Attach_34_Answers_to_Questions_Amendment_06_9_18_25_0006.pdf

PDF 304 KB Posted

Attached to
MEVE 218998, Rehabilitate Eight Residences and Mus
Solicitation number
140P2025R0094
Issued by

About this file

This document is a Questions and Answers (Q&A) amendment for Solicitation 140P2025R0094, a rehabilitation project for eight residences and a museum at Chapin Mesa in Mesa Verde National Park. The project involves comprehensive renovation work including historic preservation, electrical, mechanical, plumbing, and utility upgrades across multiple buildings. Key details include an estimated Notice to Proceed (NTP) date of January 12, 2026, with a 550-calendar day performance period, and a proposal due date extended to September 24, 2025. The project requires careful coordination with National Park Service (NPS) personnel, preservation of historic architectural features, and adherence to specific technical specifications for each building system.

The Q&A document addresses numerous technical and procedural questions from potential contractors, covering topics such as utility relocations, fire suppression systems, asbestos abatement, electrical service upgrades, and historic preservation treatment procedures. Notable requirements include wet-pipe fire suppression systems in residential quarters, VRF mechanical systems, specific wood repair levels for historic elements, and strict vegetation control managed by the park. The Construction Contractor will be responsible for coordinating utility services, managing temporary facilities, and ensuring minimal disruption to park operations during the rehabilitation process, with the NPS maintaining oversight and providing specific guidance through the construction documents.

View the file

Other files

File Type Posted
Sol_140P2025R0094_Amd_0006.pdf PDF
Sol_140P2025R0094_Amd_0005.pdf PDF
Attach_33_Answers_to_Questions_Amendment_05_9_8_25_0005.pdf PDF
Sol_140P2025R0094_Amd_0004.pdf PDF
Attach_32_Answers_to_Questions_Amendment_04_9_4_25_(4)_0004.pdf PDF
Attach_31_Answers_to_Questions_Amendment_03_0003.pdf PDF
Sol_140P2025R0094_Amd_0003.pdf PDF
B11_Attach_30_MEVE_Pre_Prop_Slides_0003.pdf PDF
B11_Attach_29_MEVE_218998_-_Pre_Proposal_Conference_Attendance_0002.pdf PDF
Sol_140P2025R0094_Amd_0002.pdf PDF
Sol_140P2025R0094_Amd_0001.pdf PDF
MEVE_218998_PreProposalAgenda_2025_08_26_0001.pdf PDF
B08_Attach_26_MEVE_218998_FIO_HPG_Final_2023_09_29.pdf PDF
B08_Attach_11_Solit_PSP_Vol_II_BidBond.pdf PDF
B08_Attach_08_Solit_PSP_Vol_I_PastPerf_REQD.docx DOCX document
B08_Attach_15_MEVE_218998_Rehab_Chapin_Mesa_StatementOfStructuralTestsSpecialInspections_2024_09_20.pdf PDF
B08_Attach_02_MEVE_218998_Rehab_Chapin_Mesa_Final_CD_Drawings_Part_1_of_2.pdf PDF
B08_Attach_12_Solit_PSP_Vol_II_GenRefs.pdf PDF
B08_Attach_20_MEVE_218998_FIO_Rehab_Chapin_Mesa_Topographic_Survey_2022_12_22.pdf PDF
B08_Attach_14_MEVE_218998_Rehab_Chapin_Mesa_Product_File_2024_09_20.pdf PDF
B08_Attach_22_MEVE_218998_FIO_Final_Utility_Locate_Report_2023_11_10.pdf PDF
B08_Attach_17_MEVE_218998_Rehab_Chapin_Mesa_Closeout_O_M_Reqs_2024_09_20.pdf PDF
Sol_140P2025R0094.pdf PDF
B08_Attach_09_Solit_PSP_Vol_I_Exp_REQD.pdf PDF
B08_Attach_04_-_Wage_Determination.pdf PDF
B08_Attach_27_MEVE_218998_FIO_Empire_Electric_Service_2023_09_22.pdf PDF
B08_Solit_Clauses_Construction_06Aug2025.pdf PDF
B08_Attach_19_MEVE_218998_FIO_Rehab_Chapin_Mesa_Permit_Assessment_Form_2024_08_02.pdf PDF
B08_Attach_01_MEVE_218998_Rehab_Chapin_Mesa_Final_CD_Specifications_2024_09_20.pdf PDF
B08_Attach_03_MEVE_218998_Rehab_Chapin_Mesa_Final_CD_Drawings_Part_2_of_2.pdf PDF
B08_Attach_18_MEVE_218998_FIO_Rehab_Chapin_Mesa_Permit_List_2024_08_02.pdf PDF
B08_Attach_25_MEVE_218998_FIO_Hazardous_Materials_Survey_Report_2023_07_14.pdf PDF
B08_Attach_13_Solit_PSP_Vol_II_LmtOnSubcontracting_REQD.xlsx XLSX spreadsheet
B08_Attach_06_Solit_PSP_Vol_II_SubKPlan_REQD_RELEASED_v2_Mar25.pdf PDF
B08_Attach_21_MEVE_218998_FIO_Rehab_Chapin_Mesa_Final_Geotech_Report_2023_11_30.pdf PDF
B08_Attach_23_MEVE_218998_FIO_Sewer_Lateral_CCTV_Inspection_Map_2023_03_30.pdf PDF
B08_Attach_07_Solit_PSP_Cover.pdf PDF
B08_Attach_16_MEVE_218998_Rehab_Chapin_Mesa_Submittal_List___Review_Estimate_2024_09_20.xlsx XLSX spreadsheet
B08_Attach_10_Solit_PSP_Vol_II_Equals_RELEASED_v1_25Feb25.pdf PDF
B08_Attach_24_MEVE_218998_FIO_Sewer_Lateral_CCTV_Inspection_Report_2023_03_30.pdf PDF
B08_Attach_05_MEVE_218998_Rehab_Chapin_Mesa_ContractPriceSchedule_blank_2024_09_20.xlsx XLSX spreadsheet
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140P2025R0094 / Amendment 06/

