This is a Permitting Assessment form for National Park Service project MEVE 218998 to rehabilitate and stabilize Chapin Mesa Historic Buildings and Houses at Mesa Verde National Park. The project involves comprehensive rehabilitation of historic residential quarters and a museum, including replacement of all mechanical, electrical, plumbing, and fire suppression systems that have reached the end of their serviceable life, replacement of sanitary sewer laterals, and upgrades to storm drainage systems of unknown condition. The work is being managed by the Denver Service Center with Hennebery Eddy Architects as the A/E firm and includes removal of propane tanks and installation of new fire alarm systems.
The assessment identifies several key permitting requirements, particularly for hazardous material remediation since lead, asbestos, and other hazardous materials were found in quantities exceeding state and federal regulations. Required permits include Colorado Department of Public Health and Environment permits for asbestos abatement under Regulation 8 and lead-based paint abatement under Regulation 19, with temporary storage and disposal managed by the contractor. The project also requires service applications with Empire Electric Association for electrical upgrades and temporary utilities during construction. The site is located entirely on NPS land with exclusive federal jurisdiction, is part of the Chapin Mesa Village Historic District and Mesa Verde Administration District National Historic Landmark, and is designated as a World Heritage Site. The assessment notes the presence of threatened and endangered species including Mexican Spotted Owl, Southwestern Willow Flycatcher, and Milkvetch that may require consideration during project execution.
View the file
Other files
Show all 41
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Permitting Assessment for:
MEVE 218998 - Rehab and Stabilize Chapin Mesa Historic Buildings and Houses
PMIS #: 218998
PEPC ID#:
REGION:
8/02/224
Questions Examining Jurisdiction - Who needs to be involved?
Yes
Yes
Questions regarding circumstances that might give an agency jurisdiction at a site.
No
No
No
Yes
Yes
Permitting Lead:
A/E: Hennebery Eddy Architects A/E CONTACT: Will Ives Dates of Assessment -
2nd PARK CONTACT:
Have the site's structures been reviewed? (levees, utilities, etc.)?
Other designations that may carry rights (special waters, critical habitat, easements etc.)?
Chapin Mesa Village Historic District NRHP Nomination
Mesa Verde Administration District National Historic Landmark Nomination
Mesa Verde Cultural Landscape Inventory
Condition of storm drains is unknown.
CCTV of the sanitary sewer laterals concluded all laterals have reach the end of their servicable life and need to be replaced.
MEP inspections concluded all residences require new mechanical, electrical, plumbing and fire suppression. The Museum requires electrical upgrades.
Threatened Species: Milkvetch
Threatened Species: Mexican Spotted Owl
Endangered Species: Southwestern Willow Flycatcher
Candidate: Monarch Butterfly
Birds of Conservation Concern: Cassin's Finch, Clark's Nutcracker, Evening
Grosbeak, Golden Eagle, Olive-sided Flycatcher, Pinyon Jay, Virginia's Warbler
Is the site COMPLETELY on NPS land?
Assessor's Name: H. Crane
PARK: Mesa Verde National Park
DSC PS: Ashley Bloomfield
Project Meta Data
Jurisdictional Assessment
DSC PM: Lawrence Mason
What is the classification of the jurisdiction for the Park at the site? See RM39-1, pg. 9. 1
Has the site's jurisdiction been DOCUMENTED?
Notes:
Exclusive (federal only) Source:
Is there any known local jurisdiction on the site?
List other existing permits, easements, agreements, etc. that are in the site boundaries site:
Programmatic Agreement (Expired): MOA between MVNP and SHPO Regarding the Rehabilitation of Quarters #5, #6, and #41 in Mesa Verde National Park (PEPC #69126) (CHS #62732).
1st PARK CONTACT: Allan Loy
Is there standing water on site?
Intermountain Region
PROGRAM:
Are there water channels on site?
