B08_Attach_17_MEVE_218998_Rehab_Chapin_Mesa_Closeout_O_M_Reqs_2024_09_20.pdf

PDF 54 KB Posted

Attached to
MEVE 218998, Rehabilitate Eight Residences and Mus
Solicitation number
140P2025R0094
Issued by

About this file

This is a Closeout and Operation & Maintenance (O&M) Requirements template for National Park Service construction projects, issued by the Denver Service Center on January 27, 2021. The document establishes comprehensive requirements for project completion deliverables organized into six main categories: Project Record Drawings, System Demonstration and Training, Tools/Spare Parts/Equipment, Extra Stock, Reports, and Keys & Keying Schedule.

Key requirements include final project record drawings for all building systems (fire sprinkler, plumbing, mechanical, electrical, communications, fire alarm, and sanitary sewer), along with documentation of embedded utilities and concealed components. The contractor must provide system training for fire sprinkler operations, mechanical equipment, electrical systems, and fire alarm systems, including minimum 2-8 hours of hands-on instruction. Essential deliverables encompass spare parts (fire sprinkler cabinet with three spare heads of each type, 50 spare bricks, 20 square feet of each tile combination, one gallon of each paint color), commissioning reports, test and balance reports, environmental documentation, and comprehensive O&M manuals. The template also specifies extensive warranty requirements ranging from 1-20 years for various building components including roofing systems (20-year TPO membrane warranty), door hardware (2-3 years), windows (5 years), and specialized equipment warranties. All deliverables require tracking through submittal dates, completion status, and Park receipt confirmation, with final changeover of permanent locks and key delivery to the Contracting Officer.

View the file

Other files

File Type Posted
Sol_140P2025R0094_Amd_0006.pdf PDF
Attach_34_Answers_to_Questions_Amendment_06_9_18_25_0006.pdf PDF
Sol_140P2025R0094_Amd_0005.pdf PDF
Attach_33_Answers_to_Questions_Amendment_05_9_8_25_0005.pdf PDF
Sol_140P2025R0094_Amd_0004.pdf PDF
Attach_32_Answers_to_Questions_Amendment_04_9_4_25_(4)_0004.pdf PDF
Attach_31_Answers_to_Questions_Amendment_03_0003.pdf PDF
Sol_140P2025R0094_Amd_0003.pdf PDF
B11_Attach_30_MEVE_Pre_Prop_Slides_0003.pdf PDF
B11_Attach_29_MEVE_218998_-_Pre_Proposal_Conference_Attendance_0002.pdf PDF
Sol_140P2025R0094_Amd_0002.pdf PDF
Sol_140P2025R0094_Amd_0001.pdf PDF
MEVE_218998_PreProposalAgenda_2025_08_26_0001.pdf PDF
B08_Attach_26_MEVE_218998_FIO_HPG_Final_2023_09_29.pdf PDF
B08_Attach_11_Solit_PSP_Vol_II_BidBond.pdf PDF
B08_Attach_08_Solit_PSP_Vol_I_PastPerf_REQD.docx DOCX document
B08_Attach_15_MEVE_218998_Rehab_Chapin_Mesa_StatementOfStructuralTestsSpecialInspections_2024_09_20.pdf PDF
B08_Attach_02_MEVE_218998_Rehab_Chapin_Mesa_Final_CD_Drawings_Part_1_of_2.pdf PDF
B08_Attach_12_Solit_PSP_Vol_II_GenRefs.pdf PDF
B08_Attach_20_MEVE_218998_FIO_Rehab_Chapin_Mesa_Topographic_Survey_2022_12_22.pdf PDF
B08_Attach_14_MEVE_218998_Rehab_Chapin_Mesa_Product_File_2024_09_20.pdf PDF
B08_Attach_22_MEVE_218998_FIO_Final_Utility_Locate_Report_2023_11_10.pdf PDF
Sol_140P2025R0094.pdf PDF
B08_Attach_09_Solit_PSP_Vol_I_Exp_REQD.pdf PDF
B08_Attach_04_-_Wage_Determination.pdf PDF
B08_Attach_27_MEVE_218998_FIO_Empire_Electric_Service_2023_09_22.pdf PDF
B08_Solit_Clauses_Construction_06Aug2025.pdf PDF
B08_Attach_19_MEVE_218998_FIO_Rehab_Chapin_Mesa_Permit_Assessment_Form_2024_08_02.pdf PDF
B08_Attach_01_MEVE_218998_Rehab_Chapin_Mesa_Final_CD_Specifications_2024_09_20.pdf PDF
B08_Attach_03_MEVE_218998_Rehab_Chapin_Mesa_Final_CD_Drawings_Part_2_of_2.pdf PDF
B08_Attach_18_MEVE_218998_FIO_Rehab_Chapin_Mesa_Permit_List_2024_08_02.pdf PDF
B08_Attach_25_MEVE_218998_FIO_Hazardous_Materials_Survey_Report_2023_07_14.pdf PDF
B08_Attach_13_Solit_PSP_Vol_II_LmtOnSubcontracting_REQD.xlsx XLSX spreadsheet
B08_Attach_06_Solit_PSP_Vol_II_SubKPlan_REQD_RELEASED_v2_Mar25.pdf PDF
B08_Attach_21_MEVE_218998_FIO_Rehab_Chapin_Mesa_Final_Geotech_Report_2023_11_30.pdf PDF
B08_Attach_23_MEVE_218998_FIO_Sewer_Lateral_CCTV_Inspection_Map_2023_03_30.pdf PDF
B08_Attach_07_Solit_PSP_Cover.pdf PDF
B08_Attach_16_MEVE_218998_Rehab_Chapin_Mesa_Submittal_List___Review_Estimate_2024_09_20.xlsx XLSX spreadsheet
B08_Attach_10_Solit_PSP_Vol_II_Equals_RELEASED_v1_25Feb25.pdf PDF
B08_Attach_24_MEVE_218998_FIO_Sewer_Lateral_CCTV_Inspection_Report_2023_03_30.pdf PDF
B08_Attach_05_MEVE_218998_Rehab_Chapin_Mesa_ContractPriceSchedule_blank_2024_09_20.xlsx XLSX spreadsheet
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Closeout and Operation & Maintenance (O&M) Requirements National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21

