21d_Navigation_Report.pdf

PDF 3 MB Posted

Attached to
WA RRP RIDG 100(2), RIVER S BRIDGE REPLACEMENT Federal contract opportunity
Solicitation number
DTFH7017B00007
Issued by
Department of Transportation Federal Highway Administration

About this file

21d_Navigation Report

View the file

Other files for this federal contract opportunity

Other files attached to WA RRP RIDG 100(2), RIVER S BRIDGE REPLACEMENT, newest first.
File Type Posted
Bid_Opening_Summary.pdf PDF
Q&A_10-1-18.pdf PDF
Public_Notice_1981.pdf PDF
Finding_of_Fact_1958.pdf PDF
Amendment_A007.pdf PDF
Original_Permit_ACOE_1958.pdf PDF
Public_Notice_1958.pdf PDF
(6)_Ridgefield_WQDataTracker_FINAL_081815_ToClient.xlsx XLSX spreadsheet
River_S_Revised_Cross-Sections_Line_RS1_Sta_13+50_to_17+00.pdf PDF
Finding_of_Fact_1981.pdf PDF
Permit_amendment_dated_1982.pdf PDF
Amendment_A006.pdf PDF
Q&A_9-26-18.pdf PDF
Revised_RiverS_APP_C.pdf PDF
Amendment_A005.pdf PDF
Revised_RiverS_APP_D.pdf PDF
Revised_RiverS_APP_E.pdf PDF
FIS_Vol_1_of_2_-_53011CV001A.pdf PDF
RiverS_APP_C.pdf PDF
RiverS_APP_E.pdf PDF
RiverS_APP_D.pdf PDF
FIS_Vol_2_of_2_-_53011CV002A.pdf PDF
RiverS_APP_B.pdf PDF
RiverS_APP_A.pdf PDF
A0004_River_S.pdf PDF
Q&A_9-20-18.pdf PDF
Q&A_9-14-18.pdf PDF
Amendment_A003.pdf PDF
Amendment_A002.pdf PDF
Q&A_9-13-18.pdf PDF
Amendment_A001.pdf PDF
Q&A_9-5-18.pdf PDF
Q&A_9-4-18.pdf PDF
19_Cross_Sections-WA_RRP_RIDG_100(2).pdf PDF
20d_GR14-15_River_S_Bridge_Replacement,_Final_Geotech_Report,_Aug_2016.pdf PDF
20c_GR14-15_Geotech_Report.pdf PDF
Draft_20170919_WQMPP_Plan_WA_RRP_RIFG_100(2)_River_S_Bridge_Replace.pdf PDF
21c_Hydraulics_Report.pdf PDF
IFB.pdf PDF
22c_Access_Rd_Geometry.xml XML file
19a_River_'S'_Earthwork.pdf PDF
SWPPP_WA_RRP_RIDG_100(2).pdf PDF
01b_Plan_Set-WA_RRP_RIDG_100(2)_Updated_07242018.pdf PDF
22a_S_Refuge_Rd_Geometry.xml XML file
21b_Bridge_Inspection_Report.pdf PDF
20a_GM_08-12_Geotech_Memo.pdf PDF
21a_Asbestos_Inspection_and_Reporting.pdf PDF
20b_GM_08-12_Ridgefield_Existing_Condition_Assessment.pdf PDF
22b_Auto_Tour_Rt_Geometry.xml XML file
09_Bridge_and_Seismic_Design_Standards-WA_RRP_RIDG_100(2).pdf PDF
Show all 50

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ridgefield Wildlife River ‘S’ Unit Access Bridge

Lake River Navigation Assessment

(This page intentionally left blank.)

Table of Contents

EXECUTIVE SUMMARY

Ordinary High Water Mark

SECTION 1: INTRODUCTION AND OBJECTIVES

SECTION 2: STUDY AREA DESCRIPTION

2.1 McCuddy’s Marina

2.2 Felida Marina

SECTION 3: METHODOLOGY

3.1 Digital Data Analysis

3.2 Field Verification

3.2.1 Abney Level

3.2.2 25-foot Survey Rod

3.3 Selection of Measurement Method

SECTION 4: EXISTING HEIGHT OBSTRUCTIONS

SECTION 5: BOAT INVENTORY

SECTION 6: HOUSEBOAT INVENTORY

SECTION 7: USER INTERVIEWS

7.1 Port of Ridgefield

7.2 McCuddy’s Marina

7.3 Felida Marina

7.4 Vancouver Lake Sailing Club

7.5 Vancouver Lake Rowing Club

SECTION 8: CLEARANCE DEMAND

8.1 River Stage Fluctuation

8.1.1 River Stage in the Portland Area

8.1.2 River Stage on Lake River

8.2 Maximum Heights Found

8.3 Dredge Limits Set by USACE

8.4 Concluding Observations

SECTION 9: REFERENCES

Appendix A

Appendix B

Appendix C

Land Uses

Zoning Designations

Shoreline Management Act and Growth Management Act

Development Opportunities

References

EXECUTIVE SUMMARY

This River Navigation Assessment surveyed existing traffic on Lake River to support preliminary planning for a new bridge to cross Lake River between the City of Ridgefield, Washington and the Ridgefield National Wildlife Refuge. The potential river traffic identified is primarily from two houseboat marinas, sailboats located at the marinas, a few recreational craft from the Port of Ridgefield boat ramp, Vancouver Lake Sailing Club’s sailboats, and Vancouver Rowing Club’s rowing boats. Houseboats were counted and indexed from aerial photography with Light Detection Land Ranging (LiDAR) Survey with an on-site survey to verify dimensions and identified new or replaced vessels.

The field study found that the current highest houseboats between the two marinas is three stories high, located on McCuddy’s Marina, with a height of 34 feet. Two McCuddy’s residents currently own and actively use their sailboats. The sailboats’ masts are 48-feet and 55-feet tall (measured from water line to top of the mast). McCuddy’s Marina residents live downriver of the existing bridge; therefore, they do not currently have any existing clearance issues except for a Clark PUD (75’-V) power line paralleling Division Street in Ridgefield (see authorized permit in attachments).

Houseboats located at the second marina, Felida, are upriver of the existing bridge which currently limits vessel clearances. The current highest houseboat at Felida is 29-feet tall, and one sailboat with 34-foot mast (retractable).

