Attachment H - BESEP Base and Sector San Juan 03AUG21.pdf

PDF 630 KB Posted

Attached to
Design-Build USCG Hurricane Rebuild San Juan Phase III West/Central
Solicitation number
70Z04722R43000001
Issued by

View the file

Other files

File Type Posted
AMEND_012_RFP3 PRICE PROPOSAL FORM rev2.pdf PDF
AMEND 012 SAN_JUAN_PHASE_III.pdf PDF
AMEND 0011_Exchange Trailer - Sales Area.pdf PDF
AMEND 0011 SAN_JUAN_PHASE_III.pdf PDF
AMEND 011_Exchange Trailer -Storage Room.pdf PDF
AMEND 010 SAN JUAN PHASE III.pdf PDF
AMEND 010_RFP3 PRICE PROPOSAL FORM revised.pdf PDF
AMEND_009_ Revised Drawings - West Amendment 9.pdf PDF
AMEND_009_SAN_JUAN_PHASE_III.pdf PDF
AMEND_009_ Space Criteria Sheets - Buildings 117 and 118.pdf PDF
AMEND_009_Attachment G - San Juan_Phasing Diagrams.pdf PDF
AMEND 0008 SAN JUAN PHASE III.pdf PDF
AMEND_007_10878158_AD_104_rev1.pdf PDF
AMEND_007_10878158_A101_rev1.pdf PDF
AMEND_007_SAN_JUAN_PHASE_III.pdf PDF
AMEND 006 SAN_JUAN_PHASE_III_1.pdf PDF
AMEND 0005 SAN_JUAN_PHASE_III.pdf PDF
AMEND_0004_10878158-E-001.pdf PDF
AMEND_0004_10878158-A-112.pdf PDF
AMEND_0004_10878158-E-003.pdf PDF
AMEND_0004_Wage Determination.pdf PDF
AMEND 0004_SAN_JUAN_PHASE_III.pdf PDF
AMEND_0004_10878158-G-001.pdf PDF
AMEND_0003_Attachment L-Part 3 of 3-As-Built Reference Drawings.pdf PDF
AMEND 003 SAN JUAN PHASE III.pdf PDF
AMEND_0003_Attachment K - Final Geotechnical Report and Soil Sampling Report.pdf PDF
AMEND_0003_Space Criteria Sheet H112 General Storage.pdf PDF
AMEND_0003_10878158C102-rev1.pdf PDF
AMEND_003_Attachment L-Part 2 of 3-As-Built Reference Drawings.pdf PDF
AMEND 0003_10878158C101_rev1.pdf PDF
AMEND 0003_Wage_Determination_PR20220001 01072022.pdf PDF
AMEND_0003_Attachment L-Part 1 of 3-As-Built Reference Drawings.pdf PDF
AMEND 0002 SAN JUAN PHASE III.pdf PDF
AMEND 0001.pdf PDF
RFP W-10878158 Appendix A - ComputerGenDrwgs.pdf PDF
TO Announcement San Juan_Phase III_Final_1.pdf PDF
Attachment A - Drawings.pdf PDF
RFP W-10878158 Appendix B - ElectDeliv.pdf PDF
Attachment G - San Juan_Phasing diagrams 2.pdf PDF
10878158 - Final Specifications.pdf PDF
Wage Determination.pdf PDF
Attachment B - Space Criteria Sheets 10_06_21.pdf PDF
Attachment C - BFR 10_06_21.pdf PDF
RFP W-10878158 Appendix D - Design Narrative.pdf PDF
RFP W-10878158 Appendix C - Adept File Naming.pdf PDF
Attachment J - CSTO Electric Vehicle Support Equipment.pdf PDF
Attachment I - CSTO Advanced Metering Infrastructure .pdf PDF
Attachment F - US Coast Guard Public Address.pdf PDF
Attachment E - US_Coast_Guard_ISP_Cabling_Standards.pdf PDF
Attachment D - Final ACM and LBP Survey_ Base San Juan.pdf PDF
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Base San Juan Hurricane Rebuild West and Central Locations

Project No. 10878158 USCG Base San Juan, PR

Attachment H Base Electronics Systems Engineering Plan (BESEP)

U.S. COAST GUARD

Base Electronics System Engineering Plan (BESEP)

RFP SUBMITTAL

Sector San Juan Hurricane Supplemental Rebuild

San Juan, Puerto Rico

C5ISC-ISD-PSB Project: PSB-21-005

SFRL: 07-10878151 & 10878154

Developed by:

C5I Service Center ISD-PSB

300 East Main Street, Suite 750 Norfolk, VA 23510-9103

Date: 03 AUG 2021 C5I-SC submitted on 03AUG21 as approved by Mark Poisson and Peter Roux (ISD-PSB). Various product lines to coordinate through design phase.

