This is a Task Assignment Change Order Form (Change Order No. 1) issued on January 16, 2023, under DEP Contract No. BS135 between the Florida Department of Environmental Protection (FDEP) and Mott MacDonald. The change order modifies Task Assignment Number 12 for the Mangrove Restoration Monitoring project in Marco Island, Florida. The contract involves coordination with multiple stakeholders including the Rookery Bay National Estuarine Research Reserve (RBNERR), Florida Fish and Wildlife Commission (FWC), Coastal Resources Group, Inc. (CRG), National Centers for Coastal Ocean Science (NCCOS), and the City of Marco Island. James Johnson serves as the Contractor's Contract Manager, while Genita Alexander represents FDEP as the Contract Manager.
The change order revises task completion dates to align with actual construction activities and the contract end date, reducing the completion date from April 30, 2024, to March 28, 2024—a net decrease of 33 days. However, the task amount remains unchanged at $141,800.00, with no modification to fee schedule or cost reimbursement components. The contract encompasses 14 tasks totaling $141,800.00, including site evaluations, regulatory agency coordination, scope of work development, construction coordination, baseline monitoring of vegetation and fish, and comprehensive Time Zero monitoring of hydrology, vegetation, and fish following construction events. Task deliverables span from June 2021 through March 28, 2024, with the primary focus on monitoring pre- and post-restoration conditions for the Fruit Farm Creek restoration project in the Ten Thousand Islands Aquatic Preserve.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT D -TASK ASSIGNMENT CHANGE ORDER FORM
DEP CONTRACT NO. BS135
Task Assignment Number: ___ 1 ___ 2 ___ _ Date: 1 -16 -2023 Change Order No._1�--
Contractor Name: Mott MacDonald
Contractor Contract Manager: -'J""'a""'m.:..ae""s-"-Jo=h"""n.:.::s""o.:.:.n ________ _ Phone: ---=8=50:..-=68=8:..-=91=6a.a6------
DEP Contract Manager: _G ___ e ___ n ___ it=a ..... A ___ l=ex ___ a ___ n ___ d ___ er _____________ _ Ph one: ______ 8 ___ 50 __ -=24 ___ 5 __ -___ 80 .... 2 ___ 1 ____ _
Description of Change: Revise task dates as shown in attached scope to better coincide with actual construction activities and reduce completion date to coincide with contract end date.
Task Description: Complete Time Zero monitoring of hydrology, vegetation, and fish following construction events.
CHANGE IN TASK AMOUNT
Fee Schedule Cost Reimbursement
Original Task Amount: $141,800.00
Task Amount Prior to this Change Order: $141,800.00
Net Increase/Decrease in Task Amount:
Task Amount with all Change Orders: $141,800.00
CHANGE IN TASK TIME
Original Task Completion Date: April 30, 2024
Completion Date Prior to This Change: April 30, 2024
Net Increase/Decrease in Task Period: -33 days
Completion Date with all Change Orders: March 28. 2024
Total
$141,800.00
$141,800.00
$141,800.00
CONTRACTOR FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION
Project Principal
David Skipper
1/16/2023
Date
Jeffrey A.
Carter
Digitally signed by Jeffrey A. Carter Date: 2023.01.30 16:43:47 -05'00'
Project Manager
Jeffery A. Carter
Date
Gen ·1 ta A I exa n de r Digitally signed by Genita Alexander Date: 2023.01.31 16:32:59 -05'00'
Contract Manager
Genita Alexander
APPROVED:
Cost Center Administrator
Date
Date cc: DEP Procurement Section (MS93), Bureau of Finance and Accounting (MS78) - 2 copies
Alex Reed
2/17/2023