In order to estimate the current and anticipated future traffic on Lake River, local people/organizations that rely economically on the river were interviewed as they have a significant stake in the new bridge construction. The interviewees provided information on current and anticipated future vessel traffic for the river. Future traffic, according to the representatives of each organization, will be dredges for the maintenance of the river, and three story high house boats (estimated at 34 feet) destined for Felida Marina.

It should be observed that the taller of the existing houseboats at Felida Marina were likely completed on-site, and considering the restrictions imposed by the existing bridge, the hulls of future three-story house boats would have to be moved upriver at an incomplete stage of construction and upper stories added on-site.

The U.S. Coast Guard (USCG) Bridge Division informed the Federal Highway Administration (FHWA) that they consider the entire length of Lake River to be under their jurisdiction. The USCG Bridge Division published data has previously determined that the tidally effected zone on Lake River ends at MP 3.3 (aligned with what portion of the river bathymetry is currently mapped and also just downstream of the existing bridge), but considers all of Lake River to be navigable.

The vertical clearance of a new bridge needed to accommodate current use will depend on location. If new bridge is located downriver of the existing bridge (MP 3.3 or less), clearance would have to be 34-feet high to accommodate all house boats, and 55-feet high to accommodate all sailing boats. For bridge alignments upriver (MP 3.3 or more) a clearance restriction matching the existing bridge low chord elevation of 40.5 feet (NAVD 88), would maintain the current level of navigational access.

Datum correlation at the River S Bridge:

• CRD = 0.58 NGVD 1929 = 0.98 NGVD 1947 = 4.26 NAVD 1988

US Army Corps of Engineers (USACE) has an existing dredge project: “a channel 6-feet deep, 100-feet wide and 3-miles long from the Columbia River.” This 100-foot wide channel width would need to be maintained and not impacted during construction. To not impact the dredge channel, the recommended horizontal main span for any new bridge will need to be 100 feet + 20 feet from edge of dredge channel to centerline pier for a total main span of 140 feet.

A land use assessment is also included within the report (Appendix C). This is an assessment of existing tax lots, land use, zoning, and potential development opportunities in the project area. The assessment study area includes the Ridgefield Wildlife Refuge, lands adjacent to Lake River, and associated connected waters.

Through discussion between FHWA and USCG, the guidance provided on how to determine vertical clearances for a bridge is to establish an approximate the average annual river stage with cross referencing to when the tallest vessels routinely use Lake River. After this water level is determined, add the height of vessels to be accommodated to determine the proposed vertical clearance. This would apply to all users downstream of the existing bridge.

Upstream users’ needs would be assessed, but if a new bridge is proposed at the current site, deference would be given to the existing clearance as this clearance pre-dates any of the current upstream uses of Lake River.

The existing bridge has a low chord elevation of 40.5 feet NAVD 88. Assessing the vertical clearance of the existing bridge is dependent upon the water level in Lake River correlated to the current river gage information. Lake River has U.S. Geological Survey (USGS) gage (recorded in National Geodetic Vertical Datum of 1929 [NGVD 1929]) but has only been in service for two years. Over that time, Lake River gage has recorded high water level of

24.15 feet and a low of 9.40 feet (adjusted from NGVD 1929 to NAVD 88).

Ordinary High Water Mark

The Ordinary High Water Mark (OHWM) as defined by the Shoreline Management Act (SMA) is a biological vegetation mark. According to Revised Code of Washington (RCW) 90.58.030, the definition of Ordinary High Water Mark is the “ordinary high water mark on all lakes, streams, and tidal water is that mark that will be found by examining the bed and banks and ascertaining where the presence and action of waters are so common and usual, and so long continued in all ordinary years, as to mark upon the soil a character distinct from that of the abutting upland, in respect to vegetation as that condition exists on June 1, 1971, as it may naturally change thereafter, or as it may change thereafter in accordance with permits issued by a local government or the department ( ecology):

Provided, that in any area where the ordinary high water mark cannot be found, the ordinary high water mark adjoining salt water shall be the line of mean higher high tide and the ordinary high water mark adjoining fresh water shall be the line of mean high water”. The OHWM line was documented and surveyed the FHWA in 2012 as 11.70 feet NAVG 1988.

Additionally, for determination of State Lands Boundary, the U.S. Fish and Wildlife Service (USFWS) through a contract with Minister-Glaeser Surveying, Inc. (2200 E. Evergreen Blvd, Vancouver, WA 98661; Phone: (360) 694-3313, Fax: (360) 694-8410, dar@mgsurvey.com), performed a survey, in 2000, to update a WA Department of Natural Resources Permit. To determine the Mean High Water (MHW) (river side property boundary) at Columbia River mile 90 (equivalent River mile to the River S access bridge), Minister-Glaeser documented and recorded with Clark County WA (Book 25, page 50) the State Lands Boundary. Note 3 of this recorded document states, “ Ordinary High Water Line: The Ordinary High Water Line, (OHWL) for the Columbia River Mile 89-92 was computed from the USACE publication ‘Flood Profiles, CL-03-116, April 1973 Revision.’ The OHWL at the Columbia River Mile 90 is 13.6 Columbia River Datum (CRD) or 17.86 NAVD 1988.” This elevation will be used for determination of State Aquatic Lands limits.

Using the SMA determined OHWM as an average water level (which matches closely to the average between high and low events) this places the existing bridge vertical clearance at

40.5 (NAVD 88) – 11.70 (NAVD 88) = 28.80 feet (NAVD 1988).

There are slightly less than two years of USGS river stage data available for Lake River, but on the basis of that limited data it would appear that the average annual maximum river stage is between 22.78 and 24.15 feet (adjusted from NGVD 1929 to NAVD 88), the average annual river stage is between 11.28 and 16.28 feet, and the average annual minimum river stage is 9.40 feet (NAVD 88). For this report and the decision making process, vertical and horizontal clearances are recommended as follows:

Location Vertical Clearance (NAVD 88) Horizontal Clearance (denotes centerline pier to centerline pier spacing)

MP 0.0 to

MP 3.3

55 feet + OHW (11.70 feet) +2 feet (freeboard) = 68.70 feet

140 feet

MP 3.3 to

MP 11

28.80 feet 140 feet

Note: All clearances are referenced to NGVD 1947.

SECTION 1: INTRODUCTION AND OBJECTIVES

This River Navigation Assessment surveyed existing and future vessel traffic on Lake River to support preliminary design plans for a new bridge to cross Lake River between the City of Ridgefield, Washington and the Ridgefield National Wildlife Refuge. Types, sizes, and operational characteristics of the vessels that transit through Lake River and Vancouver Lake were identified. The area surveyed began at the mouth of Lake River, where it joins the Columbia River, and ended in Vancouver Lake. Vessels were counted and indexed from aerial photography, Reference 1 and Reference 2. Dimensions were estimated from an analysis of a 2005 LiDAR research, Reference 3 and Reference 4. An on-site survey verified dimensions and identified new or replaced vessels since 2005.

