About this file

This document is an attachment to a contract for materials and equipment management at Ellington Field (EF) in Houston, Texas, involving the U.S. Air Force or related government agency. The attachment provides comprehensive guidelines for transportation, handling, storage, and protection of products, with specific instructions for contractors regarding product options, substitutions, and material management protocols. The document outlines detailed procedures for inspecting shipments, storing materials in various conditions, and managing potential product substitutions during the project.

The attachment includes provisions for material storage compensation, which requires contractors to submit an inventory of stored materials with supplier invoices, with payment limited to the actual cost of materials. The document establishes a structured process for requesting product substitutions, requiring detailed documentation and pre-approval from the Project Manager. Contractors must demonstrate that proposed substitutions meet or exceed specified product quality, provide equivalent warranties, and coordinate installation without additional costs to the owner. The guidelines emphasize maintaining product integrity, preventing damage, and ensuring compliance with manufacturer and contract specifications.

View the file

Other files

File Type Posted
ESBD_401277_1748872677255_ATB408~1.PDF PDF
ESBD_401277_1748872520449_ATF409~1.PDF PDF
ESBD_401277_1748872644533_ATAC97~1.PDF PDF
ESBD_401277_1748872655152_ATBB18~1.PDF PDF
ESBD_401277_1748872126186_ATTACHMENT G.1 Direct Deposit 74-176.pdf PDF
ESBD_401277_1748872207683_ATTACHMENT G.8 B1377 System.pdf PDF
ESBD_401277_1748872139337_ATTACHMENT G.2 Application for Texas ID #_AP_152.pdf PDF
ESBD_401277_1748872472153_AT7BBC~1.PDF PDF
ESBD_401277_1748872566336_AT04E2~1.PDF PDF
ESBD_401277_1748872162925_ATTACHMENT G.4 Mandatory Pricing Schedule.xlsx XLSX spreadsheet
ESBD_401277_1748872431050_AT9E6E~1.PDF PDF
ESBD_401277_1748872553365_ATCF02~1.PDF PDF
ESBD_401277_1748872309609_ATTACHMENT G.5 Site Location.pdf PDF
ESBD_401277_1748872197790_ATTACHMENT G.7 B1363 System.pdf PDF
ESBD_401277_1748872632942_ATC8C2~1.PDF PDF
ESBD_401277_1748872531990_ATE6CA~1.PDF PDF
ESBD_401277_1748872665557_ATTACHMENT G.W - Ellington AFB (EF) AF103_REV.pdf PDF
ESBD_401277_1748872371253_AT6F64~1.PDF PDF
ESBD_401277_1748872415459_ATFC65~1.PDF PDF
ESBD_401277_1748872621894_AT9546~1.PDF PDF
ESBD_401277_1748872396937_AT909E~1.PDF PDF
ESBD_401277_1748872599840_AT8DD5~1.PDF PDF
ESBD_401277_1748872497677_AT5BF6~1.PDF PDF
ESBD_401277_1748872186497_ATTACHMENT G.6 B1057 System.pdf PDF
ESBD_401277_1748872588788_ATC871~1.PDF PDF
ESBD_401277_1748872543207_ATF572~1.PDF PDF
ESBD_401277_1748872611679_ATE420~1.PDF PDF
ESBD_401277_1748872342568_ATTACHMENT G.9 HUB Subcontracting Plan (HSP).pdf PDF
ESBD_401277_1748872104631_TMD25-~1.PDF PDF
ESBD_401277_1748872509961_ATF9DE~1.PDF PDF
ESBD_401277_1748872487237_ATF70F~1.PDF PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT G.M - ELLINGTON AFB (EF) MATERIAL EQUIPMENT

PART 1 – GENERAL

1. RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and

Supplementary Conditions, apply to this Section.

2. SUMMARY

A. This Section includes:

a. Transportation and handling

b. Storage and protection

c. Product options

d. Substitutions

3. TRANSPORTATION AND HANDLING

A. Transport and handle Products in accordance with manufacturer's instructions.

B. Promptly inspect shipments to ensure that Products comply with requirements, quantities are correct, and Products are undamaged.

C. Provide equipment and personnel to handle Products by methods to prevent soiling, disfigurement, or damage.

4. STORAGE AND PROTECTION

A. Store and protect Products in accordance with manufacturers' instructions, with seals and labels intact and legible.

B. Store sensitive Products in weather tight, climate-controlled enclosures.

C. For exterior storage of fabricated Products, place on sloped supports, above ground.

D. Provide bonded off-site storage and protection when site does not permit on-site storage or protection.

E. Cover Products subject to deterioration with impervious sheet covering. Provide ventilation to avoid condensation or potential degradation of Product.

F. Store loose granular materials on solid flat surfaces in a well-drained area. Prevent mixing with foreign matter.

G. Provide equipment and personnel to store Products by methods to prevent soiling, disfigurement, or damage.

H. Arrange storage of Products to permit access for inspection. Periodically inspect to verify Products are undamaged and are maintained in acceptable condition.

I. Payment for materials stored on site will be made only when the request is accompanied by an inventory of stored materials along with copies of the supplier invoices for the stored materials. Only actual cost of the materials stored will be compensated.

5. PRODUCT OPTIONS

A. Products Specified by Reference Standards or by Description Only: Any Product meeting those standards or description.

B. Products Specified by Naming One or More Manufacturers: Products of manufacturers named and meeting specifications, no options or substitutions allowed.

C. Products Specified by Naming One or More Manufacturers with a Provision for

ELLINGTON FIELD, HOUSTON, TX 21 May 2024

Substitutions: Submit a request for substitution for any manufacturer not named in accordance with the following article.

6. SUBSTITUTIONS

A. Project Manager will consider requests for Substitutions during the submittal phase of the project.

B. Substitutions may be considered when a Product becomes unavailable through no fault of the Contractor.

C. Document each request with complete data substantiating compliance of proposed

Substitution with Contract Documents.

D. A request constitutes a representation that the Contractor:

a. Has investigated proposed Product and determined that it meets or exceeds the quality level of the specified Product.

b. Will provide the same warranty for the Substitution as for the specified

Product.

c. Will coordinate installation and make changes to other Work which may be required for the Work to be complete with no additional cost to Owner.

d. Waives claims for additional costs or time extension which may subsequently become apparent.

E. Substitutions will not be considered when they are indicated or implied on shop drawing or product data submittals, without separate written request, or when acceptance will require revision to the Contract Documents.

F. Substitution Submittal Procedure:

a. Submit three copies of request for Substitution for consideration on

Substitution Request Form attached to this section. Limit each Substitution

Request Form to one proposed Substitution.

b. Submit shop drawings, product data, and certified test results attesting to the proposed Product equivalence.

c. The Project Manager will notify Contractor in writing of decision to accept or reject re- quest.

G. If request for substitution is not accepted by the government, Contractor is responsible for sup- plying item as originally specified or an acceptable substitution without additional cost to the Owner.