PM: LT Joel Amendolara,COR D-B RFP requirements developer

Base Electronics Systems Engineering Plan (BESEP) Sector San Juan

C5ISC-ISD-PSB Project: FRS20016

1. GENERAL

1.1. Introduction

This BESEP provides system design guidelines, equipment space requirements, identifies funding needs, and assigns project execution responsibilities. Areas addressed are data and voice telecommunications, public address (PA) systems, and the minimum guidelines for the building cabling of the electronics infrastructure. The scope of the project is to repair past hurricane damage and make improvements to increase future hurricane resiliency. Work will include construction of two new buildings and a new Gate Guard Shack; first building will house a relocated Command Center, Station/ANT San Juan, and Command personnel; the second building will contain medical/dental in addition to Prevention and Planning personnel. The following current facilities are due to be demolished: Station San Juan, Medical, Exchange, and Guard Shack. Work will also include renovation/refurbishment of most existing buildings, and to the shore-tie boxes.

The project will be accomplished with a single RFP for C5I Infrastructure and underground utilities, however; the project is split into an East and West configuration with phasing to be determined.

1.2. Reference / Historical Background

1.2.1. DD1391 Planning Proposal – Executive Summary

1.2.2. 35% RFP Specifications

This BESEP is based primarily on a site survey conducted 18 – 20 MAY 2021.

1.3. Existing Conditions

1.3.1. Building 100’s main equipment room contains the primary telecommunication functions for the Coast Guard facility. The equipment room contains a Cortelco eOn Millennium PBX whose connection to other buildings is via OSP copper and also fiber to nodes located in Medical (Building 125) and Administration (Building 126).There are two (2) Russellstoll receptacles on each pier shore tie box.

1.3.2. Shore-tie pier connections for data and voice are fed from the Building 100 main telecommunications space to the Command Center where patching is accomplished in two (2) 48 Port Patch Panels (P/P). Currently the cable pairs leading to the cutter shore-tie mounds are experiencing very high failure rates.

1.3.3. The two UPH Facilities on the west side of the Base receive phone lines from OSP copper originating in Building 126.

1.3.4. Supply (building 117) is currently fed (copper and fiber) from the Exchange (Building 120) which will be demolished.

1.3.5. There are two temporary trailers located in the grassy area between Building 119 and the Chief’s Hut. The telecommunications lines for these trailers originate from the telecommunications closet (TC) in Medical (125) and route to a pedestal outside the trailers.

1.3.6. All base Coast Guard telecommunication services (Data and Voice) originate in the Building 100 Entrance Facility located on the first floor. There are non-Coast Guard services (telephone, CATV), controlled by the local telecoms provider (Claro), located throughout the base. The lines for these services travel through the Base underground conduit system). The Coast Guard C5I Service Center does not manage or control these lines.

1.3.7. The Sector uses roof mounted RF antennas located on Building 100 for operations. These antennas support various systems in the Sector San Juan Command Center and will be replaced/relocated to the roof of the new Multi-Mission building. There is a large monopole supporting microwave dishes that are part of the Puerto Rico Area Wideband System Defense Information System Network (PRAWS/DISN) that are supported from an office in building 100. This is not a USCG system.

1.3.8.

2. AREA OF RESPONSIBILITY

Lines of Accounting provided by C5I-ISD-PSB to C5I Product Lines and Shared Service Divisions and to other units are limited to PC&I funding only.

2.1. CG FDCC

2.1.1. Review and comment on this BESEP.

2.1.2. Provide specifications and drawings (as design phases progress) for review by C5ISC-ISD-PSB including floor plans and riser diagrams for data/voice telecommunications, public address (PA) system, wireless access points, and radio frequency (RF) systems; and submit for review site drawings showing pathways for outside plant cabling.

2.1.3. The FDCC construction contractor shall build and test the telecommunications infrastructure in accordance with the construction specifications and drawings.

2.1.4. The FDCC construction contractor shall ensure CAT6A horizontal cabling does not exceed 295 feet in accordance with ANSI/TIA standards.

2.1.5. Provide a layout of underground utilities and other obstructions near any new buildings and other affected areas of the property.

2.1.6. The FDCC construction contractor shall install all outside plant cabling and pathway required for this project including copper and fiber optic.

2.1.7. Ensure the contracted telecommunications system designer holds a Building Industry Consulting Services International (BICSI) certification as a Registered Communications Distribution Designer (RCDD), or equivalent.

2.2. CG C5ISC-ISD-PSB (Infrastructure Services Division-Physical Infrastructure Services Branch)

2.2.1. Assign project manager to manage the overall electronics installation portion of this project.

2.2.2. Submit a BESEP and BESEP modifications, as necessary.

2.2.3. Provide information to C5ISC-ESD-ASB for spectrum management approval. Provided information will include any new transmitters, antennas, antenna height, and location information.

2.2.4. Provide power and horizontal distribution requirements to FDCC for the various product lines and core technologies listed in this BESEP.

