This document is a Task Assignment Form and Scope of Work under FDEP Contract No. BS135, issued by the Florida Department of Environmental Protection (FDEP) and executed with Mott MacDonald Florida, LLC. The assignment involves professional engineering services for field survey and hydrologic modeling related to high hazard potential dams owned by the Southwest Florida Water Management District (SWFWMD) in Hillsborough County, Florida. Key personnel include Tracy Woods (FDEP Project Manager), Deneka Smith (FDEP Contract Manager), David Skipper (Mott MacDonald Project Principal), and James Johnson (Mott MacDonald Principal Project Manager). The work focuses on two control structures: S-161 along Harney Canal and S-159 (Upper, Middle, and Lower) along Tampa Bypass Canal.
The contract is structured as a fixed-price task assignment valued at $70,853.36, with work execution through February 28, 2025. The scope comprises four primary tasks: (1) field reconnaissance and site coordination with deliverables due November 15, 2024 ($4,608.40); (2) field survey data acquisition with deliverables due December 20, 2024 ($37,844.16 combined, with Southeastern Survey and Mapping Corp receiving $29,508.56 and Mott MacDonald receiving $8,335.60); (3) LiDAR data compilation and analysis with deliverables due January 31, 2025 ($13,463.80); and (4) watershed hydrologic modeling inputs with deliverables due February 28, 2025 ($14,937.00). Funding is provided through Budget Entity 37350400 with grant number BIL24. All compensation is contingent upon completion and FDEP acceptance of deliverables, with no payment issued for incomplete work.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment C – TASK ASSIGNMENT FORM
DEP CONTRACT NO._BS135_____
Task Assignment Number: 22 Date: 10/3/2024
Contractor Name: Mott MacDonald Florida, LLC
Contractor Representative: James Johnson
DEP Contract Manager: Deneka Smith
Task Description (Use additional sheets if necessary): Field Survey and Hydrologic Model Inputs for the High Hazard Potential Dams System, at the Harney Canal Structure S-161 and the Tampa Bypass Canal Structure S-159 Upper, Middle and Lower Dams, in Hillsborough County, Owned by the Southwest Florida Water Management District, FL
Deliverables: see attached detailed Scope of Work dated October 2024
Performance Measures: Deliverables will be reviewed by FDEP to confirm they are complete, accurate, and timely Financial Consequences: As per Professional Services Contract BS135 between FDEP and Mott MacDonald
Period of Performance: Execution of Task Assignment through February 28, 2025
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
FIXED-PRICE FEE SCHEDULE COST REIMBURSEMENT
$70,853.36
TOTAL TASK ASSIGNMENT VALUE $ 70,853.36
Funding Information:
Org. Code |E.O. |Object Code |Budget Entity |Special Category| Grant # |Year |Amount |
|37350400000 | LR | 131500 | 37350400 | 100628 | BIL24 | |$ $70,853.36 |
|37 | | | | | | |$ | |37 | | | | | | |$ | |37 | | | | | | |$ |
CONTRACTOR FLORIDA DEPARTMENT OF
ENVIRONMENTAL
PROTECTION
10/3/2024 Project Principal David Skipper
Date Project Manager Tracy Woods
Contract Manager
Date
Date
Deneka Smith
APPROVED:
Cost Center Administrator Avery Lehmann
DWRM Director John Coates
Date
Date cc: DEP Procurement Section (MS93), Bureau of Finance and Accounting (MS78) – 2 copies
FDEP Contract BS135, Task Assignment No. 22, Project 1 - Field Survey and Hydrologic Model Inputs for the High Hazard Potential Dams System, at the Harney Canal Structure S-161 and the Tampa Bypass Canal Structure S-159 Upper, Middle and Lower Dams, in Hillsborough County, Owned by the Southwest Florida Water Management District, FL
Background and Project Description:
Mott MacDonald (MM) is pleased to submit this proposal to the Florida Department of Environmental Protection (FDEP) to conduct required professional engineering services for Task Assignment Number 22 under FDEP Contract No. BS135. The engineering services involves the compilation of existing pertinent data provided by Southwest Florida Water Management District (SWFWMD),and conducting Field Surveying and limited topographic mapping at the dam structures, as well as developing hydrologic modeling input for the High Hazard Potential (HHP) Dams system, owned by SWFWMD, for control structure S-161 along the Harney Canal, and the Tampa Bypass Canal control structures at S-159 Upper, Middle and Lower dams in Hillsborough County.