Notes on Jurisdictional Assessment:
All waterways feed to Mancos River
World Heritage Site
PROJECT TITLE: Rehabilitate and Stabilize Chapin Mesa Historic Buildings and Houses
NPS units: RD=Regional Director, WRD=Water Resources Division Permitting Assessment FORM, 12-2-16
National Park Service - Denver Service Center 7/26/2024 | page 1 of 15
Permit? Jurisdiction: Agency No Federal: NMFS and/or FWS No State:
No Local: ----
Permit? Jurisdiction: Agency
No Federal: USFWS
No State:
No Local: ----
Permit? Jurisdiction: Agency
No
Federal: USFWS
No State:
No Local: ----
Permit? Jurisdiction: Agency
No
Federal: USFWS
No State:
No Local: ----
Basis of Decision: N/A
Basis of Decision: N/A
Impacts to Resource Topics - Compliance Related
---- Local jurisdiction typically does not apply to NPS for this topic
Permit Type:
Listed Species Incidental Take: Fish (NPS typically avoids incidental take)Not part of project
Listed Species Incidental Take: Marine Mammals (NPS typically avoids incidental take)Not part of project
Permit Type:
Incidental Take Permit
Law, regulation, etc. Requirements, Actions, Etc.:
ESA § 95,7, MBTA8
Incidental take permits may be sought when a non-federal entity believes their otherwise lawful activities may result in take of endangered or threatened animal species.
Permit Type:
---- Local jurisdiction typically does not apply to NPS for this topic
Basis of Decision: Incidental take permits may be sought when a non-federal entity believes their otherwise lawful activities may result in take of endangered or threatened animal species.
Threatened Species: Milkvetch
Threatened Species: Mexican Spotted Owl
Endangered Species: Southwestern Willow Flycatcher
Candidate: Monarch Butterfly
Birds of Conservation Concern: Cassin's Finch, Clark's Nutcracker, Evening Grosbeak, Golden Eagle, Olive-sided Flycatcher, Pinyon Jay, Virginia's Warbler
Incidental Take Permit
ESA § 95,7 Incidental take permits may be sought when a non-federal entity believes their otherwise lawful activities may result in take of endangered or threatened animal species.
Law, regulation, etc.
ESA § 95,7
Requirements, Actions, Etc.:
Local jurisdiction typically does not apply to NPS for this topic
Law, regulation, etc. Requirements, Actions, Etc.:
Permit Type:
ESA § 95,7, MMPA6
---- Local jurisdiction typically does not apply to NPS for this topic
Part of project Protected/Critical Habitat (NPS typically avoids incidental take)
Law, regulation, etc. Requirements, Actions, Etc.:
Basis of Decision: Incidental take permits may be sought when a non-federal entity believes their otherwise lawful activities may result in take of endangered or threatened animal species.
Proposed PACT for Mexican Spotted Owl
Listed Species Incidental Take: Terrestrial (NPS typically avoids incidental take)Part of project
NPS units: RD=Regional Director, WRD=Water Resources Division
National Park Service - Denver Service Center 7/26/2024 | page 2 of 15
Permit? Jurisdiction: Agency
No Federal: USACE, USEPA
No State:
No Local: ----
Permit? Jurisdiction: Agency
No Federal: FEMA
No State:
No Local:
Permit? Jurisdiction: Agency No Federal: NOAA No State:
No Local:
Permit? Jurisdiction: Agency No Federal: USACE, USCG No State:
No Local:
Permit? Jurisdiction: Agency
No Federal: USACE
No State:
No Local:
Permit Type:Law, regulation, etc. Requirements, Actions, Etc.:
Not part of project Coastal Lands - Usually addressed in NEPA on NPS land. If project is NOT on NPS land review this topic.
Not part of project Navigable Waters
---- Local jurisdiction typically does not apply to NPS for this topic
NFIP Permit
Permit Type:
44 CFR12, EO 1198813,
Basis of Decision: N/A
Basis of Decision: N/A
Basis of Decision: N/A
Basis of Decision: N/A
Basis of Decision: N/A
Permit Type:Law, regulation, etc.