09.18.2025

MEVE 218998, Rehabilitate Eight Residences and Museum at Chapin Mesa

Question No.

Sheet or

Reference Question Response

Considering the complexity of this project and all of the different facets involved, Mihm is wondering if it would be possible to extend the bidding process for at least 2 weeks, from September 10th to September 24th or Oct. 1st?

Yes, the proposal due date has been extended from September 10, 2025 to September 24, 2025.

8/28/2025

What are the specific phasing, staging, and sequencing restrictions for construction operations within the park, including visitor access, tunnel load/height restrictions, haul routes, and allowable construction hours?

Phasing, Staging, and sequencing are at the discretion of the Construction Contractor. Construction Schedules are a DIV 01 submittal and subject to review by NPS per 01 31 00. General information re: construction hours, tunnel information, etc. are noted within 01 11 00 “Summary of Work”.

9/4/2025

How should the contractor coordinate with concurrent and future NPS projects such as Spruce Tree Arch Stabilization, Cliff Palace Observation Deck, FHWA roadwork, and Trail Lighting?

Coordination calls amongst the various project teams and personnel will be facilitated by NPS on an as needed basis to deconflict and ensure minimal to no impacts to all projects as is practicable.

9/4/2025

Which permits are to be furnished by NPS and which are the responsibility of the contractor, including environmental, species, and cultural permits?

Refer to 01 31 00 “Project Management and Coordination”, 1.9 PERMITS. 9/4/2025

What are the required historic treatment procedures for masonry, wood, plaster, windows, and doors as specified in Divisions 04, 06, 08, and 09?

Treatment procedures are at the discretion of the Construction Contractor as these are considered “means and methods”. Per DIV 01 The Construction Contractor is required to submit a Historic Preservation Treatment Plan which shall outline the Construction Contractors intended approach to rehabilitation/preservation - see 01 35 91 for further details.

9/4/2025

Which materials and finishes are approved for flooring, plaster, paint systems, and casework to align with the Historic Preservation Guide recommendations?

The Construction Contractor shall reference the Construction Specifications, Drawings, and supporting documentation such as the Product File – all of which are included with the solicitation documentation. Items therein are intended as basis of design establishing minimum technical criteria.

9/4/2025

Question No.

Sheet or

Reference Question Response

Should historic architectural features such as vigas, latillas, and fireplace details be salvaged, replicated, or replaced with new construction?