PROJECT INFORMATION
The requested services include:
1. Conducting an on-site field reconnaissance survey, and initial site meeting with MM, the surveying crew and SWFWMD representatives to:
a. Discuss pertinent issues of concern and confirm using control structures and related watershed data included in the External Hard drive provided by SWFWMD.
2. Conducting field cross- section, plan and profile surveying and site specific topographic mapping of the control structures at the S-161 Harney Canal and S-159 Tampa Bypass structures S-159 Upper, Middle, and Lower.
3. Developing Hydrologic Modeling Inputs for the watershed subareas within the project domain areas for future inundation modeling and mapping required to support the development of an Emergency Action Plan for the HHP system associated with structures S-161 and S-159 Upper, Middle, and Lower.
SCOPE OF SERVICES
Task 1: Field Reconnaissance Site Visit and Coordination with FDEP, and SWFWMD representatives.
The following work tasks will be performed to verify the available pertinent data for the below listed HHP system in Hillsborough County, FL.
1. S-161 structure, National Inventory of Dams (NID) ID # FL00640, Hillsborough County
2. S-159 structures Upper, Middle, and Lower and NID ID # FL12001, Hillsborough County
A. Conduct on site field reconnaissance and attend an initial meeting, with the representatives of the FDEP, SWFWMD and the surveying crew to discuss pertinent project issues of concern and verify the available data items regarding the control structures at the impoundments, as follows:
1) S-161 control structure along Harney Canal, and S-159 Upper, Middle and Lower Control structures along the Tampa Bypass Canal -
As-built drawings - plan, elevation, details, and cross-sections Latest Inspection Reports Project Hydrologic design criteria/ data
2) Watershed Master Control Plan and related reports Watershed Master Control Plan Report - electronic file.
Lidar and topographic data - electronic file Hydrologic Modeling data - electronic file
3) Existing Field Survey data Existing field survey data of the control structures and benchmarks datum -electronic files
B. Compilation of pertinent available data identified above.
DELIVERABLES:
1) Prepare and submit electronic files for:
Draft Site Reconnaissance Summary Report including Appendices with Figures and Excel Tables - summarizing pertinent available data used and recommendations regarding downstream consequence areas during extreme storm events.
Final Site Reconnaissance Summary Report
Performance Measure: Deliverables will be reviewed by the Department to confirm that they are complete, accurate, and timely.
Task 2: Field Survey Data Acquisition
Refer to Figures SD1 , SD2 and SD3 for the S-161 and S-159 structures aerial view locations and layout of field surveying cross-section work. Conduct field surveying data acquisition at the structures and:
1) Establish the top of embankment profiles and cross-sections at the control structures and verify structures outlet works dimensions data necessary to support future hydrologic analyses.
2) Confirm (ground truth) site topographic mapping of the adjacent embankments at the control structures.
Note: Field cross-section and topographic surveying work to be conducted by Southeastern Survey and Mapping Corp (SSMC).
1) Provide e-mail notification to the FDSP at least one week prior to the scheduled field site visit to conduct the required field surveying work. The notification should include the date, time, team meeting location, and the vendor contact name and phone numbers (office and cell).
The e-mail notification should be sent to Tracy.Woods@FloridaFDEP.gov
2) Provide an electronic version of the original field surveying data obtained for the dam structures, along with photographs taken at the selected field survey locations.
Task 3: LiDAR Data Compilation and Analysis
Conduct LiDAR Data compilation and Analysis for the HHP dam systems study area, Refer to Figure
H/TBC.
1) Download the available 2017 LiDAR data and produce a DEM for the HHP dam systems associated with the control structures S-161` and S-159 on Harney Canal and the Tampa Bypass canal, respectively, in the Hillsborough County, project study domain areas using GIS methods.
2) Integrate the 2017 LiDAR bare earth Digital Elevation Models (DEMs) with the cross-section and topographic survey data developed in Task 2 for the control structures S-161 and S- 159 Upper, Middle, and Lower.