The two assessment methods used in the clearance study are discussed in Section 3. The desk top study consisted of importing geographical survey data into Rhinoceros 3D (Rhino), Reference 6, where approximate heights and lengths were measured. The second method was on-site survey, where FHWA representatives checked the accuracy of measures from the office activity and any changes that occurred subsequent to when the geographical data was taken. Results from the electronic data and on-site survey are in Section 5 Boat Inventory and Section 6 Houseboat Inventory.

Interviews seeking to characterize current and anticipated vessel traffic on Lake River were conducted with local people and organizations that rely economically or recreationally on the river, and therefore have a higher stake in the development of the new bridge. Current and future plans of these organizations are in Section 7.

Information from the National Oceanic and Atmospheric Administration (NOAA), USGS, and the USCG were considered in order to assess the appropriate vertical reference datum and the potential role of fluctuations in river stage. Section 8 addresses these topics.

This report provides information about the study methods used, and existing conditions found on Lake River. The data in this report are appropriate for consideration in establishing agency positions regarding design of horizontal and vertical clearance for a new bridge.

SECTION 2: STUDY AREA DESCRIPTION

Lake River originates from Vancouver Lake and flows from south to north, toward its juncture with the Columbia River. An aerial view is provided in Figure 1. The area surveyed in this study extends from the Lake River entrance to Vancouver Lake. The juncture of Lake River with the Columbia River is the origin for distance measured along the axis of Lake River.

According to Reference 11 the U.S. Coast Guard has determined that tidal influence on Lake River extends to mile 3.3 (due to limits of bathymetry), corresponding to a point slightly below (down river) the existing timber bridge over Lake River. By U.S. definition, a waterway is navigable if it is “subject to the ebb and flow of the tide” or “presently used and/or susceptible to use in its natural condition, or by reasonable improvement, as a means to transport interstate or foreign commerce.” McCuddy’s Marina and Felida Marina have significant concentrations of houseboats. Houseboats result in the largest horizontal clearance demands for the Lake River population. McCuddy and Felida residents also have vertical uses that surpass houseboat heights. Though currently few in number (three), the masts of large sailboats impose the greatest vertical clearance demand. Furthermore, the sailboats are likely to transit Lake River from their respective customary mooring locations (two in McCuddy’s and one in Felida) to the juncture of Lake River and Columbia River with greater frequency than the relatively rare to non-existent movements of houseboats.

Global Positioning System (GPS) waypoints taken during the on-site survey for landmarks identified in the study area are presented in Table 1. Lake River joins with Vancouver Lake at approximately River Mile 11. According to USACE there are 11 miles of navigable length along Lake River, and there are three miles identified as an authorized dredging corridor “under authorized project.” (Reference 14).

Table 1 Waypoints of Areas Surveyed

Location Latitude Longitude River Mile

Mouth of Lake River N45º 50.589’ W122º 46.916’ 0

Port of Ridgefield Boat Ramp N45º 48.964’ W122º 45.059’ 2.4

North of McCuddy’s Marina N45º 48.964’ W122º 45.059’ 2.4

South of McCuddy’s Marina N45º 48.696’ W122º 44.680’ 3.0

D/S of Existing Bridge N45º 48.438’ W122º 44.434’ 3.3

North of Felida Marina N45º 42.652’ W122º 43.481’ 10.4

South of Felida Marina N45º 42.381’ W122º 43.370’ 10.7

Vancouver Lake Sailing Club N45º 40.432’ W122º 42.045’ N.A

Vancouver Lake Rowing Club N45º 40.200’ W122º 44.500’ N.A

Saint Helens Tidal Gauges N45º 51.900’ W122º 47.800’ N.A

The aerial photos are from 2007 for McCuddy’s Marina and 2011 for Felida, see Reference 1 and Reference 2. The Geographic Information System (GIS) data is from a 2005 LiDAR survey, Reference 3 and Reference 4. The aerial photos were used to count and index the houseboats, as seen in Figure 2 and Figure 3. The houseboats were indexed from North (closer to Columbia River) to South (toward Vancouver Lake), and from West (toward Oregon) to East (toward Ridgefield/Clark County WA).

Figure 1. Aerial Picture of Area Surveyed (north is to the left)

2.1 McCuddy’s Marina

The houseboat indexing for McCuddy’s Marina is seen in Figure 2. Fifty-five houseboats are identified from the Reference 1 aerial photography taken in 2007.

During the field survey, the FHWA team had access to the entire length of the docks, but not permitted to board the houseboats and sailboats. However, houseboat owners were informed of the study by a letter prior to the verification work. When owners were present, permission to go aboard and obtain measurements with greater precision was requested. The survey team performed the study throughout the entire Marina.

Figure 2. McCuddy’s Marina

2.2 Felida Marina

The houseboat indexing for Felida Marina is seen in Figure 3. Forty three houseboats are identified from the Reference 2 aerial photography taken in 2011.

During the field survey, the FHWA team had access to the entire length of the dock, but not permitted to board all watercraft. However, houseboat owners were informed of the study by a letter prior to the field verification work. Therefore, when owners were present, permission to go aboard and obtain measurements with greater precision was requested. The survey team performed the study throughout the entire Marina.

The

Figure 3. Felida Marina

SECTION 3: METHODOLOGY

Analysis of the houseboats at McCuddy’s and Felida utilized two methods: electronic data analysis and on-site field measurements. The electronic data was used to find length, beam, and height of all houseboats present during a 2005 survey. Dimensions of the largest vessels were subsequently checked during the on-site survey.

The on-site field measurement had four objectives: 1) to reconcile the electronic data; 2) to identify the exchange or addition of houseboats since the electronic data was acquired; 3) to verify the traffic and uses of the river; and 4) to account for sailboats (or other vessels taller than the houseboats). Data verification involved two different field methods, a survey grade rod and an Abney level, each described in Section 3.2. The on-site survey found a height and at least one horizontal dimension (length or beam) of a measured vessel. If the owner was present and permission was given to board the vessel, then the second horizontal dimension could be measured. For houseboats that were not present during a 2005 survey, only the on-site data is available. In these cases, only one horizontal dimension may be known.