Requirements, Actions, Etc.:
Law, regulation, etc. Requirements, Actions, Etc.:
Section 404 D&F
CWA § 40410, EO 119909,
Law, regulation, etc.
Not part of project Waters of the US and Wetlands (or other Special Aquatic Sites)
Not part of project Floodplain (Construction in)
Permit Type:
CZMA14,
Permit Type:Law, regulation, etc. Requirements, Actions, Etc.:
R&HA 1899 §§9-1011
Not part of project Water Quality Certification (required if project has federal permit)
Requirements, Actions, Etc.:
CWA § 40410, EO 119909, Section 404 D&F
NPS units: RD=Regional Director, WRD=Water Resources Division
National Park Service - Denver Service Center 7/26/2024 | page 3 of 15
Permit? Jurisdiction: Agency No Federal: DOI-OSM No State:
No Local: ----
Permit? Jurisdiction: Agency
No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Requirements, Actions, Etc.:
Not part of project Mine Land
Basis of Decision: N/A
Basis of Decision: N/A
Not part of project Zoning - Not normally required on NPS land
Not part of project OTHER TOPIC:
Law, regulation, etc. Permit Type: Requirements, Actions, Etc.:
Basis of Decision: N/A
SMCRA
Law, regulation, etc. Permit Type: Requirements, Actions, Etc.:
Local jurisdiction typically does not apply to NPS for this topic
Law, regulation, etc. Permit Type:
NPS units: RD=Regional Director, WRD=Water Resources Division
National Park Service - Denver Service Center 7/26/2024 | page 4 of 15
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Not part of project Wastewater Collection System
Not part of project Wastewater Pump/Lift Station
Basis of Decision:
Law, regulation, etc. Requirements, Actions, Etc.:
Basis of Decision: N/A
Law, regulation, etc. Requirements, Actions, Etc.:
Permit Type:
Permit Type:
Not part of project Pretreatment, i.e. Oil/Water Separator
Basis of Decision: N/A
Not part of project Wastewater Treatment Plant
Permit Type:Law, regulation, etc. Requirements, Actions, Etc.:
Requirements, Actions, Etc.:
Basis of Decision: N/A
Law, regulation, etc. Requirements, Actions, Etc.:
Topics included in Design - Integrated into Plans
Not part of project Septic System
Permit Type:
Basis of Decision: N/A
Law, regulation, etc.
Permit Type:
NPS units: RD=Regional Director, WRD=Water Resources Division
National Park Service - Denver Service Center 7/26/2024 | page 5 of 15
Permit? Jurisdiction: Agency
No
Federal: USACE
No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Law, regulation, etc.
Law, regulation, etc. Requirements, Actions, Etc.:
RCRA, 36 CFR Part 6 §6.52, NPS Guidance3, Permit Type:
Not part of project Landfill (NPS does not usually allow Landfills on NPS land)
Permit Type:
Not part of project Aggregation Pt. or Transfer Facility
Permit Type:
Basis of Decision: N/A
Law, regulation, etc. Requirements, Actions, Etc.:
Basis of Decision: N/A
Requirements, Actions, Etc.:
Section 404 & CWA NPS Internal Standards and Guidelines and Organic Act: If less than one acre of soil disturbance, then Contractor to prepare a
Temporary Stormwater Management Plan
NPDES Phase II regulations: Construction disturbances 1 acre and above typically require a formal NPDES permit and a formal Stormwater Pollution Prevention Plan (SWPPP) must be submitted to the Authority Having
Jurisdiction (AHJ) for review and approval.