Refer to 01 35 91 Historic Preservation Treatment Procedures for general guidance on this topic. Typically preservation and/or rehabilitation of existing historic fabric is preferred in lieu of replication and/or replacement – however, case by case considerations are often required.

9/4/2025

What are the required stabilization methods for cracked or tilted slabs, sandstone walls, and chimneys per the geotechnical and structural reports?

Construction methodology and processes are at the discretion of the Construction Contractor as these are considered “means and methods”.

9/4/2025

How should utility relocation and replacement (water, sewer, telecom, electric) be coordinated where conflicts exist between GPR mapping, CCTV inspections, and construction drawings?

The Construction Contractor is responsible for confirming locations of utilities prior to commencement of construction activities.

9/4/2025

What is the required method for sanitary sewer lateral replacement based on the CCTV inspection findings?

Construction methodology and processes are at the discretion of the Construction Contractor as these are considered “means and methods”.

9/4/2025

What are the design expectations for site drainage upgrades given the topographic survey and stormwater pollution prevention requirements?

Please rephrase this question to ensure best response.

9/4/2025

Which mechanical systems (unit heaters, VRF, baseboards) are to be selected where the specifications list multiple options?

The Construction Contractor shall reference the Construction Specifications, Drawings, and supporting documentation such as the Product File – all of which are included with the solicitation documentation. Items therein are intended as basis of design establishing minimum technical criteria.

9/4/2025

What are the fire suppression design criteria, and what specific training and spare requirements must be met?

Refer to 21 00 00 “Fire Suppression Basic Requirements” 9/4/2025

What plumbing fixture types and connection requirements are approved, particularly with respect to integration with historic interiors?

The Construction Contractor shall reference the Construction Specifications, Drawings, and supporting documentation such as the Product File – all of which are included with the solicitation documentation. Items therein are intended as basis of design establishing minimum technical criteria.

9/4/2025

What panelboard schedule updates and circuiting changes must be incorporated into the record drawings versus the new design?

Refer to 01 77 00, 1.2 Project Record Drawings.

Reference Question Response

Where should fire alarm devices be located within historic interiors to comply with both code and preservation requirements?

Locations are clearly noted within the Construction Documents (Drawings). 9/4/2025

What is the approved routing for telecom and data cabling through historic building fabric? Please rephrase this question to ensure best response.

9/4/2025

What is the defined scope of asbestos and lead-based paint abatement per the hazardous materials survey?

Refer to Technical Specifications Division 2 – 02 82 00, and 02 83 00. 9/4/2025

How should PCB- and mercury-containing materials be handled during electrical and plumbing demolition?

Refer to Technical Specifications Division 2 – 02 84 00, and 02 87 00. 9/4/2025

What are the disposal requirements for abated and hazardous materials under this contract? Refer to Technical Specifications Division 2 – 02 82 00, 02 83 00, 02 84 00, and 02 87 00. 9/4/2025

What specific training content must be provided for fire alarm, electrical, sprinkler, and mechanical systems at project closeout?

Refer to Technical Specifications. Refer to 21 00 00 “Fire Suppression Basic Requirements” 3.6 Demonstration. Refer to 01 77 00 and 01 79 00

9/4/2025

What record documents are required at closeout, including as-builts, commissioning reports, test reports, IAQ and moisture control documentation, and pest control reports?

Refer to 01 77 00 – Closeout Procedures.

9/4/2025

What is the interior and exterior color of the frames? Refer to 09 91 13 and 09 91 23.

9/4/2025

What are the desired glass specs? Refer to 08 52 00, 08 80 00, and other pertinent

Specification sections. 9/4/2025

Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals? Yes.

9/4/2025

Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?

The POP will not start until NTP is issued. Typically that is after Division 1 have been reviewed and approved.

9/4/2025

27 Amendement 03 Please provide the site visit attendee sign in sheet. The sign in sheet for the Pre-Proposal Conference was posted with Amendment 03 on 08/28/2025. 9/4/2025

Are soil boring reports available? If not, will it be assumed that excavation will be clear of rocks and obstructions?

Refer to Technical Specifications, Appendix A, “Geotechnical Investigation”. 9/4/2025

Reference Question Response

Is there a bulk water fill (i.e. a hydrant or water source) available in close proximity for construction operations?