Not all houseboats were measured during the on-site survey. A houseboat was measured if it was: 1) new or replaced since the 2005 survey; or 2) a two-story houseboat as identified in the 2005 survey that was not adjacent to a taller houseboat. Among neighboring houseboats, only the tallest were measured. Photographs of the largest houseboats are in Appendix B.

To check for exchanged or new properties, sailboats, and overhead interferences, the FHWA team surveyors spent a day travelling the extent of Lake River into Vancouver Lake, documenting and measuring any existing obstructions to vertical clearance and identifying houseboats and other vessels with the potential to affect design clearances for the potential new bridge.

The extent of on-water use was verified through interviews with five different organizations that routinely engage in activities on Lake River and Vancouver Lake. These interviews provided a baseline for documenting current use and predicting future traffic on the greater Lake River waterway. The interviews are in Section 7 of this report.

After both analyses were concluded, results from both methods were compiled and compared. Wherever discrepancies were identified, on-site survey measurements were accorded a higher priority than measures from digital data analysis.

3.1 Digital Data Analysis

The GIS data collected in the LiDAR survey, Reference 3 and Reference 4, generated a triangulated irregular network (TIN). TIN control points were contained in Design Files. When the drawing was opened in Rhino, points representing the houseboats were visible. The highest and furthest apart points for each houseboat were identified. A bounding box for each houseboat was drawn between these points by connecting six points for the roof and four points for the base; see Figure 4. If the points selected were incoherent, they were adjusted manually. Figure 4 is an example of the houseboat control point selection in Rhino.

The accuracy of the electronic data is approximately ±1/2 feet. The source of error comes primarily from the native accuracy of the GIS data, and the selection of ‘points’ to draw a bounding box around each houseboat. The bounding box provided the dimensions for maximum length, breadth, and height.

Figure 4 Bounding Box from TIN Control Points in Rhino3D

3.2 Field Verification

During the on-site survey, the FHWA team documented existing objects that may impose marine navigation clearance restrictions, performed interviews with Lake River waterway users (see Section 7), accounted for new or revised properties and sailboats, and checked the precision of the GIS data analysis by identifying and measuring the tallest houseboats.

The first step of the field survey effort was to perform river reconnaissance through the entire length of Lake River and Vancouver Lake to check existing restrictions to navigation clearance and possible areas not identified prior to the trip. Following completion of this general reconnaissance a more meticulous field survey of McCuddy’s and Felida Marinas commenced in order to check for data precision, sailboats, and new or revised properties.

From the dock, the tallest points of each measured houseboat were identified, and based upon circumstances, either of two methods was used to find the height, see

Section 3.2.1 and Section 3.2.2. Many houseboats were unattended preventing the field team from boarding the vessel to verify the outboard dimension.

Measurements and GPS waypoints were obtained for all properties of significant height.

Interviews occurred on separate dates and times, and are detailed in Section 7.

3.2.1 Abney Level

The Abney level is a simple instrument often used by foresters to determine tree heights and grade elevations. The unit measures the angle between the height of the instrument and a point on top of the object. A linear baseline measurement then forms an imaginary right triangle to enable trigonometric computation of the height of the object.

Prior to field deployment, the FHWA team tested Abney level computations against the known heights of various objects. The accuracy of the Abney level computations could be verified to within 0.1 foot provided a good baseline measurement was executed. Errors in height correlate with errors in measurements of the baseline length according to the tangent of the measured angle.

Longer baselines correspond to smaller angles and reduced errors in estimated height. When using the Abney level in the field, baseline measurements were occasionally compromised by structural setbacks to the highest point or private property restrictions. During such situations the survey team computed elevations from different locations in an attempt to quantify the tallest possible height. For accuracy, a combination of measuring tape and survey rod were used to measure the baseline, the height of the instrument and the vessel freeboard. Overall, heights estimated using the Abney level are accurate within approximately ±2 feet.

3.2.2 25-foot Survey Rod

An extendable survey grade rod, measuring to hundredths of a foot, was used to directly measure those structures whose highest point was adjacent to the dock. This height measurement could be read from an eye level scale on the reverse side of the rod. In Appendix B, there is a picture showing a team member measuring houseboat No. 29 at McCuddy’s Marina. An independent observer could also read the height from the scale on the front of the rod. The survey rod has four sources of error: 1) the reading; 2) the location of the maximum height; 3) inaccuracy in the rod itself; and 4) the compression and movement of the rod. Error sources add to an approximate error of ±1foot.

3.3 Selection of Measurement Method

Height measurement error bands using the Abney Level are thought to be ±2feet, and height measurement error bands using the survey rod are thought to be ±1foot. Therefore, error bands were not the major factor taken into account when selecting a method to measure the height of any particular point, but rather the location and accessibility of the highest point. If a location was accessible, the survey rod was chosen for efficiency and better precision. If not, then the Abney level method was chosen as less intrusive.

SECTION 4: EXISTING HEIGHT OBSTRUCTIONS

The entire length of the study area was traversed during the survey, and existing height obstructions were identified and measured. During the on-site survey, the FHWA survey team documented existing objects that may constitute restrictions to navigation clearances on Lake River. Table 2 provides a summary of existing obstructions to vertical clearance.

Table 2 Existing Heights of Obstructions (measured at 13feet USGS river stage)

Object Latitude Longitude Height Power Line 1 (North of McCuddy) N45º 49.127’ W122º 45.134’ > 70 ft Existing Bridge N45º 48.438’ W122º 44.434’ 27.1 ft Power Line 2 (Between Marinas) N45º 45.780’ W122º 44.924’ > 70 ft Power Line 3 (Between Marinas) N45º 42.771’ W122º 43.538’ > 70 ft

Other than the existing bridge, the remaining obstructions are all high power line crossings and of no significance to recommending bridge clearances. Reference 15 shows Lake River and gives “Soundings and Clearances of Bridges and overhead cables in feet at the Columbia River Datum (Mean Lower Low Water during Lowest River Stages)”. The chart shows Power Line 1 and notes an authorized clearance of 75 feet. (Reference 15) (77.30 NAVD 88). The existing bridge is shown on the navigation chart but no clearance is noted.

The vertical distance between the bottom of the existing bridge and the surface of the water was measured on site at 34.0 feet. At about the beginning of the 2011 water year, on or about 29 September 2010, the United States Geologic Survey, Water Resources Division (USGS) established a new stream gauging station 14213090, identified as “Lake River at Ridgefield, WA”, at the location of the existing wooden bridge. At the time that the survey team obtained field measures of the existing bridge clearances the USGS river stage was 7.89(NGVD 1929),

8.29 feet (NGVD 1947), 11.57 feet(NAVD 88) or 7.31 feet (CRD), according to Reference 8.