2.2.5. Provide Heat Dissipation data to FDCC for HVAC requirements in telecommunications rooms.

2.2.6. Provide space requirements to FDCC for all telecommunications spaces, and other spaces required by the various C5I product lines and core technologies listed in this BESEP. Coordinate inputs with operational commands and applicable Base C5I Support Department.

2.2.7. Review FDCC design and construction drawings and plans for RF, telecommunications, and PA infrastructures. Provide comments to FDCC accordingly.

2.2.8. Request funding from CG-431 or FDCC to purchase all required Electronics Outfitting materials, equipment and labor.

2.2.9. Provide line of accounting to the various product lines and core technologies listed in this BESEP for procurement and installations of their systems and materials.

2.2.10. Process procurement requests, as necessary.

2.2.11. Supervise the electronic outfitting portion of this project.

2.2.12. Coordinate all circuit outages and system down times with applicable operational commands.

2.2.13. Represent the Contracting Officer’s Representative for all testing as specified in Paragraph 3 of this

BESEP.

2.2.14. Initiate requests, with responsible parties, for ordering POTS, OneNet, and other telecommunications circuits and services, as applicable.

2.2.15. Develop cutover plans as required.

2.2.16. Track development of SIPRNET ECP as routed from District Office, through LANT/PAC AREA, and C5ISC-ISD, as applicable.

2.2.17. Track the relocation of SIPRNET circuits and equipment with C5ISC-ISD, LANTAREA, and District Office.

2.2.18. Prepare and submit ITAR package as necessary.

2.3. CG C5ISC-ESD-ASB (Engineering Services Division – Architecture & Standards Branch) for spectrum management

2.3.1. Review and comment on this BESEP.

2.3.2. Review and comment on the potential of the planned Wireless LAN system interfering with existing or planned Coast Guard RF systems.

2.3.3. Ensure spectrum certification is done in accordance with current procedures.

2.4. CG C5ISC-UCPL-TEL (Unified Capabilities Product Line – Telephony Branch) for telephone systems

2.4.1. Review and comment on this BESEP and future design stages and submittals, as necessary.

2.4.2. Review unit PBX system requirements and provide C5ISC-ISD-PSB with cost estimate and design for any new PBX installation requirements.

2.4.3. Provide to C5ISC-ISD-PSB a listing of all power distribution requirements for PBX equipment.

2.4.4. Provide to C5ISC-ISD-PSB a listing of all heat dissipation specifications for PBX equipment.

2.4.5. Coordinate ordering of PBX equipment (switch, interface modules, network switches, cabling, and desk sets).

2.4.6. Install PBX equipment and cabling, configure PBX, and install cross-connects as required for cutover.

2.5. CG C5ISC-UCPL-TEL (Unified Capabilities Product Line – Telephony Branch) for public address systems

2.5.1. Review and comment on this BESEP and future design stages and submittals, as necessary.

2.5.2. Review unit Public address system requirements and provide C5ISC-ISD-PSB with cost estimate and design for a new Public address system hardware including installation.

2.5.3. Provide to C5ISC-ISD-PSB a listing of all power distribution requirements for public address system equipment.

2.5.4. Provide to C5ISC-ISD-PSB a listing of all heat dissipation specifications for public address system equipment.

2.5.5. Coordinate ordering of public address system equipment.

2.5.6. Install public address system equipment and necessary cabling, configure system, and install cross-connects.

2.6. CG C5ISC-ISD-IMS for Coast Guard Standard Workstation (CGSW)

2.6.1. Review and comment on this BESEP and future design stages and submittals, as necessary.

2.6.2. Review to determine if new CGSW equipment is required. Provide a cost estimate for all new requirements to C5ISC-ISD-PSB.