Yes – refer to Construction Drawings, utility survey series for location(s). 9/4/2025

Please confirm whether asbestos or lead is present on this project, and if so, provide the relevant documentation.

Refer to Technical Specifications and Appendix B “Hazardous Material Survey”. 9/4/2025

Does this project require phasing? Phasing, Staging, and sequencing are at the discretion of the Construction Contractor. 9/4/2025

Is this project tax exempt? No, this project is not tax exempt.

9/4/2025

When do you anticipate on site work starting? The estimated NTP Proceed date is January 12, 2026.

9/4/2025

Are third party inspections required? Inspection requirements vary by element of work and may require third party qualified or certified personnel.

Refer to sections 02 through 49 for specific inspection requirements which may require third party engagement.

For specific project scope work, please submit inquiries re: specific inspections as necessary.

9/4/2025

Is permitting required? Refer to 01 31 00 “Project Management and

Coordination”, 1.9 PERMITS.

9/4/2025

Is any landscaping restoration required for this project, such as topsoil, seeding, and fertilizer? Refer to Division 32 and Construction Drawings

(LANDSCAPE series). 9/4/2025

Please confirm if all utility laterals (water, sewer, electric, telecom) are to be replaced fully to the main, or only from each building to the nearest connection point.

Laterals shall connect to mains as indicated within the Construction Documents. 9/4/2025

Are there phasing requirements for utility cutovers to minimize service interruptions to occupied park facilities?

Outages and cutovers shall be coordinated between Construction Contractor and NPS to minimize service disruptions to NPS / park facilities.

9/4/2025

Please confirm if temporary utility services (power, water, telecom) are required during cutover phases, and if so, what the expected duration is.

Temporary utility services are not an anticipated requirement – outages at Building 13 / Archaeological Museum shall be coordinated to minimize impacts and disruptions.

9/4/2025

Please confirm that fire suppression is required in all residences (Quarters 1–8) but not in the Museum, which only requires electrical upgrades.

Fire Protection is required at Quarters 1-8 per Construction Documents. No Fire Protection work is in scope at Building 13 / Archaeological Museum .

Reference Question Response

Are dry systems required for any portions of fire suppression due to freeze protection, or will all systems be wet-pipe?

All systems are wet pipe.

9/4/2025

CCTV report identifies vitrified clay pipe in multiple laterals—please confirm replacement pipe material (PVC SDR-35 vs DIP) for sanitary sewer.

Refer to 33 31 00 “Sanitary Sewerage Piping”. Refer to Construction Drawings and Technical Specifications for material requirements (i.e. reference Civil Sheets). 9/4/2025

Please clarify if domestic water service is to be copper Type K, HDPE, or alternate. Refer to 33 14 16 “Site Water Utility Distribution

Piping”.

9/4/2025

Are plumbing fixture selections confirmed per the product file, or are alternates acceptable? The Construction Contractor shall reference the Construction Specifications, Drawings, and supporting documentation such as the Product File. Items therein are intended as basis of design establishing minimum technical criteria.

9/4/2025

Please confirm that VRF systems are the basis of design for residences, and identify whether any backup heating systems are required (e.g., electric baseboard).

Refer to Construction Drawings – specifically Mechanical Plans and Schedules which indicate VRF and BASEBOARD.

9/4/2025

Does the Museum HVAC upgrade scope include replacement of all existing SCADA controls, or only electrical integration with the new equipment?

Refer to Construction Drawings and Technical Specifications – there is NO HVAC scope at Building 13 / Archaeological Museum.

9/4/2025

Is temporary heating/cooling required for occupied facilities during switchover? Temporary utility services are not an anticipated requirement – outages at Building 13 / Archaeological Museum shall be coordinated to minimize impacts and disruptions.

9/4/2025

Please confirm if new electrical services will require Empire Electric coordination and service upgrade fees to be included in the contractor’s scope.

YES, refer to solicitation FIO document “Empire_Electric_Service_2023_09_23”. 9/4/2025

Are existing underground electrical vaults to be abandoned and replaced, or reused with new feeders?

