This is a Task Assignment Form under Florida Department of Environmental Protection (FDEP) Contract BS135 between FDEP and Mott MacDonald Florida, LLC. Task Assignment Number 20 was executed on August 23, 2024, with contract management by FDEP Contract Manager Deneka Smith and contractor representation by James Johnson. The project involves coordination with multiple stakeholders including the Rookery Bay National Estuarine Research Reserve (RBNERR), Florida Fish and Wildlife Commission (FWC), the City of Marco Island, the Conservancy of Southwest Florida, and the National Centers for Coastal Ocean Science (NCCOS).
The scope of work encompasses post-restoration monitoring for the Fruit Farm Creek Mangrove Restoration Project Phase 2, located in Marco Island, Florida, south of State Road 92. The contractor shall provide monitoring services from execution through June 30, 2025, on a fixed-price basis totaling $52,303.16. Deliverables include: Task 1—retrieve acoustic telemetry data by June 30, 2025 ($8,891.88); Task 2—Time Zero + 12 Months monitoring report by August 30, 2024 ($11,483.76); Task 3—Time Zero + 18 Months monitoring report by November 1, 2024 ($15,963.76); and Task 4—Time Zero + 24 Months monitoring report by June 20, 2025 ($15,963.76). The monitoring addresses vegetation, hydrology, fish sampling, and habitat assessment per Army Corps of Engineers permit SAJ-2011-003361 and Southwest Florida Water Management District permit 11-03308-P. Funding is allocated from organization code 37 with cost center reference 53802000000. Full compensation is contingent upon completion and FDEP approval of each deliverable.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment C – TASK ASSIGNMENT FORM
DEP CONTRACT NO._BS135_____
Task Assignment Number: 20 Date: 2 /2024
Contractor Name: Mott MacDonald Florida, LLC
Contractor Representative: James Johnson
DEP Contract Manager: Deneka Smith
Task Description (Use additional sheets if necessary): Fruit Farms Creek Mangrove Restoration Project Phase 2. Develop hydrologic restoration plans, coordinate channel construction, and monitor pre- and post- restoration conditions of the project area located south of SR-92. Coordinate all work with the permit holder and resource managers (RBNERR),restoration managers (Florida Fish and Wildlife Commission; FWC) and the City of Marco Island engineering and construction teams.
Deliverables: see attached detailed Scope of Work dated May 2024
Performance Measures: Deliverables will be reviewed by FDEP to confirm they are complete, accurate, and timely Financial Consequences: As per Professional Services Contract BS135 between FDEP and Mott MacDonald
Period of Performance: Execution of Task Assignment through June 30, 2025
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
FIXED-PRICE FEE SCHEDULE COST REIMBURSEMENT
$52,303.16
TOTAL TASK ASSIGNMENT VALUE $ 52,303.16
Funding Information:
Org. Code |E.O. |Object Code |Budget Entity |Special Category| Grant # |Year |Amount | |37 | | | | | | |$ | |37 | | | | | | |$ | |37 | | | | | | |$ | |37 | | | | | | |$ |
CONTRACTOR FLORIDA DEPARTMENT OF
ENVIRONMENTAL PROTECTION
6/20/2024 Project Principal David Skipper
Date Project Manager
Date
Date Contract Manager
Deneka Smith
APPROVED:
Cost Center Administrator Date cc: DEP Procurement Section (MS93), Bureau of Finance and Accounting (MS78) – 2 copies
Jared Franklin
Digitally signed by Jared Franklin Date: 2024.08.23 14:46:03 -04'00'
Deneka Smith Digitally signed by Deneka Smith Date: 2024.08.23 16:24:52 -04'00'
Jeffrey A. Carter Digitally signed by Jeffrey A. Carter Date: 2024.08.26 14:04:44 -04'00'
8/23/2024
8/23/2024
8/26/2024
Scope of Work For: Fruit Farm Creek – Phase 2
Mangrove Restoration Monitoring in Marco Island, Florida
Background
The Fruit Farm Creek (FFC) restoration project area is located on the western edge of the Ten Thousand Islands Aquatic Preserve in southwest Florida. The region was distinctly characterized by standing mangrove snags surrounded by severely stressed shrub mangroves. Surveys conducted before hurricane Irma (2017) documented 65 acres of complete vegetation loss and an additional 200 acres of severe stress; these areas have enlarged following recent hurricane impacts. The project area is on the south side of SR-92 in Marco Island (Collier County) within parcels owned by the Trustees of the Internal Improvement Trust Fund and managed by the Rookery Bay National Estuarine Research Reserve (RBNERR). The restoration was managed by Florida Fish and Wildlife Commission (FWC), and will re-established hydrologic connections through creek channel repair and culvert construction across SR-92.
Pre-restoration mangrove die-off surrounded by severely stressed mangroves circa . This image shows the area at the end of the dry season (Dec – Mar). Under rainy conditions (Apr – Nov) this basin is continuously flooded.