2.6.3. Approve and coordinate installation of new WSIII equipment, as necessary.

2.7. CG C5ISC-UCPL-TEL (Unified Capabilities Product Line – Telephony Branch) for video teleconferencing

2.7.1. Review and comment on this BESEP and future design stages and submittals, as necessary.

2.7.2. Provide to C5ISC-ISD-PSB a listing of all power distribution requirements for SVTC and VTC equipment.

2.7.3. Provide to C5ISC-ISD-PSB a listing of all heat dissipation specifications for SVTC and VTC equipment.

2.7.4. Order and install new SVTC or VTC equipment, as necessary.

2.8. CG C5ISC-ISD-TSB (Infrastructure Services Division – Transport Services Branch) for circuits

2.8.1. Review and comment on this BESEP and future design stages and submittals, as necessary.

2.8.2. Make arrangements for ordering OneNet and SIPRNET circuit changes and contracted relocations of facility routers.

2.8.3. Provide to C5ISC-ISD-PSB a listing of all power distribution requirements for ONENET and SIPRNET equipment.

2.8.4. Provide to C5ISC-ISD-PSB a listing of all heat dissipation specifications for ONENET and SIPRNET equipment.

2.8.5. Execute the SIPRNET circuit and equipment relocations.

2.9. CG C5ISC-ESD-ASB (Engineering Services Division – Architecture & Standards Branch) for

TEMPEST

2.9.1. Review and comment on this BESEP and future design stages and submittals, as necessary.

2.9.2. Make arrangements for inspection of any PDS after installation prior to SIPRNET circuit relocation.

2.9.3. Make arrangements for TEMPEST inspection after building has been accepted.

2.10. CG OL-C5ISC-Portsmouth OISPL Product Line for Command Centers

2.10.1. Review and comment on this BESEP and future design stages and submittals, as necessary.

2.10.2. Develop Command Center and Communications Center cutover plans and provide plans to C5ISC-ISD- PSB project officer.

2.10.3. Provide to C5ISC-ISD-PSB a listing of all telecommunications circuits that must be relocated.

2.10.4. Provide to C5ISC-ISD-PSB a listing of all horizontal drop requirements for the Command Center, including operator positions and locations for wall monitors.

2.10.5. Provide to C5ISC-ISD-PSB a listing of all power distribution requirements for the Command Center, including operator positions and the associated Command Center equipment.

2.10.6. Provide to C5ISC-ISD-PSB a listing of all heat dissipation specifications for the Command Center, including operator positions and the associated Command Center equipment.

2.10.7. Provide to C5ISC-ISD-PSB a listing of all current tower and antenna requirements affected by this construction project.

2.10.8. Provide to C5ISC-ISD-PSB a diagram of the desired floor layout for all operator positions, and all equipment racks in both the Communications Center and in the Secure Command Center telecommunications space.

2.10.9. Procure all new Command Center equipment and materials including approved command center display system, operator consoles, equipment racks, and cabling.

2.10.10. Provide contracting for installation of all new and relocated Command Center equipment and materials.

2.11. CG C5ISC-C2PL-C2B (Command & Control and Navigation Systems Product Line – Command and Control Branch) for Vessel Traffic System

2.11.1. Not Applicable.

2.12. CG C5ISC COMPL-SRS (Communications Systems Product Line – Short Range Systems) for

RESCUE 21

2.12.1. RESCUE 21

2.12.1.1. Review and comment on this BESEP and future design stages and submittals, as necessary.

2.12.1.2. Prepare R21 cutover plan and cost estimate for system relocation. Provide plan and cost estimate to C5ISC-ISD-PSB project officer.

2.12.1.3. Coordinate with C5ISC-ISD-TSB cutover of R21 to OneNet as needed.

2.12.1.4. Provide to C5ISC-ISD-PSB a listing of all horizontal drop requirements for R21, including operator positions and locations for wall monitors.

2.12.1.5. Provide to C5ISC-ISD-PSB a listing of all power distribution requirements for R21, including operator positions and the associated R21 front room equipment and backroom equipment space.

2.12.1.6. Provide to C5ISC-ISD-PSB a listing of all heat dissipation specifications for R21, including operator positions and the associated R21 front room equipment and backroom equipment space.

2.12.1.7. Provide to C5ISC-ISD-PSB a diagram of the desired floor layout for all operator positions, and all equipment racks in both the Communications Center and in the Secure Communications Center telecommunications space.

2.12.1.8. As necessary, procure all new R21 equipment and materials including operator consoles, equipment racks, and cabling.

Provide contracting for installation of all new and relocated R21 equipment and materials.

2.13. CG C5ISC OISPL-EOS (Operations Information Systems Product Line – Enterprise Operations Systems Branch) for NAIS

2.13.1.1. Not applicable.

2.14. CG C5ISC COMPL (Communications Systems Product Line) for short and long range communications systems

2.14.1. Review and comment on this BESEP and future design stages and submittals, as necessary.

2.14.2. Prepare RF systems cutover plan and cost estimate for required equipment and contracted labor.

Provide plan and cost estimate to C5ISC-ISD-PSB project officer.

2.14.3. Provide to C5ISC-ISD-PSB a listing of all telecommunications circuits that must be relocated.

2.14.4. Provide to C5ISC-ISD-PSB a listing of all power distribution requirements for RF equipment.

2.14.5. Provide to C5ISC-ISD-PSB a listing of all heat dissipation specifications for RF equipment.

2.14.6. Procure all new RF equipment and materials.

2.14.7. Provide contracting for installation of all new and relocated RF equipment and materials.

2.15. CG CC3-FMD (Field Maintenance Division)

2.15.1. Review and comment on this BESEP and future design stages and submittals, as necessary.

2.15.2. Assign this project to the appropriate Base C5I Support Department.

2.16. CG Base Miami C5I Department

2.16.1. Review and comment on this BESEP and all future design stages and submittals, as necessary.

2.16.2. Assign designated personnel to attend design reviews of this project.

2.16.3. Assist in determining the requirements for electronics outfitting, as necessary.

2.16.4. Make arrangements for ordering POTS, OneNet, and other telecommunications circuits and services, as applicable.

2.16.5. Coordinate deinstallation of any unused circuits prior to demolition.

2.16.6. Determine ownership and coordinate removal of any unused electronics gear prior to demolition.

2.17. CG ESD San Juan

2.17.1. Review and comment on this BESEP and all future design stages and submittals, as necessary.

2.17.2. Assign designated personnel to attend design reviews of this project.

2.17.3. Assist in determining the requirements for electronics outfitting, as necessary.

2.17.4. Assist in representing the Contracting Officer’s Representative for all testing as specified in Paragraph 3 of this BESEP.