Not part of project Stormwater Management (permanent)
Permit Type:Law, regulation, etc. Requirements, Actions, Etc.:
Basis of Decision: N/A
Not part of project Drinking Water Treatment Plant
Basis of Decision: N/A
NPS units: RD=Regional Director, WRD=Water Resources Division
National Park Service - Denver Service Center 7/26/2024 | page 6 of 15
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal: USEPA No State:
No Local:
Permit? Jurisdiction: Agency
No
Federal: USEPA
No State:
No Local:
Permit? Jurisdiction: Agency No Federal: FCC4
No State:
No Local:
Not part of project Communication Tower
Law, regulation, etc. Permit Type: Requirements, Actions, Etc.:
Permit
Basis of Decision: N/A
Basis of Decision: N/A
Not part of project
Underground Injection
Permit Type:Law, regulation, etc. Requirements, Actions, Etc.:
Tank Construction (AST or UST)
Permit Type:Law, regulation, etc. Requirements, Actions, Etc.:
Not part of project Well Construction (includes geothermal)
Permit Type:Law, regulation, etc. Requirements, Actions, Etc.:
Basis of Decision: N/A
Not part of project
Basis of Decision: Hazardous material remediation is part of this project. Lead, asbestos, and other hazardous materials were found in quantities that exceed state and federal regulations. Remediation will occur during construction. Anticipate temporary/short-term storage and disposal by contractor. Analysis and review with the Park is on-going.
Permit Type:
Permit
Law, regulation, etc. Requirements, Actions, Etc.:
RCRA , OSHA, and NESHAPS RCRA Permit Exceptions include:
Businesses that generate hazardous waste and then store for short periods of time before transporting the waste off site.
Basis of Decision: N/A
Part of project Hazardous Material/Waste Storage
US Code, Title 42, Chap 82, Sub chap IX
NPS units: RD=Regional Director, WRD=Water Resources Division
National Park Service - Denver Service Center 7/26/2024 | page 7 of 15
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal: USCG No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
Yes Local: Empire Electric Association
Requirements, Actions, Etc.:
Law, regulation, etc. Permit Type: Requirements, Actions, Etc.:
Law, regulation, etc. Permit Type: Requirements, Actions, Etc.:
Basis of Decision:
Condition of storm drains is unknown.
CCTV of the sanitary sewer laterals concluded all laterals have reach the end of their serviceable life and need to be replaced.
MEP inspections concluded all MEP systems at all residences have reached the end of their serviceable life and need to be replaced. The residences will also receive fire alarm and fire suppression systems. Propane tanks associated with the residences will be disconnected and removed. The Museum requires electrical upgrades.
Only electrical upgrades require service request application.
Application Service Request online application
Basis of Decision: N/A
Not part of project Roadway/Highway and Associated structures
Part of project OTHER TOPIC: Site Utilities
Basis of Decision: N/A
Not part of project Work in Navigable Waters - Aids to Navigation
Law, regulation, etc. Permit Type:
NPS units: RD=Regional Director, WRD=Water Resources Division
National Park Service - Denver Service Center 7/26/2024 | page 8 of 15
Permit? Jurisdiction: Agency No Federal: USEPA No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Part of project Traffic Control
Permit Type:Law, regulation, etc. Requirements, Actions, Etc.:
Permit Type:Law, regulation, etc. Requirements, Actions, Etc.:
Clean Air Act-Title II
Basis of Decision: Construction vehicles will use the same roadway as visitors in the Park. See G004 for a preliminary traffic control site plan. Contractor to provide a traffic control plan for approval by the Contracting Officer.
Construction Topics (Based on Means and Methods)
Not part of project Construction Air Pollution - Usually handled via Division 1 Specifications
Not part of project Airport Hazard/Safety Clearances
Not part of project Railroad Crossing
Basis of Decision: N/A
Permit Type:
Permit Type:
Law, regulation, etc. Requirements, Actions, Etc.:
Permit Type:Law, regulation, etc. Requirements, Actions, Etc.:
Basis of Decision: N/A
Basis of Decision: N/A
Not part of project Highway Encroachment Permit
Law, regulation, etc. Requirements, Actions, Etc.:
Basis of Decision: N/A
NPS units: RD=Regional Director, WRD=Water Resources Division
National Park Service - Denver Service Center 7/26/2024 | page 9 of 15
Needed? Jurisdiction: Agency No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal: USEPA
No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
Yes Local: Empire Electric Association
Part of project Digging / Excavation Permit - Usually handled via Division 1 Specifications
Part of project Noise Abatement - Usually handled via Division 1 Specifications
Not part of project NPDES over an acre Construction Permit
Permit Type:Law, regulation, etc. Requirements, Actions, Etc.:
Permit Type:
Service Request online application
Temporary Utilities (Communication, Electrical, Water, Sanitary Sewer, etc.)Part of project
Basis of Decision:
No, a NPDES Construction Permit is not required.