The severe mangrove forest stress and loss resulted from changes to the natural hydrology created by the 1938 construction of SR-92, which prohibited adequate hydrologic connection and tidal flow. The impoundment prevented exchange of oxygen-rich water and flushing of naturally-occurring sulfide material. The resulting stress was likely exacerbated in the following decades through a cascading pattern of additional elevation loss and hydroperiod (flood duration) extension. More recently, mangroves south of SR-92 reached a point of critical stress after heavy rains increased flooding extent and duration.
Overview of SR-92 with the Fruit Farm Creek mangrove die-off areas. Yellow lines highlight the historic flow of Fruit Farm Creek before the road was constructed. Prior to restoration only one 60” culvert crossed SR-92.
Restoration
The restoration plan was designed by Coastal Resources Group, Inc. (CRG), in consultation with J.
R. Evans Engineering. The restoration work encompassed three shovel-ready project phases: 1A, 1B and
2. Phase 1A (4.0 acres north of SR 92) was completed in 2012 as a pilot project to test the hypothesis that hydrologic restoration alone (without additional seeding) was adequate for this site to naturally revegetate. Over four years following the pilot restoration work, vegetation cover increased from 0.5% to 83%.
Photo-points from a fixed location following tidal creek restoration in 2012 north of SR-92 (Phase 1A). Photographs taken by Coastal Resources Group, Inc.
Completed Phases 1B and 2 included the following work:
Installation of three new culverts and widening the existing culvert under SR-92;
Mechanical- and hand-clearing of small tidal creeks;
Monitoring local hydrology, vegetation, and habitat use by wildlife.
Scope of Work – Contract BS135 - Task Assignment 20
This document with attachments provides a scope of work for the remaining monitoring tasks for the Fruit Farm Creek restoration project, Phases 1B and 2. These remaining tasks consist of monitoring the post-restoration conditions of the project area located south of SR-92 (Phases 1B and 2). The field-based monitoring and reporting work will be conducted by Coastal Resources Group (CRG; “Contractor”), who will coordinate with Conservancy of Southwest Florida and the National Centers for Coastal Ocean Science (NCCOS).
The Contractor will coordinate all work with the permit holder and resource managers (RBNERR), restoration managers (Florida Fish and Wildlife Commission; FWC) and the City of Marco Island engineering and construction teams.
The Contractor shall:
1) Provide the remaining, required monitoring (Years 1-2) as outlined in Army Corps permit SAJ-2011- 003361 and Southwest Florida Water Management District permit 11-03308-P. This includes monitoring for vegetation, hydrology, and fish sampling, including providing the final report for the acoustic telemetry study.
Definitions
Hydrologic restoration – Reconnection of adequate tidal water flow in a previously hydrologically-restricted area to promote historical ecosystem function and productivity
- Project area – See map below:
A map of the mangrove die-off restoration area and proposed creek clearing. This contract will include Phases 1B and 2 as indicated in the map.
- Project design – The project design and associated monitoring will follow the guidance documents provided by Coastal Resources Group, Inc. to RBNERR in 2019 (see attached).
- Baseline – The time period before restoration work has begun
- Time Zero – The time at which hydrologic restoration (culvert construction plus creek channel clearing and reconnection) is completed
- Acoustic telemetry – The use of acoustic tags and receivers placed in species of importance and along movement corridors, respectively.
Contractor Responsibilities
Deliverables. The Contractor shall provide the following remaining deliverables with this task order:
- Task 1: Retrieve acoustic telemetry data to monitor fish movements in local creeks near the restoration area by June 30, 2025 o Payment: $8,891.88
- Task 2: TZ + 12 Months Amended Report with Fish Monitoring Results by , 2024:
o Payment $11,483.76
- Task 3: TZ + 18 Months Vegetation and Fish Monitoring and Report by November 1, 2024:
o Payment $15,963.76
- Task 4: TZ + 24 Months Vegetation and Fish Monitoring and Report by June 20, 2025:
o Payment $15,963.76
Compensation and Method of Payment
Compensation to be paid to the Contractor for providing the services described in Exhibit A shall be on a fixed price basis. No compensation will be paid for services and/ or tasks that are not performed.
The Contractor will submit invoices to FDEP for work performed according to the above deliverable schedule. Invoicing will be accompanied by a brief description of the work effort completed.
Invoices will be prepared for work completed as outlined in accordance with the Professional Services Contract BS135. Full compensation will not be paid for a task until the deliverable has been completed and approved by the FDEP. The Tasks, Deliverables, and Payments are summarized in the following table and provided in Exhibit A. Total cost for this scope of work is $52,303.16.
Fruit Farm Creek – Phase 2 Summary of Tasks, Deliverables, Due Dates, and Costs
Task Number Task Deliverable Due Date Total
1 Retrieve acoustic telemetry
Report with data analysis 6/30/2025 $8,891.88
Time Zero + 12 Vegetation and Fish Sampling
Amended Time Zero + 12 Months Monitoring Report with Fish Sampling Results
/ /2024 $11,483.76
3 TZ+ 18 Vegetation and Fish Sampling
Time Zero + 18 Months Monitoring Report 11/01/2024 $15,963.76
4 TZ + 24 Vegetation and Fish Sampling
Time Zero + 24 Months Monitoring Report 6/20/2025 $15,963.76
Grand Total = $52,303.16