This is a Task Assignment Form (Attachment C) under DEP Contract No. BS135, a Professional Services Contract between the Florida Department of Environmental Protection (FDEP) and Mott MacDonald Florida, LLC. The task assignment was executed on January 10, 2020, with FDEP Project Manager Jennifer Steele and Contract Administrator Avery Lehmann representing the state, and Michael Layne as the Contractor Representative. Billy Perry serves as the Project Principal for Mott MacDonald, with Casey Connor as the Project Engineer/Architect.
The task assignment involves developing a comprehensive Florida Offshore Sediment Resources Inventory to review legacy geological and geophysical data and combine it into a statewide inventory for use by all five Gulf states and the Bureau of Ocean Energy Management. The scope of work consists of two tasks: Task 1 (Literature Review and Draft Memorandum) with a fee of $19,434.83, due March 9, 2020, and Task 2 (Final Memorandum) with a fee of $3,993.86, due April 1, 2020. The total task assignment value is $23,428.69 on a cost reimbursement basis, with payment contingent upon FDEP approval of deliverables. The work period extends through April 1, 2020, and the consultant's responsibilities include compiling geophysical and geologic data within Florida's offshore boundaries to a depth of 100 feet, coordinating with federal and state agencies, digitizing analog data, georeferencing data, and developing data management procedures with the BOEM Marine Minerals Information System.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Mott MacDonald FDEP Florida Offshore Sediment Resources Inventory
Engineering Fee Estimate
J. Carter, C. Connor
STAFF HOUR SUMMARY Date: xxx
Project
Principal
Principal
Engineer/Archi tect
Senior Project
Manager Engineer II
Sr GIS
Specialist
Administrati ve Assistant Total
Sub-
Contractor
Direct
Reimburs-able Notes
Sub
Subtotal Total
Item $240.63 $175.64 $170.20 $84.32 $114.65 $58.38 Hours Costs Expense Markup Cost Cost
TASK 1 - Literature Review and Draft Memorandum 19,434.83$
Complete Literature Review, Develop and Submit Draft Memorandum 2 37 19 10 69 8 145 $19,435
TASK 2 - Final Memorandum 3,993.86$
Develop and Submit Final Memorandum 2 6 4 2 12 4 30 $3,994
Total Hours: 4 43 23 12 81 12 175
Labor Cost: $963 $7,553 $3,915 $1,012 $9,287 $701
SubTotal Costs 963$ 7,553$ 3,915$ 1,012$ 9,287$ 701$ 23,429$ -$ -$ -$
TOTAL PROJECT COST with All Tasks 23,428.69$
Notes: MM Labor Budget $23,429
MM Direct Costs $0
MM Markup on Subs $0
Total $23,429