This is based upon the following background calculations for disturbed area.
• Calculate area of disturbance for 8 total Quarters
• Estimated average length of disturbance per 1 Quarter is 150 LF
• Width of disturbed area for construction is 30 feet
• Disturbed area per Quarter is 4500 SF
• Total Quarters disturbed area is 36,000 SF
• Area of 1 Acre is 43,560 SF
• Remaining potential area for disturbance is 7,560 SF
• Calculate disturbed area for new parking spaces 20’x 60’ is 1200 SF
• Remaining potential area for disturbance is 4,360 SF
• This accounts for various concrete, vegetated swales, and other miscellaneous disturbed areas
Law, regulation, etc. Permit Type: Requirements, Actions, Etc.:
Application
Permit Type:
Law, regulation, etc. Requirements, Actions, Etc.:
Basis of Decision: Project will include grading and excavation for site accessibility, foundation drains, foundation underpinning, and new utilities. Excavation depth is pending results of the geotechnical report which located utilities via GPR and measured the depth to bedrock, soil percolation, and soil bearing capacity. Digging and excavation requirements will be handled via Division 1 Specifications.
Basis of Decision: The residences will be unoccupied during construction. Temporary power will be needed for the museum and residences during construction. Temporary power will require a service request application.
Law, regulation, etc. Requirements, Actions, Etc.:
CWA-Section 401
Basis of Decision: Noise abatement will be handled via Division 1 Specifications.
NPS units: RD=Regional Director, WRD=Water Resources Division
National Park Service - Denver Service Center 7/26/2024 | page 10 of 15
Permit? Jurisdiction: Agency
No
Federal:
Yes
State: CDPHE-AQCC
CDPHE-APCD
No Local:
Permit? Jurisdiction: Agency No Federal: USCG No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Part of project Hazardous Waste Removal, Transportation, and disposal
Law, regulation, etc. Permit Type: Requirements, Actions, Etc.:
The EPA has granted authority to the state of Colorado to implement the Resource Conservation and Recorvery Act (RCRA).
Asbestos: CDPHE Regulation 8
Lead Paint: CDPHE Regulation 19 & Revised Statute
25-7-1101
Asbestos: Based on the quantities of regulated asbestos-containing material (RACM) planned for abatement, the abatement must be completed in accordance with Colorado Department of Public
Health and Environment (CDPHE) Regulation 8, a permit must be submitted to the CDPHE-AQCC https://cdphe.colorado.gov/indoor-air-quality/asbestos/notification-and-permits
Lead Paint: Lead-based paint abatement must be conducted by state-certified firms and individuals. State requirements include training, certification, accreditation and work practice standards.
The requirements apply to housing constructed prior to 1978, and child-occupied facilities. These requirements are found in Colorado
Air Quality Control Regulation No. 19 (opens in new window) and the Colorado Revised Statute 25-7-1101, et seq.
https://cdphe.colorado.gov/for-abatement-professionals/lead-abatement-permit
Basis of Decision: Hazardous material remediation is part of this project. Lead, asbestos, and other hazardous materials were found in quantities that exceed state and federal regulations. Remediation will occur during construction. Anticipate temporary/short-term storage and disposal by contractor.