2.17.5. Provide final data and voice cross-connects to contractor-installed wiring, as necessary.

2.17.6. Relocate applicable CG Standard Workstation (CGWS) servers/switches when the new facilities are ready for occupancy.

2.18. CG District Seven Office (DRT)

2.18.1. Review and comment on this BESEP and future design stages and submittals, as necessary.

2.18.2. Develop and route SIPRNET ECP to C5I-ISD for approval.

2.18.3. Coordinate certification of SIPRNET physical spaces.

2.18.4. Coordinate certification of secure video teleconferencing and EKMS equipment relocations, as applicable.

2.19. CG Sector San Juan

2.19.1. Review and comment on this BESEP and future design stages and submittals, as necessary.

2.19.2. Coordinate with District Office for relocation of video teleconferencing and EKMS equipment.

2.19.3. Relocate applicable CG Standard Workstations (CGSW) when the new facility is ready for occupancy.

2.20. CG STATION SAN JUAN

2.20.1. Review and comment on this BESEP and future design stages and submittals, as necessary.

2.20.2. Relocate applicable CG Standard Workstations (CGSW) when the new facility is ready for occupancy.

2.21. CG Vessel Traffic Services Center (VTSC)

2.21.1. Not applicable.

3. TELECOMMUNICATIONS / ELECTRONICS CONSTRUCTION SPECIFICATIONS

Provide and test new telecommunications campus, backbone, and horizontal cabling infrastructure including cabling, work area outlets, equipment racks, horizontal and fiber optic patch panels, cable support trays, conduit paths, wireless access points, and miscellaneous support equipment. Installations shall comply with CAT6A standards and shall be designated in construction specifications, and on applicable shop prints. The Government will install all telecommunications cross-connections, and will provide and install patch cords for telephone and data circuits.

Make all arrangements for, and incur costs of installation of access cabling and pathways between the TELCO facilities (street or property point of presence), and TELCO demarcation within the new facilities. The Government will only make arrangements for the various telephone services (dial tones) required for facility operations. *Government circuit lines will feed from Building 100 but commercial non-government lines (private phone lines for UPH, CATV etc. are the responsibility of the FD&CC contractor).

3.1. References, Codes and Standards

Note: The latest edition, at the time of bid proposal, shall be used.

3.1.1. Electronics Components Industry Association (ECIA) EIA/ECA-310 Cabinets, Racks, Panels and Associated Equipment Standard

3.1.2. Telecommunications Industry Association (TIA-568) Commercial Building Telecommunications Cabling Standard

3.1.3. Telecommunications Industry Association (TIA-569) Commercial Building Standard for Telecommunications Pathways and Spaces

3.1.4. Telecommunications Industry Association (TIA-606) Administration Standard for Commercial Telecommunications Infrastructure

3.1.5. Telecommunications Industry Association (TIA-607) Generic Telecommunications Bonding and Grounding (Earthing) for Customer Premises Standard

3.1.6. Telecommunications Industry Association (TIA-758) Customer-Owned Outside Plant Telecommunications Infrastructure Standard

3.1.7. Telecommunications System Bulletin (TSB-162) Telecommunications Guidelines for Wireless Access Points

3.1.8. Coast Guard COMDINST M5530.1C Physical Security and Force Protection Program

3.1.9. Coast Guard Public Address System Standards (Shore Units Only)

3.1.10. Telecommunications Industry Association (TIA-222) Structural Standard for Antenna Supporting Structures and Antennas

3.1.11. Telecommunications Industry Association (TIA-570) Residential Telecommunications Infrastructure

3.1.12. Chief of Naval Operations/United States Marine Corps Information Assurance Protected Distribution System (PDS) Publication (FOUO)

3.1.13. Coast Guard COMDTINST M2241.6 TEMPEST Program (FOUO)

3.1.14. Coast Guard C5I Shore Tie Cable Standards

3.1.15. National Electrical Safety Code (NESC)

3.1.16. National Fire Protection Association NFPA 13: Standard for the Installation of Sprinkler Systems

3.1.17. National Fire Protection Association NFPA 70: National Electrical Code (NEC)

3.1.18. National Fire Protection Association NFPA 2001: Standard on Clean Agent Fire Extinguishing Systems

3.1.19. Coast Guard Inside Plant (ISP) Cabling Standards

3.1.20. Coast Guard Configuration Standard Technical Order (CSTO) Family Housing

3.2. Contract Requirements

3.2.1. Contractor/subcontractor designing the campus, backbone, wireless access point locations, and horizontal telecommunications cabling infrastructure shall be a certified BICSI RCDD or hold an industry equivalent certification.