1) DEM from 2017 LiDAR in both ASCII and GDB format (GIS readable geodatabase data); and cross-section and topographic data developed in Task 2 in XML and DWG formats for the control structures S-161 and S-159 Upper, Middle, and Lower and the downstream flooding impact area.
Task 4: Project domain watershed Hydrologic modeling inputs for the S-161 and S-159 HHP dam system.
Develop project domain watershed characteristics for S-161 and S-159 HHP dam systems to include:
1) The delineation of watershed subareas contributing flow to selected Point of interest (POI)for S-161 and S-159 HHP dam system impoundments and downstream flooding impact area.
2) Utilize base watershed and subareas data, and pertinent hydrologic data provided by SWFWMD in conjunction with watershed DEM to define selected Point of Interest (POI) locations.
1) Provide Draft watershed and subareas map contributing flow to the selected POIs for the S- 161 and S-159 HHP dam system impoundments and downstream flooding impact area, along the TBC.
2) Provide Final watershed and subareas map contributing flow to the selected POIs for the S- 161 and S-159 HHP dam system impoundments and downstream flooding impact area, along the TBC.
Key Personnel
FDEP
Role Name Entity
Project Manager Tracy Woods FDEP Contract Manager Avery Lehmann FDEP
Mott MacDonald Role Name Entity
Project Principal David Skipper Mott MacDonald Principal Project Manager James Johnson Mott MacDonald
Principal Engineer Michael Cox Comak Group
Project Schedule: CONSULTANT is available to begin work on this project immediately following receipt of the executed Task Assignment Number 22 from FDEP.
Compensation and Method of Payment
Compensation to be paid to the Consultant for providing the services described herein shall be on a fixed-price basis for each Task Deliverable. No compensation will be paid for services and/ or tasks that are not performed. The fixed-price compensation for the Deliverable shall be as listed in the detailed Payment and Deliverables Schedule Table. See Appendix A for Payment and Deliverables Schedule Table.
The Consultant will submit invoices to the FDEP for work performed at the completion and acceptance by FDEP of the final deliverable. The invoicing will be accompanied by a brief description of the work effort completed, including deliverables achieved, in accordance with the attached Fee Schedule. Compensation will not be paid for a deliverable until the deliverable has been completed and accepted by the FDEP.
AUTHORIZATION
The following individual is a representative for the CONSULTANT with the authority to enter.
into a binding Contract with the FDEP:
Signature Date
10-3-2024
Name and Title
David Skipper, PE Senior Vice President
Company Name
Mott MacDonald Florida, LLC
Appendix A
PAYMENT AND DELIVERABLES SCHEDULE
For all tasks, payment shall be made on a fixed price basis in the fixed amounts specified below for each deliverable following receipt and acceptance by the FDSP in accordance with Contract Terms.
Deliverable Deliverable Description Due Date
Total Payment Amount
Task 1
Field Reconnaissance Site Visit and Coordination with FDEP, and SWFWMD representatives.
1) Draft & Final Site Reconnaissance Summary Reports, including Appendices with Figures and Excel Tables summarizing pertinent available data
11/15/2024
$4,608.40
Task 2
Field Survey Data Acquisition
1)Provide e-mail notification to the FDSP at least one week prior to the scheduled field site visit to conduct the required field surveying work.
2) Provide electronic file of field surveying and topographic data for control structures S-161 and S-159 Upper, Middle, and Lower HHP dam system
12/20/2024
SSMC =
$29,508.56
MM =
$8,335.60
Task 3
LiDAR Data Compilation and topographic data integration
1) Compile DEM from 2017 LiDAR and topographic data developed in Task 2 for the control structures S-161, and S-159 Upper, Middle, and Lower and the downstream flooding impact area along the TBC.
01/31/2025 $13,463.80
Deliverable Deliverable Description Due Date Total
Payment Amount
Task 4
Project domain watershed Hydrologic modeling inputs for control structures S-161 and S-159 HHP dam system.
1)Provide watershed subareas map contributing flow to the selected points of interest for the S-161 and S-159 HHP dam system impoundments and downstream flooding impact area, along the TBC.
02/28/2025 $14,937.00
TOTAL $70,853.36