Document Summary

This is a Task Assignment Change Order Form (Change Order No. 1) issued on January 16, 2023, under DEP Contract No. BS135 between the Florida Department of Environmental Protection (FDEP) and Mott MacDonald. The change order modifies Task Assignment Number 12 for the Mangrove Restoration Monitoring project in Marco Island, Florida. The contract involves coordination with multiple stakeholders including the Rookery Bay National Estuarine Research Reserve (RBNERR), Florida Fish and Wildlife Commission (FWC), Coastal Resources Group, Inc. (CRG), National Centers for Coastal Ocean Science (NCCOS), and the City of Marco Island. James Johnson serves as the Contractor's Contract Manager, while Genita Alexander represents FDEP as the Contract Manager.

The change order revises task completion dates to align with actual construction activities and the contract end date, reducing the completion date from April 30, 2024, to March 28, 2024—a net decrease of 33 days. However, the task amount remains unchanged at $141,800.00, with no modification to fee schedule or cost reimbursement components. The contract encompasses 14 tasks totaling $141,800.00, including site evaluations, regulatory agency coordination, scope of work development, construction coordination, baseline monitoring of vegetation and fish, and comprehensive Time Zero monitoring of hydrology, vegetation, and fish following construction events. Task deliverables span from June 2021 through March 28, 2024, with the primary focus on monitoring pre- and post-restoration conditions for the Fruit Farm Creek restoration project in the Ten Thousand Islands Aquatic Preserve.

View the file

Other files

File Type Posted
CN-370000-BS135-CMC1.pdf PDF
CN-370000-BS135-CMC5.pdf PDF
CN-370000-BS135-CMC6.pdf PDF
CN-370000-BS135-T10CO2.pdf PDF
CN-370000-BS135-T10CO6.pdf PDF
CN-370000-BS135-T13CO3.pdf PDF
CN-370000-BS135-T13CO5.pdf PDF
CN-370000-BS135-T15CO2.pdf PDF
CN-370000-BS135-T16.pdf PDF
CN-370000-BS135-T18.pdf PDF
CN-370000-BS135-T19CO1.pdf PDF
CN-370000-BS135-T1CO3.pdf PDF
CN-370000-BS135-T1CO4.pdf PDF
CN-370000-BS135-T24.pdf PDF
CN-370000-BS135-T4.pdf PDF
CN-370000-BS135-T4CO3.pdf PDF
CN-370000-BS135-T8CO1.pdf PDF
CN-370000-BS135-T1.pdf PDF
CN-370000-BS135-T13.pdf PDF
CN-370000-BS135-T14.pdf PDF
CN-370000-BS135-T15CO1.pdf PDF
CN-370000-BS135-T17.pdf PDF
CN-370000-BS135-T21.pdf PDF
CN-370000-BS135-T21CO1.pdf PDF
CN-370000-BS135-T22CO1.pdf PDF
CN-370000-BS135-T23.pdf PDF
CN-370000-BS135-T23CO3.pdf PDF
CN-370000-BS135-T3CO1.pdf PDF
CN-370000-BS135-T5.pdf PDF
CN-370000-BS135-T7.pdf PDF
CN-370000-BS135-T8.pdf PDF
CN-370000-BS135.pdf PDF
CN-370000-BS135-CMC2.pdf PDF
CN-370000-BS135-CMC3.pdf PDF
CN-370000-BS135-CMC4.pdf PDF
CN-370000-BS135-T10.pdf PDF
CN-370000-BS135-T10CO1.pdf PDF
CN-370000-BS135-T10CO3.pdf PDF
CN-370000-BS135-T10CO4.pdf PDF
CN-370000-BS135-T12.pdf PDF
CN-370000-BS135-T13CO2.pdf PDF
CN-370000-BS135-T13CO4.pdf PDF
CN-370000-BS135-T19.pdf PDF
CN-370000-BS135-T1CO1.pdf PDF
CN-370000-BS135-T1CO2.pdf PDF
CN-370000-BS135-T1CO5.pdf PDF
CN-370000-BS135-T2.pdf PDF
CN-370000-BS135-T20.pdf PDF
CN-370000-BS135-T21CO2.pdf PDF
CN-370000-BS135-T22.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT D -TASK ASSIGNMENT CHANGE ORDER FORM

DEP CONTRACT NO. BS135

Task Assignment Number: ___ 1 ___ 2 ___ _ Date: 1 -16 -2023 Change Order No._1�--

Contractor Name: Mott MacDonald

Contractor Contract Manager: -'J""'a""'m.:..ae""s-"-Jo=h"""n.:.::s""o.:.:.n ________ _ Phone: ---=8=50:..-=68=8:..-=91=6a.a6------

DEP Contract Manager: _G ___ e ___ n ___ it=a ..... A ___ l=ex ___ a ___ n ___ d ___ er _____________ _ Ph one: ______ 8 ___ 50 __ -=24 ___ 5 __ -___ 80 .... 2 ___ 1 ____ _

Description of Change: Revise task dates as shown in attached scope to better coincide with actual construction activities and reduce completion date to coincide with contract end date.

Task Description: Complete Time Zero monitoring of hydrology, vegetation, and fish following construction events.

CHANGE IN TASK AMOUNT

Fee Schedule Cost Reimbursement

Original Task Amount: $141,800.00

Task Amount Prior to this Change Order: $141,800.00

Net Increase/Decrease in Task Amount:

Task Amount with all Change Orders: $141,800.00

CHANGE IN TASK TIME

Original Task Completion Date: April 30, 2024

Completion Date Prior to This Change: April 30, 2024

Net Increase/Decrease in Task Period: -33 days

Completion Date with all Change Orders: March 28. 2024

Total

$141,800.00

$141,800.00

$141,800.00

CONTRACTOR FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION

Project Principal

David Skipper

1/16/2023

Date

Jeffrey A.

Carter

Digitally signed by Jeffrey A. Carter Date: 2023.01.30 16:43:47 -05'00'

Project Manager

Jeffery A. Carter

Date

Gen ·1 ta A I exa n de r Digitally signed by Genita Alexander Date: 2023.01.31 16:32:59 -05'00'

Contract Manager

Genita Alexander

APPROVED:

Cost Center Administrator

Date

Date cc: DEP Procurement Section (MS93), Bureau of Finance and Accounting (MS78) - 2 copies

Alex Reed

2/17/2023

File details come from the government source that posted it. Updated .