Topic Specification

Section Requirement

Submittal

Date Completed

Received by Park

01770 Final Project Record Drawings.

Record locations of embedded utilities and components concealed from view.

21 13 00 Fire Sprinkler Shop level drawings with calculations

22 00 00 Plumbing record drawings

Project Record 23 00 00 Mechanical record drawings

Drawings 26 00 00 Electrical Record Drawings

26 24 16 Record changes in panelboard schedules and circuiting plans

27 00 00 Communications Record Drawings

28 00 00 Electronic Safety and Security Basic Requirements

28 31 00 Fire Alarm record drawings

33 31 00 Sanitary Sewer Project Record Documents

21 00 00 Fire Sprinkler system training: operations, scheduled inspissation times, hands-on instructions

23 81 29 Owner Training of mechanical equipment.

26 00 00 Electrical equipment and system demonstration and training.

System 26 09 24 Provide minimum of 2-hour training session to Government at a time approved by Contracting Officer. Training to include discussion of operation, adjustment, and replacement of sensors, photocells and control.

Demonstration 28 00 00 Training of Operating Personnel and Training 28 10 00 Provide eight hours of training of operational instruction and two hours of maintenance instruction.

28 31 00 Fire alarm system training: basic operation, detailed operation, hands-on instruction, classroom instruction.

10 31 00 Fireplace Tools: Provide shovel, brush, poker, and tongue tool set, finished to match hearth enclosure.

Tools, Spare Parts and Equipment 21 13 00

Fire Suppression: Spare Fire Sprinkler Cabinet - Sized to accommodate a minimum of three spare sprinklers of each type and temperature. Welded steel with hinged steel cover. Polyester coated finish inside and out. Attach to wall at the main sprinkler system riser. Locate so cover is easy to open and readily accessible. Locate in an area with a temperature between

40 and 100 degrees Fahrenheit. Locate sprinkler wrenches inside cabinet. Inside the cabinet, provide a list of sprinklers installed in the property, including sprinkler identification number, manufacturer, model, orifice, deflector type, thermal sensitivity and pressure rating, quantity of each type to be contained in the cabinet and issue or revision date of the list.

31 05 19 Geotextiles for Earthwork: Furnish two seam repair kits, special and other devices for Owner to maintain and repair geotextile material.

04 03 00 Spare parts: Provide 50 bricks for Park’s use in maintenance of project.

09 30 00 Maintenance Materials: 20 square feet of each tile size, color, and surface finish combination.