The 2010 Bridge Inspection and Appraisal Report, Reference 13, shows the vertical and horizontal bridge span clearance at 33 feet and 55.5 feet, respectively. The vertical reference datum associated with the 11 feet water level shown in Reference 13, from whence the 33 foot vertical clearance is determined, is not identified. The bridge’s horizontal navigation clearance was confirmed at 55.5 feet. Vessel traffic from, or destined to, upriver of the bridge must pass through the bridge span. The existing bridge is pictured in Figure 5.

Figure 5. Existing Bridge

Prior to 1981, the bridge had a 42-foot main span. Figure 5 illustrates the original bridge, and how the 42-foot main span was replaced by combining this span with an adjacent 16 foot span to create the new 58-foot span. This modification to increase the main span was at the request by a private contractor to the US Fish and Wildlife Service as a one-time-only removal and replacement to facilitate the dredging contract of Vancouver Lake at the expense of the private contractor.

SECTION 5: BOAT INVENTORY

The boats operating on Lake River are recreational craft, small workboats, and houseboats.

Many of the small craft operating on Lake River are launched from the Port of Ridgefield public boat ramp while many of the resident vessels are docked at the marinas. During the onsite survey, an average of 20 boats per day were seen using the boat ramp. The largest sailboats in the study area are listed in Table 3. In general, sailboat masts of this size are only removed with mechanical assistance (e.g., cranes). The tallest sailboat is pictured in Figure 6. The boat was recognized as a Cheoy Lee Offshore 40. The mast height is 55feet.

The Vancouver Lake Sailing Club (VLSC) and Vancouver Rowing Club contribute to vessel traffic on the north end of Vancouver Lake. The sailboats, rowing shells, and related craft have smaller beam than the houseboats, and therefore do not affect horizontal clearance requirements.

FHWA team members traveled to Felida and McCuddy’s marine on 10/23/2012. The team located sailboat N0.1, 3, and 4 from Table 3. The owner of the boat # 4 was not present but a neighbor reported that the owner doesn’t use the boat. The FHWA team interviewed the owner of Boat No. 1. Observations of both boats are noted below.

FHWA observations of sailboat No. 4 are as follows:

• Last date of boat licensing- 2000

• No outboard or inboard motor

• Boat covered in moss

• All teak wood members on the boat have been removed or rotted away

• Rigging ropes appear to be in very poor shape

• Mast is retractable

FHWA observation of sailboats No. 1 and 3 at McCuddy’s:

• Boats are in good working order

• Boats are currently licensed

• Boat travel downstream to the Columbia year round

Table 3 Sailboats Inventory

Location GPS Position Mast Height Length

Sailboat No.1 McCuddy’s N45º 48.921’

48ft 31ft Sailboat No.2 McCuddy’s N45º 48.905’

32ft 26ft

Sailboat No.3 McCuddy’s N45º 48.720’

55ft 40ft Sailboat No.4 Felida N45º 42.401’

34ft 23ft

Group of

VLSC N45º 40.432’

≤ 28ft ≤ 20ft

Figure 6 Largest Sailboat No. 3–55-foot Height

SECTION 6: HOUSEBOAT INVENTORY

The houseboat inventory includes 95 houseboats from the two marinas. At McCuddy’s Marina, there were three additional houseboats identified on-site that were not in the aerial photos. The new houseboats are located at the north end of the Marina. New houseboats were indexed by their relative cardinal direction to the nearest previously indexed houseboat. For example, the new three-story houseboat, S23, is south of Houseboat 23.

Table 4 summarizes the houseboats, including maximum dimensions. McCuddy’s Marina, has 52, a net change of minus three (-3) from the LiDAR research. Six were no longer there, three were new, and five were rebuilt. Thirty-five of the houseboats were single story, 16 were two stories high, and one was three stories high. At McCuddy’s Marina, the maximum height was 34 feet, and maximum beam 42 feet. The tallest houseboat is S23, Figure 7. At Felida Marina, the number of houseboats was 43, a net change of zero (0) since the LiDAR research, three were rebuilt. Seventeen of the houseboats were single story, and 26 were two stories high.

At Felida Marina, the maximum height was 29 feet and maximum beam 50 feet. The tallest houseboat at Felida is No. 13, Figure 8. All houseboats at the two marinas with more than one floor are tabulated in Appendix A.

The houseboat traffic is minimal. No houseboats were seen transiting the river during the site visit. On-site data collection shows that from 2011 to 2012, for Felida, three houseboats were rebuilt, and from 2007 to 2012, for McCuddy’s, six houses moved out, and three either moved in or were built on-site.

Table 4 Houseboat Counts and Statistics

McCuddy’s Marina Felida Marina

Additional Houseboats between 2010 and 2012

-3 (6 not there, 3 new ones, and 5 rebuilt) 0 (3 rebuilt)

Houseboats 2012 (quantity) 52 43

2-story Houseboats (quantity) 16 29

3-story Houseboats (quantity) 0

Houseboats with height ≥27 ft 1 1

Houseboats with height ≥20 ft 9 15

Maximum Width (ft) 42 50

Maximum Height (ft) 34 29

Figure 7. Tallest Houseboat at McCuddy’s Marina, No. S23–34 ft

Figure 8. Tallest Houseboat at Felida Marina, No. 13 – 29 ft

SECTION 7: USER INTERVIEWS

Five groups using the river were contacted for this study: Port of Ridgefield, McCuddy’s Marina, Felida Marina, Vancouver Sailing Club, and Vancouver Rowing Club. The group representatives discussed their current and anticipated activities related to bridge clearance and provided additional opinions about Lake River.

7.1 Port of Ridgefield

The Port of Ridgefield was represented by Mr. Brent Grenning. Mr. Grenning’s comments are summarized as follows:

The port’s main activity affecting clearance criteria is a public boat ramp, located at the north end of McCuddy’s Marina. Common vessels using the area are fishing vessels, and small pleasure boats. Occasionally, small barges with crane equipment are seen heading towards Vancouver Lake. Typically, the barges dismantle equipment to clear the existing bridge.

The Port’s forecasted activity is maintenance in the form of dredging the lower river.

Comments provided but unrelated to their current use:

Emergency vessels may also pass by the Port of Ridgefield during a flood stage.

