About this file
This is a technical application procedure document for EcoTherm thermoplastic road marking material produced by Crown USA, Inc. The document outlines the standard application procedures for applying alkyd thermoplastic line markings on both asphalt and Portland cement concrete (PCC) road surfaces. Key application requirements include ensuring road surfaces are clean and dry, removing curing compounds from new concrete, and applying sealer primer to aged asphalt with exposed aggregate. The material must be heated to temperatures between 390–440°F depending on ambient conditions, with specific temperature ranges recommended for varying environmental conditions ranging from 50–90°F and above. The procedure specifies that new asphalt should cure for 3–5 days before thermoplastic application to minimize tracking, and strictly prohibits mixing hydrocarbon and alkyd materials. Glass spheres must be applied uniformly at optimal rates of 8–10 lbs./100 ft² to achieve proper retro-reflectivity, with application methods including pressurized or gravity devices.
The document emphasizes critical safety requirements, including avoiding application when road surface and ambient temperatures are below 50°F, preventing material overheating beyond 440°F to avoid flashing or ignition, and implementing proper first-aid procedures for burns caused by hot molten material. Material storage must occur in cool, dry locations with protective covering to prevent moisture damage. The document includes contact information for Crown USA, Inc., located in Woodbury, Georgia, with telephone and fax numbers and a website provided for additional product information and support. No pricing, contract terms, renewal options, or procurement timeline information is included in this technical procedures document.
View the file
Other files
Show 40 more
Latest 50 of 86 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EcoTherm Standard Application Procedure
1) Road must be clean and dry to maximize bonding. Sweep or blow debris from the road.
2) When applying on new concrete, all curing compound should be removed before sealer application. Apply
Crown’s recommended Sealer Primer to PCC and aged asphalt with a significant amount of exposed aggregate according to manufacturer’s recommended procedures. Make certain all solvent has evaporated and sealer has dried. Solvent left in the sealer will cause obstructions in the line commonly referred to as blistering and pin holing. If a sealer is applied at a heavier mil thickness, solvent can be trapped beneath the top dry film resulting in the same type of problem.
3) Crown USA, Inc. recommends that new asphalt be allowed to cure for 3 to 5 days before applying alkyd thermoplastic. However, tracking may still occur based on the condition of the asphalt. Using temporary paint for traffic control and giving the asphalt time to cure before applying thermoplastic will reduce tracking of the asphalt liquid onto the thermoplastic line.
4) Do not mix hydrocarbon and alkyd.
5) Heat the material to 400 – 440°F in equipment with agitation. At ambient temperatures of 50 – 60°F, apply materials at 420 – 440°F. At ambient temperatures of 85 – 90°F, apply materials at 400 – 420°F. For inlaid, recessed applications, when ambient temperatures are 50 – 90°F, materials can be extruded at 390 – 420°F, due to the increased application thickness.
6) Do not apply material when road surface and ambient temperatures are below 50°F. Wind will cause material cooling in spray and ribbon gun applications. To compensate for this, apply material at upper end of the application range (420 – 440°F). During high road and ambient temperatures greater than 85°F, apply material at lower end of the application range (400 – 420°F) to facilitate cooling. Set times may increase slightly when temperatures exceed 85°F.
7) Avoid contact with hot material. Do not breathe hot fumes. Heating material above 440°F may cause material to flash or ignite (refer to SDS for details).
8) Apply glass spheres uniformly using pressurized or gravity devices. Optimal rates of application range from 8
– 10 lbs./100 ft2 depending on application method and glass spheres used. Flooding of glass beads results in reduced retro-reflectivity.
9) Hot molten thermoplastic will burn skin. Do not attempt to remove the thermoplastic from the skin. Cool under running water and seek medical attention immediately (refer to SDS).
10) Always store material in a cool dry place. If stored outside, always cover material to prevent damage, which may be caused by moisture.
Crown USA, Inc.
35 Industrial Park Drive, P.O. Box 789, Woodbury, GA 30293
Phone: (706) 553-9500 Fax: (706) 553-9501 www.crownusa.com