09 91 13 Extra Paint and Finish Materials: 1 gallon of each color; from the same product run.

Extra Stock 09 91 23 Extra Paint and Finish Materials: 1 gallon of each color; from the same product run.

21 13 00 Stock of spare sprinkler heads with associated wrench.

31 05 19.13 Furnish two seam repair kits.

01 32 33 Complete set of digital image electronic files

01 74 19 Project Waste Management Plan worksheet for solid waste disposal and diversion

01 77 00 NPS Required forms for occupancy, Fire Alarm acceptance, and other similar forms or certificates

01 77 00 Environmental Record Documents: IAQ Management Plan

01 77 00 Environmental Record Documents: Moisture Control Inspection and Reports

01 77 00 Environmental Record Documents: Material Safety Data Sheets

01 77 00 Pest Control Report

01 77 00 Test and Balance Report

01 91 14 Commissioning Reports

02 82 00 Final Visual Inspection and Clearance Testing, Certificate of Completion

Closeout and Operation Maintenance (O) Requirements Template | National Park Service (NPS) - Denver Service Center (DSC) page 1 of 4

Topic Specification

Section Requirement

Submittal

Date Completed

Received by Park

02 82 00 Final Visual Inspection and Clearance Testing, Certificate of Completion

02 84 00 Final Visual Inspection, Certificate of Completion

Reports 02 87 00 Final Visual Inspection, Certificate of Completion

21 00 00 Commissioning Report

22 33 00 Leak test, Operational test, Test to adjust control and safeties.

23 05 00 MFG technical representative/ Factory-authorized service representatives field reports

23 05 93 Certified TAB reports

26 00 00 Commissioning Report

26 05 19 Cable Insulation test reports

26 05 26 Grounding and Bonding test reports

26 05 73 Electrical Distribution Systems Study, submit report showing final adjusted settings of protective devices.

26 09 20 Prepare and complete report of test procedures and results.

26 09 23 Provide complete report of test procedures and results.

26 41 13 Final Inspection Report

27 15 00 Horizontal Cabling Test Report

27 53 20 Cable Television Cabling Test Report

28 00 00 Commissioning Report

28 31 00 Fire alarm test reports, certification of installation

01 77 00 Make final changeover of permanent locks and deliver keys to Contracting Officer. Advise Park personnel of changeover in security provisions.

08 71 00 Door Hardware: Submit (3) copies of Keying Schedule in compliance with requirements established during Keying

Requirement Meeting unless otherwise indicated.

Keys & Keying 28 31 00 Fire alarm keys

Schedule

01 56 39 Tree and other plant maintenance during and after completion of construction

O&M Data, Warranties and

Guarantees

07 54 23

TPO Membrane Roofing: Material Warranty: See Section 01 7800 - Closeout Submittals for additional warranty requirements. Provide membrane manufacturer's warranty agreeing to replace material that shows manufacturing defects within 10 years after installation. System Warranty: Provide manufacturer's system warranty agreeing to repair or replace roofing that leaks or is damaged due to wind or other natural causes.

1. Warranty Term: 20 years.

2. For repair and replacement include costs of both material and labor in warranty.

3. Include accidental punctures according to the manufacturer's standard warranty terms.

4. Include hail damage according to the manufacturer's standard warranty terms.

07 62 00

Sheet metal flashing and trim: Installers warranty: The contractor shall warrant that the work will remain free from defects of labor and materials used in conjunction with his work in accordance with the general conditions for this project or a maximum of three (3) years.

1. Warranty includes installation, leaks, displacement, failed joints, and damages to other building components impacted by failure.

Special Finish Warranty: Submit a written warranty, signed by manufacturer, covering failure of the factory-applied exterior finish on metal wall panels within the specified warranty period and agreeing to repair finish or replace panels that show evidence of finish deterioration. Deterioration of finish includes, but is not limited to, color fade, chalking, cracking, peeling, and loss of film integrity.

1. Finish Warranty Period: 20 years from date of Substantial Completion.

07 92 00

Join Sealants: See Section 01 78 00 - Closeout Submittals for additional warranty requirements.

Manufacturer Warranty: Provide 2-year manufacturer warranty for installed sealants and accessories that fail to achieve a watertight seal, exhibit loss of adhesion or cohesion, or do not cure. Complete forms in Contracting Officer's name and register with manufacturer.

