HEAT PUMP AND BOILER AND BOILER FLUE REPLACEMENTS
Solicitation number
TMD25-ANG-WJ-24150004_5_6_B1057_1363_1377
Issued by
Harris County, Texas

About this file

This document is a Quality Control attachment (Attachment G.G) for the Ellington Air Force Base (AFB) project located in Houston, Texas, dated 21 May 2024. The attachment outlines comprehensive quality assurance requirements for contractors, focusing on installation, workmanship, testing, and compliance standards for the project. The document provides detailed guidelines for monitoring product quality, adhering to manufacturers' instructions, maintaining specified tolerances, and ensuring proper installation techniques.

The attachment emphasizes the contractor's responsibilities for employing an independent testing laboratory, which must be approved by the Project Manager and perform required inspections and tests. Contractors are responsible for all testing costs, including potential re-testing due to non-compliance, and must provide necessary access and cooperation during the inspection process. The document also requires manufacturers' field services to observe site conditions, installation quality, and equipment performance, with reports to be submitted within 30 days of observation. The quality control measures are designed to ensure that all work meets or exceeds the specified standards and contract requirements.

View the file

Other files

File Type Posted
ESBD_401277_1748872677255_ATB408~1.PDF PDF
ESBD_401277_1748872520449_ATF409~1.PDF PDF
ESBD_401277_1748872644533_ATAC97~1.PDF PDF
ESBD_401277_1748872655152_ATBB18~1.PDF PDF
ESBD_401277_1748872126186_ATTACHMENT G.1 Direct Deposit 74-176.pdf PDF
ESBD_401277_1748872207683_ATTACHMENT G.8 B1377 System.pdf PDF
ESBD_401277_1748872139337_ATTACHMENT G.2 Application for Texas ID #_AP_152.pdf PDF
ESBD_401277_1748872577160_ATCD32~1.PDF PDF
ESBD_401277_1748872472153_AT7BBC~1.PDF PDF
ESBD_401277_1748872566336_AT04E2~1.PDF PDF
ESBD_401277_1748872162925_ATTACHMENT G.4 Mandatory Pricing Schedule.xlsx XLSX spreadsheet
ESBD_401277_1748872431050_AT9E6E~1.PDF PDF
ESBD_401277_1748872553365_ATCF02~1.PDF PDF
ESBD_401277_1748872309609_ATTACHMENT G.5 Site Location.pdf PDF
ESBD_401277_1748872197790_ATTACHMENT G.7 B1363 System.pdf PDF
ESBD_401277_1748872632942_ATC8C2~1.PDF PDF
ESBD_401277_1748872531990_ATE6CA~1.PDF PDF
ESBD_401277_1748872665557_ATTACHMENT G.W - Ellington AFB (EF) AF103_REV.pdf PDF
ESBD_401277_1748872371253_AT6F64~1.PDF PDF
ESBD_401277_1748872415459_ATFC65~1.PDF PDF
ESBD_401277_1748872621894_AT9546~1.PDF PDF
ESBD_401277_1748872396937_AT909E~1.PDF PDF
ESBD_401277_1748872599840_AT8DD5~1.PDF PDF
ESBD_401277_1748872497677_AT5BF6~1.PDF PDF
ESBD_401277_1748872186497_ATTACHMENT G.6 B1057 System.pdf PDF
ESBD_401277_1748872588788_ATC871~1.PDF PDF
ESBD_401277_1748872543207_ATF572~1.PDF PDF
ESBD_401277_1748872611679_ATE420~1.PDF PDF
ESBD_401277_1748872342568_ATTACHMENT G.9 HUB Subcontracting Plan (HSP).pdf PDF
ESBD_401277_1748872104631_TMD25-~1.PDF PDF
ESBD_401277_1748872487237_ATF70F~1.PDF PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT G.G - ELLINGTON AFB (EF) QUALITY CONTROL

PART 1 – GENERAL

1. SUMMARY

A. This Section includes:

a. Quality assurance – control of installation.

b. Tolerances.

c. References.

d. Mockup.

e. Inspecting and testing laboratory services.

f. Manufacturers’ field services and reports.

2. RELATED SECTIONS

A. Attachment G.T - Ellington AFB (EF) Post Award Submittals: Submission of manufacturers’ instructions and certificates.

B. Attachment G.M - Ellington AFB (EF) Material Equipment.

C. Attachment G.O - Ellington AFB (EF) Starting Of Systems.

3. QUALITY ASSURANCE – CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, Products, services, site conditions, and workmanship, to produce Work of specified quality.

B. Comply with manufacturers' instructions, including each step-in sequence.

C. Should manufacturers' instructions conflict with Contract Documents, request clarification from the Project Manager before proceeding.

D. Comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

E. Perform work by persons qualified to produce workmanship of specified quality.

F. Secure Products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, or disfigurement.

4. TOLERANCES

A. Monitor tolerance control of installed Products to produce acceptable Work. Do not permit tolerances to accumulate.

B. Comply with manufacturers' tolerances. Should manufacturers' tolerances conflict with Contract Documents, request clarification from the Project Manager before proceeding.

C. Adjust Products to appropriate dimensions; position before securing Products in place.

5. REFERENCES

A. For Products or workmanship specified by association, trade, or other consensus standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.

B. Conform to reference standard by date of issue current on date of Contract

Documents, except where a specific date is established by code.

C. Obtain copies of standards where required by product specification sections.

ELLINGTON FIELD, HOUSTON, TX 21 May 2024

D. The contractual relationship, duties, and responsibilities of the parties in Contract nor those of the Architect or the Project Manager shall not be altered from the Contract

Documents by mention or inference otherwise in any reference document.

6. INSPECTING AND TESTING LABORATORY SERVICES

A. Contractor shall employ and pay for specified services of an independent firm to perform inspecting and testing. The independent lab shall be approved by the Project

Manager prior to use and should be submitted in sufficient time to eliminate delay.

B. The independent firm will perform inspections, tests, and other services specified in individual specification sections and as required by the Project Manager. Test reports are required to be submitted within 3 working days of each test performed.

C. Inspecting, testing, and source quality control may occur on or off the project site.

Perform off-site inspecting or testing as required by the Project Manager.

D. Reports will be submitted by the independent firm to the Project Manager and the

Contractor, in duplicate, indicating observations and results of tests and indicating compliance or non-compliance with Contract Documents.

E. Cooperate with independent firm; furnish samples of materials, design mix, equipment, tools, storage, safe access, and assistance by incidental labor as requested.

F. Notify the Project Manager and independent firm in writing 24 hours prior to expected time for operations requiring services.

G. Make arrangements with independent firm and pay for additional samples and tests required for Contractor's use.

H. Testing or inspecting does not relieve Contractor to perform Work to contract requirements.

I. Retesting required because of non-conformance to specified requirements shall be performed by the same independent firm on instructions by the Project Manager.

Payment for all testing services (including re-testing) will be the responsibility of the

Contractor.

7. MANUFACTURERS’ FIELD SERVICES AND REPORTS

A. When specified in individual specification sections, require material or Product suppliers or manufacturers to provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, start-up of equipment, test, adjust and balance of equipment as applicable, and to initiate instructions when necessary.

B. Submit qualifications of observer to the Project Manager 30 days in advance of required observations. Observer subject to approval of the Project Manager.

C. Report observations and site decisions or instructions given to applicators or installers that are supplemental or contrary to manufacturers' written instructions.

D. Submit report in duplicate within 30 days of observation to Architect for information if applicable.