This traffic was seen previously in 1996. At such time, emergency vessels struggled to go under the existing bridge. Furthermore, the water at Lake River is relatively stationary, meaning it can take a considerable amount of time for the Lake River stage to recede to normal conditions. In addition, sailboats with 40 feet or higher masts are often on Lake River.

7.2 McCuddy’s Marina

McCuddy’s Marina was represented by Mr. Mark McCuddy. Mr. McCuddy’s comments are summarized as follows:

The main activity of his Marina is houseboats. Any change in activity is not anticipated; the marina has a three story high houseboat and a sailboat with a mast of approximately 55 feet. The tallest sailboat currently going under the bridge is 30-feet tall due to the depth of the river.

7.3 Felida Marina

Felidas Marina’s only activity in the present and future is houseboats. Felida’s Management, was represented by Mr. Mike Roe. Mr. Roe’s comments are summarized below:

It is anticipated that house boat heights will be three stories high. During some on-site interviews, some of Mr. Roe’s clients stated that some houses were built on site, and some were brought up the river from another marina. House No.42 at Felida Marina transited under the current bridge. Mr. Roe concluded by stating his personal preference is have the new bridge top of piling provide 100 feet of vertical clearance.

7.4 Vancouver Lake Sailing Club

The Vancouver Lake Sailing Club Information Officer, Erik Troelsen, described the club’s vessel traffic and fleet. Mr. Troelsen’s comments are summarized below:

VLSC may host over a hundred vessels during regattas. However, such boats are typically trailer transported to the lake. Every few years club members sail on Lake River to and from St Helens, north of Ridgefield on west shore of the Columbia River. Future plans include sailing on Lake River every few years. The VLSC fleet consists majorly of Lightning’s, Lasers, Fireballs, Hobie Cats and A- Cats, with a maximum height of 28 feet.

Dock maintenance is another potential future use of the river. Dock pilings are often adjusted and contractors use Lake River for access to the club.

7.5 Vancouver Lake Rowing Club

Vancouver Rowing Club was represented by Mr. Alan Stewart. Mr. Stewart’s comments are summarized below:

None of the Rowing Club’s activities will affect the current criteria.

SECTION 8: CLEARANCE DEMAND

8.1 River Stage Fluctuation

The river stage on Lake River reflects three primary processes: 1) fresh water river flow; 2) astronomical tide effects; and 3) storm surges.

In Reference 7, NOAA states that the time, but not necessarily the magnitude, of astronomical tide maxima and minima can be predicted on the Columbia and Willamette Rivers, and presumably, by extension, Lake River in the Portland area.

However, because the river stage is dominated by the fresh water river flow process it is difficult to predict the magnitude of tidal effects in advance. When the river flow is high the effect of astronomical tide is small, and when the river flow is low the effect of astronomical tide is more noticeable. The dominant effect is river flow.

For the reasons given in the preceding paragraph NOAA declines to predict the magnitude of tidal fluctuations above Harrington Point, WA which is located approximately 63 miles downriver from Ridgefield, WA.

8.1.1 River Stage in the Portland Area

The U.S. Coast Guard Bridge Division in a meeting with FHWA on September 24, 2012 informed FHWA that, for Lake River, using the average annual maximum is not warranted given the historic, current, and forecasted uses of Lake River. The USCG Bridge Division suggested establishing water elevation when high vertical users are likely to use Lake River to access the Columbia River and using this as the water level basis for vertical assessment.

8.1.2 River Stage on Lake River

The USGS station 14213090 on Lake River at Ridgefield is a new river stage gage that has only been in operation since 29 September 2010. The zero datum of this gage is NGVD (1929) (Reference 16). The minimum stage measured by the USGS Lake River station was 5.72 feet (NGVD 1929) or 6.12 feet (NGVD 1947) or 9.40 (NAVD 88) and the maximum stage was 20.47 feet (NGVD 1929) or

20.87 feet (NGVD 1947) or 24.15 (NAVD 88), a range of 14.75 feet. Anecdotal reports regarding Lake River suggest that annual river stage may fluctuate through a range of 6 to 10 feet. Two essentially annual maxima have been measured since inception of the USGS Lake River gage. A maximum of

20.47 feet (NGVD 1929) was measured and recorded on 2 June 2011, and a maximum of 19.34 feet (NGVD 1929) on 3 April 2012. The average of these two sampled annual maxima is 19.91 feet (NGVD 1929) or 23.59 feet (NAVD 88).

It is suspected that the river stage at Lake River is highly correlated with that at the Columbia River at Vancouver, WA. Based on that suspension/assumption it is possible to predict that the river stage at Lake River might be on-the-order-of

22.00 feet ±0.75 when the Columbia River at Vancouver was at 25.0 foot river stage (NGVD 1929) or 28.28 feet (NAVD 88). The available data suggests that the average annual maximum river stage at Lake River is likely to be between

19.1 and 22.0 feet. FHWA conducted on site interviews with the larger boat owners to determine what river gage elevation do they typically and ideally operate at. The large sailboat at Felida was found not to be sea worthy, and the two vessels at McCuddy’s only travel downstream to the Columbia River. One of the vessels using Lake River year round, while the other typically uses Lake River only in the summer months. Both vessels have traveled out Lake River at all river stages.

For the existing bridge, assuming OHW (11.70 feet NAVD 88) as the average operating river stage, the existing bridge provides 40.5 feet – 11.70 feet = 28.80 feet of vertical clearance (NAVD 88) or 27.82 feet (CRD).

For all new bridges downstream of the existing, the two largest vessels only travel downstream from their current locations. The owners informed FHWA there was no desire to travel upstream as the river is too narrow and too shallow but with all alignment options downstream of the existing will need to traverse McCuddy’s Marina, and that the current use of high air draft (distance from water level to top of mast) is your round, initial assessments will be made for a range navigational clearances. At the extreme end, a maximum annual average river stage is estimated at 23.78 feet (NAVD 1988) and a mean annual average river stage estimated at 11.70 feet (NAVD 1988). The resulting minimum bottom chord elevation of any new bridge would be, 1- 55 feet + 2 feet (free board) + 23.78 feet = 80.78 feet (NAVD 1988) to 2- 55 feet + 2 feet (free board) + 11.70 feet = 68.70 NAVD 1988). For initial assessments, FHWA will use 68.70 feet (NAVD 1988) to perform initial screening. If options are carried forward more detailed navigational needs assessment will be developed.