Please clarify which (if any vaults) the question refers

to. 9/4/2025

Please confirm if lightning protection is required for both the residences and museum. Lightning Protection is in scope ONLY at Building 13 -aka - Archaeological Museum. 9/4/2025

Please clarify whether the telecom scope is limited to horizontal cabling inside each building, or includes backbone/site distribution.

Refer to Construction Drawings – specifically Technology Plans which indicate interior and exterior scope.

Reference Question Response

Is there an existing telecom service provider identified for final tie-in (CenturyLink, Mediacom, etc.)?

Lumen Technologies (formerly CenturyLink) is the telecom provider for Mesa Verde National Park. 9/4/2025

GPR utility locate report identified existing unknowns—please confirm who bears risk for additional utility conflicts not shown on the drawings.

The Construction Contractor is responsible for confirming locations of utilities prior to commencement of construction activities.

9/4/2025

For water line disinfection, is bacteriological testing by an independent lab required prior to acceptance?

Refer to 33 01 10 58 – “Disinfection of Water Utility Piping Systems”, 1.6 “Qualifications”. 9/4/2025

Please confirm the deadline for questions is 9/12/2025. Deadline for questions is September 17, 2025.

9/8/2025

Page G007 Project Overview Site Plan & Staging Plan does not indicate the location of the power and water hook-up for the South Parking Lot Staging Area. Please confirm there is water and power for the temporary facilities that will be installed at the South Parking Lot Staging Area.

There are no power or water services available within the South Parking Lot Staging Area – there are multiple connection points for water and electrical service within the project “footprint” which are indicated within the G200 “Utility” drawing sheets.

9/8/2025

Is there an internet service provider that provides internet and telephone service to the residents? If so, does that service extend to the South Parking Lot Staging Area?

There is no dedicated internet or telecom service provider within Mesa Verder National Park. It is recommended that Construction Contractors consider private sector satellite or other “non-tethered” service options.

9/8/2025

Spec Section 01 50 00 Temporary Facilities & Controls paragraph 2.2.B outlines a requirement for a “Contracting Officers Field Office” separate from the Contractor’s Field Office. How long will the Contractor Officer require this field office? Page G007 indicates the location for this trailer is North of the Tennis Courts. Is there power, water, and internet service available at this location? Is the contractor responsible for internet services for the “Contracting Officers Field Office”?

The Contracting Officer’s Field Office shall be provided for the full duration of construction activities through close out (the Field Office will be utilized by the NPS Construction Management Representative). Disregard 2.2.B. item 3 “Restroom” – use of the Construction Contractor job-site portable restroom facilities shall satisfy this requirement. There are two “slips” north of the Tennis Court area which are managed by the Park concessionaire – these have water and power available – at this time the park is working to facilitate availability of these “slips” – one for Construction Contractor Field Office (aka job trailer) and one for Contracting Officer’s Field Office – this arrangement is currently under discussion between the park and the park concessionaire team. The Construction Contractor is not responsible for providing internet service at the Contracting Officer’s Field Office.

9/8/2025

Reference Question Response

Factor 4 Schedule says the accompanying narrative is limited to 5 pages. Please confirm the Gantt Chart is not part of the 5-page narrative limit.

No, the Gantt Chart is not park of the 5-page narrative limit. Per Factor 4 Schedule: In your accompanying narrative (limited to 5 pages), explain schedule logic, critical path activities, and key considerations and constraints.

9/8/2025

Is there an overall page limit for the proposal? Each Factor recommends minimum pages but the solicitation itself does not have an exact limitation number.

9/8/2025

Factor 2 Project Experience – Team Experience states, “Prime Contractor experience is experience as a general contractor managing multiple subcontractors on a project you self-performed at least 60% of the cost of the contract, excluding materials.” On most projects, the General Contractor does not self-perform 60% of the contract. Please clarify this requirement.

Prime Contractor experience is experience as a general contractor managing multiple subcontractors on a project you self-performed at least 20% of the cost of the contract, excluding materials.

9/8/2025

Factor 8 – Small Business Participation states, “All offerors (both other than small business and small business) shall submit Small Business Participation documentation…contained in section M of this solicitation.” Section M states, “Small Business Offeror will receive the maximum credit for this evaluation factor and do not need to submit any documentation supporting this evaluation. Please clarify if Small Business Offers need to submit a small business plan or if they DO NOT need to submit a small business plan”.