3.2.2. Contractor/subcontractor performing campus, backbone, horizontal telecommunications cabling installations, and wireless access point locations shall be a certified BICSI ITS Installer 2 (Copper or Optical Fiber, as appropriate) or hold an industry equivalent certification or higher.

3.2.3. Contractor/subcontractor performing campus, backbone, horizontal telecommunications and wireless access point cabling testing shall be a certified BICSI ITS Technician or hold an industry equivalent certification or higher.

3.3. Existing Conditions

3.3.1. Building 100 equipment room contains the primary telecommunication functions for the Coast Guard on the both the east and west side of the base. The equipment room contains a Cortelco eOn Millennium PBX with connections to various remote nodes provided through an underground 62.5/125micron multi-mode fiber optic cable.

3.3.2. Shore-tie pier connections for data and voice are fed from the main telecommunications space to the Command Center where patching is accomplished in two (2) 48 Port Patch Panels (P/P). Currently the cable pairs leading to the cutter shore-tie mounds are experiencing very high failure rates.

3.3.3. The two UPH Facilities on the west side of the Base receive phone lines from OSP copper originating in Building 126.

3.3.4. Building 117 is currently fed (copper and fiber) from the Exchange (Building 120) which will be demolished.

3.3.5. There are two temporary trailers located in the grassy area between Building 119 and the Chief’s. The telecommunications lines for these trailers originate from the telecommunications closet (TC) in Medical (125) and route to a pedestal outside the trailers.

3.3.6. There are numerous RF Antennas located on the roof of Building 100. These Antennas will be relocated/installed on the roof of the new Command Building located on the East side of the Base. Antennas include VHF, UHF and two Satellite Communication antennas.

3.4. General Requirements

3.4.1. Design, provide, and test all campus, backbone, horizontal cabling, and terminations in accordance (IAW) with the TIA-568 standard.

3.4.2. Provide all cabling pathways and telecommunications spaces IAW the TIA-569 standard.

3.4.3. Telecommunications campus, backbone, horizontal pathways, and cabling penetrations shall be fire-stopped IAW the NFPA 70 and TIA-569 standard.

3.4.4. Design, provide, and test an antenna mounting structure on the new Command Building to replace the existing Building 100 location IAW the TIA-222 standard.

3.4.5. Administrative requirements of the telecommunications system shall be accomplished IAW the TIA-606 standard and shall include the layout of campus cabling and underground conduits. Cabling run sheets, block diagrams and riser diagrams shall be provided to the Contracting Officer’s Representative in either a spreadsheet format, as part of as-built drawings, or as an appendix to other reports.

3.4.6. Grounding and bonding of the telecommunications infrastructure shall be designed and provided IAW the NFPA 70 and the TIA-607 standard.

3.4.7. Dust protection shall be provided for all active telecommunications equipment during construction periods, if applicable.

3.4.8. Provide plywood backboards in the Telecommunications Entrance Facility and in telecommunications spaces IAW the TIA-569 standard. The backboards shall be fabricated from sheets of ¾-inch fire-rated (fire retardant) “A/C” plywood to meet applicable codes. The “A side of the plywood shall be exposed. The plywood shall be mounted on each wall vertically, 10 inches off the floor and extended up to the ceiling; or 106 inches (8’- 10”) from the floor, whichever is lower. The plywood shall be installed in full 8-foot by 4-foot sheets, where possible. All plywood shall be painted with two coats of light colored paint on all exposed surfaces, leaving at least one example of the fire retardant stamp on the plywood on each sheet exposed.

3.4.9. Provide equipment racks in each new building’s telecommunications spaces/closets. The racks shall be open frame or relay style with 19-inch mounting capability. Equipment racks shall be designed for mounting equipment depths of 36 inches, minimum. The racks shall have at least 75 inches of vertical mounting space and shall comply with the EIA/ECA-310 standard. The racks shall be provisioned with vertical cabling management on both sides of racks, and between racks, as applicable. Equipment racks manufactured with anodized aluminum frames shall NOT be provided. Provide a 3-feet minimum clearance space at the front, back, and on non-joined sides of telecommunications and electronic equipment racks. Rack quantities shall be determined by individual space purpose and layout in the final design of the buildings. These racks will be used primarily for the installation of Coast Guard data network, voice and PA system hardware, and horizontal cable distribution.