Extended Correction Period: Correct defective work within 2-year period commencing on Date of Substantial Completion.

08 14 33

Stile and Rail Wood Doors: See Section 01 77 00 - Closeout Procedures for additional warranty requirements.

Interior Doors: Provide manufacturer's warranty for the life of the installation. Include coverage for delamination of veneer, warping beyond specified installation tolerances, defective materials, and telegraphing core construction.

Closeout and Operation Maintenance (O) Requirements Template | National Park Service (NPS) - Denver Service Center (DSC) page 2 of 4

Section Requirement

Submittal

Date Completed

Received by Park

08 52 00

Wood Windows: Correct defective Work within a five year period after Date of Substantial Completion. Manufacturer

Warranty: Provide 5-year manufacturer warranty for insulated glass units against seal failure, interpane dusting or misting, and replacement of same. Complete forms in Owner's name and register with manufacturer. Manufacturer Warranty:

Provide 2-year manufacturer warranty against defects listed. Complete forms in Owner's name and register with manufacturer or warrantor.

1. Degradation of color finish.

2. Delamination or separation of finish cladding from window member.

08 71 00

Door Hardware: See Section 01 78 00 - Closeout Submittals for additional warranty requirements. Manufacturer's Warranty:

Provide warranty against defects in material and workmanship for period indicated. Complete forms in Contracting Officer's name and register with manufacturer.

1. Locksets and Cylinders: Three years, minimum.

2. Other Hardware: Two years, minimum.

08 80 00

Glazing: See Section 01 77 00 - Closeout Submittals for additional warranty requirements. Insulating Glass Units: Provide a five (5) year manufacturer warranty to include coverage for seal failure, interpane dusting or misting, including providing products to replace failed units

10 31 00

Manufacture Fireplaces: Manufacturer Warranty: Provide Limited lifetime manufacturer warranty. Complete forms in

Owner's name and register with manufacture. Catalyst Combustor: Provide 10-year manufacturer warranty. Complete forms in Owner's name and register with manufacturer

11 30 13 Residential Appliance: Provide five (5) year manufacturer warranty on refrigeration system of refrigerators. Provide ten (10) year manufacturer warranty on tub and door liner of dishwashers.

12 24 00

Window Shades: Provide manufacturer's warranty from Date of Substantial Completion, covering the following:

1. Shade Hardware: One year.

2. Fabric: One year.

3. Aluminum and Steel Coatings: One year.

12 35 30 Residential Casework: Correct defective Work within a five year period after Date of Substantial Completion.

21 00 00 Operation and Maintenance Manuals for devices valves and sprinkler heads, including air compressor and associated parts

21 00 00 Installing contractor warranty and guaranty certificates; 1-year labor.

22 05 00 O&M Manuals

22 05 19 O&M Manuals

22 11 19 O&M Manuals

22 13 19 O&M Manuals

22 14 29 O&M Manuals

22 33 00 O&M Manuals

22 41 00 O&M Manuals

23 33 00 O&M Manuals

23 34 23 O&M Manuals

23 81 29 O&M Manuals

23 81 29 Warranty

23 82 39 O&M Manuals

26 00 00 Electrical Contractor 1-year Warranty and O&M Data

26 24 16 O&M Data.

26 27 13 O&M Data.

26 43 00 O&M Data. 10-year warranty, incorporating unlimited replacements of SPD if they are destroyed by transients within warranty period.

26 51 00

O&M Data. Not less than 5 years for luminaire based on date of substantial completion. Includes cost of labor to replace luminaire. Replacement luminaire will match physical dimensions, physical appearance, chromaticity, lumen output and photometric characteristics of original installed equipment.

27 00 00 Contractor 1-year Warranty and O&M Data

28 00 00 Contractor 1-year Warranty and O&M Data

Closeout and Operation Maintenance (O) Requirements Template | National Park Service (NPS) - Denver Service Center (DSC) page 3 of 4

Section Requirement

Submittal

Date Completed

Received by Park

28 10 00 O&M Data

28 31 00

Warranty covering fire alarm system for one year. Operation and maintenance manual with catalog cut sheets, installation sheets, manufacturer O&M manuals, data file printout, record drawings, warranty, record of completion, test reports, instruction charts.

31 10 00 Acceptance

Closeout and Operation Maintenance (O) Requirements Template | National Park Service (NPS) - Denver Service Center (DSC) page 4 of 4