Small Businesses do not need to submit a Small Business Plan.

9/8/2025

Specification Section 01 50 00 – Temporary Facilities Paragraph 1.3.C states the electrical service is supposed to be transferred to the contractor for projects longer than 1 year. This project has a duration longer than 1 year. Is the contractor supposed to cover the cost for all 8 residents' meters, the museum, and the temporary facilities required?

The Construction Contractor is responsible for “temporary power” costs associated with this project.

Quarters 01 – 08 will be turned over vacant to the Construction Contractor upon Notice to Proceed – there is no anticipated meter draw at the residences during construction, particularly as scope includes new electrical service distribution laterals and meter bases at all 8 Residential Quarters. The Museum and systems shall remain energized for the duration of the project with exception of intermittent outages and change-overs necessitated by scope. The Construction Contractor is responsible only for temporary power costs associated with the Museum scope, but not general Museum metering costs.

9/8/2025

Reference Question Response

Specification Section 01 10 00 - Summary of Work paragraph 1.5.H states “establishment of a camp within the park will not be permitted.” Will temporary RV, or Campers be allowed at the staging area for Prime Contractor Staff ie Superintendent, QC Manager, Safety Manager?

At this time there is no available in-park housing or contractor camp option associated with this project.

9/8/2025

Sheet 01-A802 Door/Window Notes 2, 3, 4 all refer to additional information on sheet A801.

Sheet A801 does not contain any information on the widows, doors, or door hardware. This happens on multiple Quarters' drawings and on the Museum drawings. Please clarify what sheet these notes are referring to.

These references to A801 are a clerical error and should reference either the A802 series sheets “Door and Window Schedules” or A803 series sheets “Door and Window Elevations”.

9/12/2025

Demo Floor Plan 01-AX101 & 01-AX201 both call for the basement windows to be removed and replaced. Sheet 01-A802 Demolition Window Schedule calls for Basement window 1.W0.01X to remain and requires Level 2 Wood Repair. Please confirm that sheet 01-A802 is accurate, and the demo plans are NOT accurate.

Confirming the sheet 01-A802 prevails.

9/12/2025

Sheet 01-A802 Window Schedule calls for sheet 01-A604 for window head, window sill, and window jamb details. The plan set does not contain a sheet 01-A604. Please confirm that this refers to sheet 01-A605, and that sheet 01-A604 does not exist.

Confirming that sheet 01-A605 prevails.

9/12/2025

Sheet 13-EX101 calls for the existing electrical devices in rooms Office 13.006, 13.008, 13.009, 13.011, and new outlets to be installed on sheet 13-E101 at different locations. The walls in this area have drywall that is above 1% ACM. The Hazardous Materials Report and other provided documents are unclear as to whether all ACM drywall exceeding 1% is supposed to be abated or if the Contractor is only required to abate the drywall at electrical devices and associated electrical rough-in.

ACM abatement shall occur only at areas directly associated with Electrical Scope. In certain rooms/locations this may be very localized (single digit square-footages), in other rooms/locations there may be enough Electrical scope to warrant abatement at an entire wall/walls (or similar).

9/12/2025

Are the new site electrical services supposed to be priced in CLINS 5? Correct

9/12/2025

Sheet 01-A101 Floor Plan Legend depicts the wall types for the existing walls to have a diagonal hatching. The new wood walls are solid. The floor plan indicates that all the walls are new wood walls. Please confirm that all the walls are existing and not new wood walls.

This happens on all Quarter and Museum drawings.

Correct – and thank you for bringing this graphic discrepancy to our attention. Thicker walls are existing sandstone construction. Interior “thin” walls are wood framed. NEW wood walls are indicated within A101 (and similar) series drawings via a darker grey shading relative to existing walls.

9/12/2025

Reference Question Response

Sheet 04-A201 Detail 4 South Elevation Note 18 says “All Vigas UON”. Elevation 2 North Elevation, same sheet, note 18 does not have UON after it, and is clearly pointing to 3 of the 7 vigas on this elevation. Keynote 18 same page calls for Level 3 wood repair. Does the “UON” only apply to South Elevation 4 and not North Elevation 2? This is consistent throughout other Quarters and the museum elevations.