8.2 Maximum Heights Found

Along the river, from north (Columbia River) to south (Vancouver Lake), the air draft dimensions of the tallest houseboats are given in Figure 12 with respect to river mile between the north and south end of McCuddy’s Marina (river miles 2.4 and

3.0 respectively) and referenced from the maximum annual elevation derived above.

Three street locations from Reference 18 are noted with vertical red lines. At and above river mile 2.63 (Pioneer St. Op. 2), there are six houseboats taller than or equal to 20 feet and one houseboat taller than or equal to 27 feet. At and above river mile

2.75 (Sargent St.), there are three houseboats taller than or equal to 20 feet and no houseboats taller than or equal to 27 feet. At and above river mile 2.78 (S. Main Ave.), there are two houseboats taller than or equal to 20 feet and no houseboats taller than or equal to 27 feet. The height of the existing bridge is shown in blue dotted line presuming a USGS Lake River stage of 20 feet.

Figure 9. Air draft of 5 tallest houseboat upriver of river mile on Lake River

8.3 Dredge Limits Set by USACE

USACE dredged channel project depths are with respect to CRD, which is 0.98 feet above NGVD (1927). The Federal Navigation Project Chart No. 18524 from 2001, Reference 10, describes the existing project: “a channel 6 feet deep, 100 feet wide and 3 miles long from the Columbia River.” The dredged depth of 6 feet dates back to 1925. According to Reference 5, the dredge depth was set by the USACE to facilitate commerce from shallow draft vessels. It is unlikely that the river will be dredged to a deeper depth. Based on Reference 10, it appears that the historical USACE dredged channel project extends from the juncture of Lake River with the Columbia River and ends at an upriver point roughly corresponding with the south extent of McCuddy’s Marina. Accordingly, it is reasonable to expect that deeper draft vessels may be unable to navigate above the historical end of the USACE dredged channel project.

Absolute navigation draft limitations throughout Lake River will depend on the river stage.

8.4 Concluding Observations

Depending on the location of the new bridge, the house boats, together with the sailboats docked at the McCuddy’s Marina, are the source of the greatest demand for bridge navigational clearances. If the new bridge is located downriver of the existing bridge, clearance is controlled by current sailboat use. The tallest sailboat measures 55 feet and combined with 2 feet of free board results in a required clearance of 57 feet. For river navigation purpose, this dimension would be additive to a base Lake River water level of 11.70 feet for a total clearance of 68.70 feet (NAVD 1988) or

67.72 (CRD). For bridge alignments upriver of the existing bridge, a clearance restriction matching the existing low chord elevation would be preserved which is

40.5 feet (NAVD 1988) or 39.52 feet (CRD).

The choice of reference Lake River stage for the vertical clearance is significant to the establishment of the absolute elevation of the underside of any fixed civil structure spanning Lake River. Using USCG in guidance provided during the September 24, 2012 meeting, combined with FHWA interviews of three tallest sailboat owners, and extrapolating the Lake River data to provide for an average annual river stage (OHW) for Lake River a base water surface is estimated to be 11.70 feet with respect to

NAVD (1988).

In setting design minimum clearances for the new bridge some margins (assume 2 feet unless matching existing bridge) beyond the dimensions of the design vessels should be included, both to account for inaccuracies in measurement and for vessel maneuvering misalignment when passing the bridge.

Location Vertical Clearance

(NAVD 1988)

Horizontal Clearance (denotes centerline pier to centerline pier spacing)

MP 0.0 to MP 3.3 55 feet + OHW(11.70 feet) +2’(freeboard) =

68.70 feet

140 feet

MP 3.3 to MP 11 28.80 feet 140 feet

SECTION 9: REFERENCES

1. McCuddy’s Marina Aerial Photo, Western Federal Land, 2007

2. Felida Marina Aerial Photo, Western Federal Land, 2011

3. FelidaMarina.dgn, HDR Engineering, 28 June 2012

4. RNWRstudyArea.dgn, HDR Engineering, 13 June 2012

5. House R&H Committee 69th Congress 1st Session, United States Congress, 1925

6. Rhinoceros, McNeel North America, www.rhino3d.com, Version 4.0

7. 2011 NOAA Tide Predictions: Saint Helens, Oreg., Station ID: 9439201, National Oceanographic and Atmospheric Administration, http://tidesandcurrents.noaa.gov/get_predictions.shtml?year=2011&stn=1038+Astori a&secstn=Saint+Helens,+Oreg.&thh=%2B3&thm=31&tlh=%2B5&tlm=44&hh=*0.

0&hl=*0.0&footnote=wc5

8. Current Conditions for Washington, United States Geological Survey, http://waterdata.usgs.gov/wa/nwis/uv/?site_no=14213090&PARAmeter_cd=00060,00 065, 25 July 2012

9. Clearance Guide, United States Coast Guard, 25 July 2012, http://www.uscg.mil/hq/cg5/cg551/Bridge.asp

10. Lake River Federal Navigation Project Charts, United States Army Corps of Engineers, Date Unknown

11. Navigability Determinations for the Thirteenth District, http://www.uscg.mil/d13/docs/cg_navigable_waterways.pdf, 25 July 2012

12. Portland-Vancouver Harbor Information Package, Second Edition, Reservoir Regulation and Water Quality Section, U.S. Army Corps of Engineers, November 2004.

13. Bridge Inspection and Appraisal Report, Lake River, Bridge Number 13551-00007, Ridgefield National Wildlife Refuge, U.S. Fish & Wildlife Service, Arlington, VA, 27 August

14. List of Federally Designated Navigable Waters for Washington State, Civil Works Permit Guidebook, US Army Corps of Engineers, Seattle District, 2008.

15. NOAA Navigation Chart 18525 Edition 37, Columbia River Saint Helens to Vancouver, U.S.

Department of Commerce, National Oceanic and Atmospheric Administration, National Ocean Service, Coast Survey, Washington D.C, June 2012

16. “Re: Datum (vertical elevation reference) for Lake River at Ridgefield, WA, USGS gage 14213090”, email John Clemens 28 August 2012 http://tidesandcurrents.noaa.gov/get_predictions.shtml?year=2011& http://waterdata.usgs.gov/wa/nwis/uv/?site_no=14213090& http://www.uscg.mil/hq/cg5/cg551/Bridge.asp

17. Clark County Public Works, July 1990 Memo to file, Datum adjustments NGVD 1929 to 1947.

18. Lake River Crossing Location Options, working document, email from B C Minor, US Department of Transportation, Federal Highway Administration (FHWA) to M Traffalis (FHWA) 23 August 2012, forwarded to D B Owings, HDR, 23 August 2012.