3.4.10. Provide rack enclosures in the new Command Center space to replace those currently installed. The enclosures shall be 4-post or network style with 19-inch mounting capability, and shall comply with the EIA/ECA- 310 standard. Rack enclosures shall be designed for mounting equipment depths of 36 inches, minimum. The enclosures shall have at least 75 inches of vertical mounting space and shall be provisioned with lockable front and rear hinge style doors, side and top panels, steel frames, and are to be featured with internal vertical cable management on both sides. Front doors shall be vented style. Rear doors shall be vented and split style. Top panels shall be provisioned with grommet or cabling penetration feature, without fan option. Rack enclosures manufactured with anodized aluminum frames shall NOT be provided. Provide a 3-feet minimum clearance space at the front, back, and on non-joined sides of telecommunications and electronic equipment racks. There are currently a total of eleven (11) Rack Enclosures for Command Center backroom functions. Additional floor space is required for the Coast Guard Command Center Display System (CCDS) video matrix system.

3.5. Demolition Requirements

3.5.1.1. Coast Guard personnel shall remove any desired equipment from all buildings designated for demolition prior to demolition. The demolition and/or removal of any remaining equipment/materials shall be the responsibility of the construction contractor.

3.5.1.2. The construction contractor shall be responsible for removing any telecommunications cabling, including outside plant cabling, made obsolete by the renovation or demolition of any building.

3.6. Architectural Requirements

3.6.1. Flooring in telecommunications spaces shall be static dissipative style flooring. Carpeting is not acceptable.

3.6.2. Provide raised flooring for the Command Center and its associated telecommunications spaces.

Determine raised floor height based on conduit stub ups, cabling bend radius, etc. Flooring shall have 24-inch by 24-inch panels with laminate finish.

3.6.3. Doors for telecommunications spaces shall be outward swinging, 36-inch minimum width. Doors, door hinges, locking hardware, and door signage shall meet the requirements of COMDTINST M5530.1C Physical Security and Force Protection Program.

3.6.4. Ceilings in telecommunications spaces shall typically be either a hard floor or roof deck. A gypsum wallboard ceiling at a ten-foot minimum height is acceptable. Lay-in acoustic tile ceilings shall not be used.

3.6.5. Walls in telecommunications spaces shall be finished. Gypsum board finish is acceptable

3.7. Fire Protection Requirements

3.7.1. Sprinklers in telecommunications spaces shall be installed in accordance with NFPA 13. Sprinkler heads, when placed above equipment or racks, shall be provided with wire cage protection, and drain troughs shall be placed under the sprinkler piping to prevent leakage onto the equipment below.

3.7.2. Fire detection and alarm system cabling in interior locations shall be run in conduit or pathway systems separate from telecommunications CAT6A systems. Exceptions are CAT5, CAT5e, CAT6, CAT6A, and fiber optic cabling.

3.7.3. Alternative Automatic Fire-Extinguishing Systems for ITE (Information Technology) Spaces:

3.7.3.1. An alternative automatic fire-extinguishing system shall be provided for ITE spaces as follows:

Dedicated Server Room, Vessel Traffic Services Center (VTSC) telecommunications space, or Secure Command Center telecommunications space.

3.7.3.2. Provide the alternative automatic fire-extinguishing system only IAW NFPA 2001, Standard on Clean Agent Fire Extinguishing Systems. Do not provide automatic sprinkler protection in ITE spaces. The alternative automatic fire-extinguishing system for ITE spaces shall consist of automatic fire detection throughout, with a separate agent release fire alarm sub-panel for each room. Monitor each sub-panel system by the building main fire alarm control panel. Locate agent containers near each room in a location approved by the user.

Provide acceptance testing of each alternative fire-extinguishing system IAW NFPA 2001. Provide areas protected with alternative fire-extinguishing systems in lieu of automatic sprinkler protection to meet appropriate room separation requirements of the applicable code.

3.8. Heating, Ventilating and Air-conditioning (HVAC) Requirements

3.8.1. Telecommunications spaces shall each be provided with dedicated HVAC services. The HVAC service shall be energized from the emergency electrical panel. Provide climate control (temperature and humidity) that will maintain space conditions in accordance with the TIA-569 standard.

3.8.2. The estimated maximum heat dissipation of C5I-related equipment in the Command Center Distributor Room is xxxxx BTU/hr, not including anticipated Building Automated System (BAS) equipment.

3.8.3. The estimated maximum heat dissipation of C5I-related equipment in the new Command/STA/ANT telecommunications spaces (with the exception of 3.8.2 above) is 8810 BTU/hr for each of an expected two (2) telecommunications closets, not including anticipated Building Automated System (BAS) equipment.

3.8.4. The estimated maximum heat dissipation of C5I-related equipment in the new Medical/Dental Facility Telecommunications closets is 17610 BTU/hr per closet, not including anticipated Building Automated System (BAS) equipment.

3.8.5. The estimated maximum heat dissipation of C5I-related equipment in the Entry Guard Shack telecommunications space is 5000 BTU/hr, not including any anticipated Building Automated System (BAS) equipment.