This condition appears to be an attempt by the A/E to graphically simplify the drawings. All Vigas shown on both of the noted Elevations shall be understood to require “Level 3 Wood Repair” consistent with note 18.

Drawings within which similar instances occur shall follow the above guidance – i.e., assume “Level 3 Wood Repair”.

9/12/2025

Sheet 04-L101 CLIN 5 states “Re-Vegetate with Native See Typ.” CLIN 1 states “Overseed Typ. By Park,” The boxed text under 'Planting Notes' 5 states, 'Contractor will be responsible for soil preparation at areas of disturbance due to construction. Park will complete re-vegetation with in-kind, native seed and mulch...” The specifications do not contain a specification for seeding or landscaping. Please confirm that CLIN 5 and CLIN 1 seeding and revegetation will be performed by the Park. The contractor should not include revegetation or seeding in their pricing.

Correct. The park maintains strict levels of vegetation control and will perform re-seeding and/or re-vegetation at Contractor prepared areas.

9/12/2025

Addendum 1, 2, 3, 4, 5 all state the period of performance is 11/07/2025 to 5/11/2027.

Addendum 1 says to “Submit your schedule in Gantt Chart format; for evaluation purposes only assume a Notice to Proceed date of 12 Jan 2026”. The period of performance is 550 days after receiving the Notice to Proceed. 550 Calendar days from 1/12/2026 is 7/16/2027.

Should the schedule assume a NTP of 11/07/2025 and a completion date of 5/11/2027, or a Notice to Proceed of 1/12/2026 and a completion date of 7/16/2027?

The Gantt Chart format for evaluation purposes is going to start on January 12, 2026. The period of performance end date will change from 5/11/27 to 7/16/27 to match the 550 schedule after NTP. Dates may shift due to providing Div 1 requirements prior to NTP and actual award date. Dates posted as an answer to this question should only be concerned with providing the Gantt Chart for evaluation.

9/12/2025

Drawing 02-AX102 note 65 states “Remove (E) TPO Roof Membrane and Rigid Insulation.

Abate Hazardous Materials (ASSUMED)”. What are we assuming is hazardous, and what is the quantity?

The NPS is aware of multiple underlying roof “build-ups” below the existing TPO. No destructive testing nor destructive investigations were performed to determine the make-up and/or profile of said underlying “build-ups” – as a result, neither the exact hazardous materials nor quantities are known. It is presumed that underlying “build-ups” will include Asbestos Containing Materials (ACMs) consistent with historic practices (i.e., adhesives or other components).

Reference Question Response

Sheet 05-A101 calls for new wood walls. Please provide the wood wall framing details, i.e., the size of lumber, spacing of studs, and confirm that the wall finish is painted drywall in lieu of plaster. This happens in multiple buildings

•Refer to the following sheets to clarify the above •A601 series (Drawing 04) •A701 series please note there is a reference note at

Drawing 04 which directs to reference sheet A602, this reference should read A601 •S601 series •S602 series •framed partitions/walls shall conform to 06 10 00

“Rough Carpentry”, section 2.4 “Dimensional Lumber Framing” •stud spacing shall be 16” o.c. unless noted otherwise.

•new wall finishes at new framed locations shall conform to 09 21 16 “Gypsum Board Assemblies”

Question #25 asked if the Superintendent, SSHO, and QC Manager need to be three separate individuals. The NPS response was “yes”. On similar projects in the past, the Government has allowed the Quality Control Manager and Site Safety & Health Officer to be the same person. Will the NPS allow the Quality Control Manager to also serve as the SSHO for the Project?

Yes in the past on NPS projects there has been allowed Quality Control Manager and SSHO to be the same person. Yes NPS will consider the Quality Control Manager to also serve as the SSHO for the project.

Specification Section 01 30 40 paragraph 3.2.1.A Coordination with Utility Service Providers

– Electrical states “Contractor is responsible for establishing metering of new and temporary service”. Please clarify if the contractors are responsible for the cost of the new utility transformers and new utility meters? Alternatively, if the contractor is solely responsible for coordinating with Empire Electric for the transformer replacements and new meters, and any incurred costs will be covered by NPS/Empire Electric.

Confirming the first statement - the Construction Contractor is responsible for the cost of new Electric Service Distribution components including, but not limited to : transformers, splitters/junctions, meters, etc.