Appendix A

Table of Houseboats at McCuddy’s and at Felida Marinas With two or more Stories

Houseboats are indexed from north to south and labeled in Figure 2 and Figure 3, Section 2, Study Area Description. Dimensions presented are the maximum found from the on-site measurements.

McCuddy’s Marina Houseboats Greater than One Story Tall

Houseboat (No.)

Length Beam Height Estimated Accuracy (ft)

GPS Latitude GPS Longitude

4 --- 25 23 ± 2.0 N45º 48.979’ W122º 45.018’ 7 46 24 19 ± 0.5 N45º 48.944’ W122º 45.944’

11 ----- 37 26 ± 2.0 N45º 48.937’ W122º 45.011’

12 ----- 34 24 ± 0.5 N45º 48.921’ W122º 45.994’

18 63 42 18 ± 2.0 N45º 48.893’ W122º 45.951’

20 47 39 22 ± 2.0 N45º 48.888’ W122º 45.939’

21 63 35 18 ±2.0 N45º 48.893’ W122º 45.927’

22 52 31 18 ±2.0 N45º 48.879’ W122º 45.934’

S23 53 ---- 34 ±2.0 N45º 48.875’ W122º 45.902’

26 49 38 13 ±2.0 N45º 48.862’ W122º 45.911’

29 49 ---- 21 ± 0.5 N45º 48.853’ W122º 45.873’

32 63 31 17 ±2.0 N45º 48.806’ W122º 45.837’

33 48 34 23 ± 0.5 N45º 48.799’ W122º 45.834’

42 44 30 23 ± 2.0 N45º 48.775’ W122º 45.788’

46 ---- 41 20 ± 0.5 N45º 48.768’ W122º 45.767’

47 68 24 14 ±2.0 N45º 48.758’ W122º 45.755’

55 40 34 19 ± 2.0 N45º 48.714’ W122º 45.675’

Felida Marina Houseboats Greater than One Story Tall

Houseboat (No.)

Length Beam Height Estimated Accuracy (ft)

GPS

Latitude

GPS Longitude

1 44 36 20 ±0.5 N45º 42.655’ W122º 43.474’ 3 50 25 20 ±0.5 N45º 42.648’ W122º 43.442’

4 47 42 18 ±2.0 N45º 42.638’ W122º 43.441’

6 47 24 20 ±0.5 N45º 42.631’ W122º 43.432’

8 57 29 15 ±2.0 N45º 42.612’ W122º 43.417’

10 55 42 17 ±0.5 N45º 42.590’ W122º 43.397’

13 49 ---- 29 ±2.0 N45º 42.555’ W122º 43.361’

14 46 28 21 ±2.0 N45º 42.562’ W122º 43.368’

15 47 42 25 ±2.0 N45º 42.554’ W122º 43.364’

16 40 33 18 ±2.0 N45º 42.547’ W122º 43.356’

17 38 33 18 ±0.5 N45º 42.548’ W122º 43.354’

20 46 43 17 ±2.0 N45º 42.521’ W122º 43.336’

21 43 35 17 ±2.0 N45º 42.504’ W122º 43.340’

23 39 36 17 ±2.0 N45º 42.497’ W122º 43.341’

24 34 31 23 ±0.5 N45º 42.482’ W122º 43.334’

26 73 50 15 ±2.0 N45º 42.468’ W122º 43.340’

27 37 29 21 ±2.0 N45º 42.455’ W122º 43.341’

28 57 ---- 23 ±0.5 N45º 42.460’ W122º 43.329’

29 34 ---- 23 ±0.5 N45º 42.447’ W122º 43.338’

31 67 ---- 24 ±0.5 N45º 42.445’ W122º 43.338’

32 49 33 22 ±2.0 N45º 42.437’ W122º 43.337’

33 53 ---- 19 ±0.5 N45º 42.428’ W122º 43.342’

37 51 34 18 ±2.0 N45º 42.408’ W122º 43.342’

40 50 34 25 ±0.5 N45º 42.395’ W122º 43.341’

42 42 28 24 ±2.0 N45º 42.383’ W122º 43.354’

43 39 25 25 ±0.5 N45º 42.386’ W122º 43.348’

Appendix B

Pictures of Tallest House Boats

Appendix C

Land Use

Taxlots Figure 1

Source: Clark County GIS 2012, Bing Photo 2011\\Projects\WASHINGTON\170641 Ridgefield Wildlife Refuge\map_docs\mxd\final\Taxlots.mxd Last Updated 7/17/2012 HDR One Company/Many Solutions Western Federal Lands/Ridgefield Wildlife Refuge/Land Use Memorandum

Study Area

Taxlots

Water

0.5 1.5

Miles

Land Uses

The study area is located within the Vancouver Lake/Lake River Watershed. This watershed encompasses three subwatersheds: Lakeshore in the southeast section of the study area;

Vancouver Lake in the southern section of the study area; and Lake River in the central and northern sections of the study area. Most of the watershed lies within the Columbia River floodplain, with stream channels draining from the surrounding hills into Vancouver Lake and Lake River.

Figure 2 shows land cover in the study area, which is dominated by water/wetland and pasture/crop/grassland. Developed land is concentrated in the Lakeshore subwatershed and the Port of Vancouver. Forest land is minimal.

As shown on Figure 3, land uses in the study area include residential, parks, agricultural, commercial, vacant lands, waterbodies, and road/railroad rights-of-way (Clark County, 2011).

However, the majority of the study area consists of park/wildlife land, vacant/agricultural lands, and waterbodies. Very little commercial land is located in the northern and southern parts of the study area. Based on the GIS data, the majority of land in the southern section of the study area is “vacant”; however based on review of the 2011 aerial photographs, much of the vacant land appears to be used for agriculture.

The park/wildlife areas include Vancouver Lake Park, Shillapoo Wildlife Recreation Area, and Ridgefield National Wildlife Refuge. Bachelor Island is part of the Ridgefield National Wildlife Refuge and is accessible only by boat.

The study area includes many waterbodies including lakes, streams, sloughs, and rivers. Named waterbodies include Vancouver Lake, Curtis Lake, Green Lake, Post Office Lake, Canvasback Lake, Widgeion Lake, Lake River, and the Columbia River.

The study area contains several roads and a railroad line. NW Lower River Road/Highway 501 runs north-south along the western study area boundary.

This is the start of the file's text. The full file is on GovTribe.