Permit
Basis of Decision: N/A
Permit
Basis of Decision: N/A
Not part of project OTHER TOPIC:
Law, regulation, etc. Permit Type: Requirements, Actions, Etc.:
Not part of project Work in Navigable Waters - Notice to Mariners
Law, regulation, etc. Permit Type: Requirements, Actions, Etc.:
NPS units: RD=Regional Director, WRD=Water Resources Division
National Park Service - Denver Service Center 7/26/2024 | page 11 of 15
Permit? Jurisdiction: Agency No Federal: USEPA No State:
No Local:
Permit? Jurisdiction: Agency No Federal: USEPA No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Basis of Decision: N/A
Septic System
Not part of project AST Operation
Not part of project UST Operating
Not part of project Stationary Source Air Quality
Not part of project Solid Waste Incineration Unit
Not part of project
Permit Type:Law, regulation, etc. Requirements, Actions, Etc.:
Basis of Decision: N/A
Basis of Decision: N/A
Basis of Decision: N/A
Permit Type:
Basis of Decision: N/A
Permit Type:
Permit
Permit Type: Requirements, Actions, Etc.:
Clean Air Act Title V Permit
Operational Permits - Owner
Law, regulation, etc.
Law, regulation, etc. Requirements, Actions, Etc.:
Clean Air Act Title V, NESHAP
Permit Type:Law, regulation, etc.
Requirements, Actions, Etc.:
Requirements, Actions, Etc.:
Law, regulation, etc.
NPS units: RD=Regional Director, WRD=Water Resources Division
National Park Service - Denver Service Center 7/26/2024 | page 12 of 15
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal: USEPA No State:
No Local:
Wastewater Treatment Plant
Not part of project Pretreatment (e.g. Oil/Water Separator)
Not part of project
Not part of project Food Services (usually acquired by the Concessioner)
Basis of Decision: N/A
Permit Type:Law, regulation, etc. Requirements, Actions, Etc.:
Law, regulation, etc. Requirements, Actions, Etc.:
Basis of Decision: N/A
Permit Type:
Permit Type:
PWS permit
Basis of Decision: N/A
Basis of Decision: N/A
Safe Drinking Water Act
Not part of project
Basis of Decision: N/A
Not part of project
Law, regulation, etc. Requirements, Actions, Etc.:
Drinking Water Treatment Plant
Law, regulation, etc. Requirements, Actions, Etc.:
Wastewater Pump Station
Permit Type:Law, regulation, etc. Requirements, Actions, Etc.:
Permit Type:
NPS units: RD=Regional Director, WRD=Water Resources Division
National Park Service - Denver Service Center 7/26/2024 | page 13 of 15
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Permit? Jurisdiction: Agency No Federal:
No State:
No Local:
Basis of Decision: N/A
Permit Type:
Basis of Decision: N/A
Basis of Decision: N/A
Basis of Decision: N/A
Not part of project Well Construction (includes geothermal)
Not part of project Underground Injection Well
Not part of project Waste Transfer - Aggregation Facility
Not part of project Landfill
Not part of project Small Quality Generator
Law, regulation, etc. Requirements, Actions, Etc.:
Permit Type:Law, regulation, etc. Requirements, Actions, Etc.:
Permit Type:
Law, regulation, etc. Permit Type: Requirements, Actions, Etc.:
Law, regulation, etc. Requirements, Actions, Etc.:
Permit Type:Law, regulation, etc. Requirements, Actions, Etc.:
Basis of Decision: N/A
NPS units: RD=Regional Director, WRD=Water Resources Division
National Park Service - Denver Service Center 7/26/2024 | page 14 of 15
Permit? Jurisdiction: Agency
No
Federal: USEPA
No State:
No Local:
Basis of Decision: Hazardous material remediation is part of this project. Lead, asbestos, and other hazardous materials were found in quantities that exceed state and federal regulations. Remediation will occur during construction. Anticipate temporary/short-term storage and disposal by contractor. Analysis and review with the Park is on-going.
Part of project Hazardous Material/Waste Storage
Permit
Permit Type:Law, regulation, etc. Requirements, Actions, Etc.:
RCRA-40 CFR Parts 264 and 270 RCRA Permit Exceptions include:
Businesses that generate hazardous waste and then store for short periods of time before transporting the waste off site.
NPS units: RD=Regional Director, WRD=Water Resources Division
National Park Service - Denver Service Center 7/26/2024 | page 15 of 15
File details come from the government source that posted it. Updated .