.PDF PDF
ESBD_401277_1748872309609_ATTACHMENT G.5 Site Location.pdf PDF
ESBD_401277_1748872197790_ATTACHMENT G.7 B1363 System.pdf PDF
ESBD_401277_1748872632942_ATC8C2~1.PDF PDF
ESBD_401277_1748872531990_ATE6CA~1.PDF PDF
ESBD_401277_1748872665557_ATTACHMENT G.W - Ellington AFB (EF) AF103_REV.pdf PDF
ESBD_401277_1748872371253_AT6F64~1.PDF PDF
ESBD_401277_1748872415459_ATFC65~1.PDF PDF
ESBD_401277_1748872621894_AT9546~1.PDF PDF
ESBD_401277_1748872396937_AT909E~1.PDF PDF
ESBD_401277_1748872599840_AT8DD5~1.PDF PDF
ESBD_401277_1748872497677_AT5BF6~1.PDF PDF
ESBD_401277_1748872186497_ATTACHMENT G.6 B1057 System.pdf PDF
ESBD_401277_1748872543207_ATF572~1.PDF PDF
ESBD_401277_1748872611679_ATE420~1.PDF PDF
ESBD_401277_1748872342568_ATTACHMENT G.9 HUB Subcontracting Plan (HSP).pdf PDF
ESBD_401277_1748872104631_TMD25-~1.PDF PDF
ESBD_401277_1748872509961_ATF9DE~1.PDF PDF
ESBD_401277_1748872487237_ATF70F~1.PDF PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT G.O - ELLINGTON AFB (EF) STARTING OF SYSTEMS

PART 1 – GENERAL

1. SUMMARY

A. This Section includes:

a. Starting systems.

b. Demonstration and instructions.

c. Testing, adjusting, and balancing.

d. Third party testing, adjusting, and balancing.

2. RELATED SECTIONS

A. Solicitation Section C Statement of Work.

B. Attachment G.G - Ellington AFB (EF) Quality Control.

C. Attachment G.P - Ellington AFB (EF) Contract Closeout.

3. STARTING OF SYSTEMS

A. Coordinate schedule for start-up of various equipment and systems.

B. Notify the Project Manager in writing seven days prior to start-up of each item.

C. Verify that each piece of equipment or system has been checked for proper lubrication, drive rotation, belt tension, control sequence, or for other conditions which may cause damage.

D. Verify that tests, meter readings, and specified electrical characteristics agree with those re- quired by the equipment or system manufacturer.

E. Verify wiring and support components for equipment are complete and tested.

F. Execute start-up under supervision of applicable Contractors' personnel in accordance with manufacturers' instructions.

G. When specified in individual specification Sections, require manufacturer to provide authorized representative to be present at site to inspect, check, and approve equipment or system installation prior to start-up, and to supervise placing equipment or system in operation.

H. Submit a written report in accordance with Section 01400 that equipment or system has been properly installed and is functioning correctly.

4. DEMONSTRATION AND INSTRUCTIONS

A. Demonstrate operation and maintenance of Products to Owner's personnel prior to final payment.

B. For equipment or systems requiring seasonal operation, perform demonstration for other sea- son within six months.

C. Utilize operation and maintenance manuals as basis for instruction. Review contents of manual with Owners' personnel in detail to explain all aspects of operation and maintenance.

D. Demonstrate start-up, operation, control, adjustment, troubleshooting, servicing, maintenance, and shutdown of each item of equipment at scheduled time at designated location.

E. Prepare and insert additional data in operations and maintenance manuals when need for additional data becomes apparent during instruction.

ELLINGTON FIELD, HOUSTON, TX 21 May 2024

F. The amount of time required for instruction on each item of equipment and system is that specified in individual sections.

5. TESTING, ADJUSTING, AND BALANCING

A. General Contractor shall pay for (Hire) for services of an independent firm to perform testing, adjusting, and balancing. The independent firm shall work with the Project

Manager in conducting operations of the performance.

B. Reports will be submitted by the independent firm to the Project Manager indicating observations and results of tests and indicating compliance or non-compliance with the requirements of the Contract Documents.