3.9. Electrical Design

3.9.1. Interior Electrical Systems

3.9.1.1. In telecommunications spaces, it is preferred that there are no surface-mounted conduit for electrical outlets, and that all electrical outlets be embedded in walls prior to plywood backboard installations.

3.9.1.2. In telecommunications spaces, provide a panel board in each, dedicated to serve load requirements for that space, with room for expansion. Provide one duplex outlet on each wall, or every six feet in larger spaces.

Provide a 20 Amp circuit for every two wall-mounted duplex outlets. Provide one quad outlet for each planned equipment rack location, to be attached to the top rear of each rack, not facing down and not attached to the ceiling. Provide a 20 Amp circuit for each of the rack-mounted quad outlets.

3.9.1.3. In the Communications Center, provide a quad outlet for each planned equipment rack or equipment console section/bay. Outlets shall be centered under the racks or console sections, and installed under the raised flooring. Provide a 20 Amp circuit for each of the under-floor quad outlets. Provide duplex outlets on walls per office space requirements.

3.9.1.4. Provide a multi-outlet rack mountable 20 Amp Power Distribution Unit (PDU) for each installed rack that will contain active hardware.

3.9.1.5. In the Command Center provide L5-30R outlets at each Rescue 21 operator position on a dedicated 20 Amp circuit.

3.9.1.6. Provide between 12 and 36 inches of separation between electrical outlets and telecommunications work area outlets, and install at the same height.

3.9.1.7. Install one duplex 20A outlet within 36 inches of each planned wireless access point location above the ceiling.

3.9.2. Lighting

3.9.2.1. Illumination level for telecommunications spaces shall be a minimum 50 Foot-Candles (FC) of illumination measured three feet above the finished floor with light fixtures mounted a minimum of nine feet above the finished floor.

3.9.2.2. Provide emergency battery lighting in telecommunications spaces where loss of light could present immediate personnel danger upon loss of illumination for the period when the emergency generator is not on line.

3.9.3. Emergency Power

3.9.3.1. Emergency power loads shall include lighting and receptacles in the telecommunications spaces.

Provide a dedicated emergency power panel in the Communications Center for equipment in the Communications Center.

3.9.3.2. Provide emergency power for air conditioning equipment in all telecommunications spaces.

3.9.3.3. Provide and install one APC rack-mounted 2200W uninterruptible power supply (UPS) at the base of each equipment rack with active (powered) equipment. Racks used solely for voice/data/fiber patching do not require a UPS.

3.9.4. Intrusion Detection System (IDS), Closed Circuit Television (CCTV) System, & Cable Television (CATV)

3.9.4.1. Intrusion detection system (IDS), closed circuit television (CCTV), and cable television (CATV) cabling in interior locations shall be run in conduit or pathway systems separate from telecommunications CAT6A systems. Exceptions are CAT5, CAT5e, CAT6, CAT6A, and fiber optic cabling.

NOTE: C5ISC-ISD-PSB does not specify or design intrusion detection systems (IDS), closed circuit television (CCTV) systems, or cable television (CATV) systems.

3.10. Telecommunications Space Allocation and Usage

3.10.1. Communications Center: Provide a space of with sufficient SF to allow for all missions/functions in the existing Communication Center to be duplicated within the new Multi-Mission Building Command Center. This room will contain a watch stander console equipment rack, electronics systems and components, computers, writing surfaces, and other associated furnishings for this function. This space shall be within a Controlled Access Area and shall have 10-inch minimum raised flooring. The contractor shall provide and install a console in the new Command Center location which is a duplicate to the current Command Center console. Contractor shall provide power to the console per paragraph 3.9.1.3 above. The government will install associated electronics systems into the console.

3.10.2. Communications Center Distributor/Backroom: Provide a minimum space of 400 SF with no floor dimension less than 17 feet finished. This room will locate eleven (12) telecommunications equipment server racks and all required telecommunications systems and components. This room will provide connections for building backbone cabling, a horizontal cross-connect for distribution of all horizontal data and voice cabling in the Command Center, and space for required voice, data, and communications systems equipment.

3.10.3. For any 1st floor Telecommunications Spaces in the new MULTI-MISSION Building: Provide a minimum space of 176 SF with no floor dimension less than 11 feet finished. This room will locate three (3) telecommunications equipment racks and all required telecommunications systems and components. This room will provide a cross-connect for outside plant cabling, a cross-connect for building backbone cabling, a horizontal cross-connect for distribution of all horizontal data and voice cabling on the 1st floor, and space for required voice, data, and public address equipment.

3.10.4. For any 2nd floor Telecommunications Spaces in the new MULTI-MISSION Building: Provide a minimum space of 176 SF with no floor dimension less than 11 feet finished. This room will locate at least three (3) telecommunications equipment racks and all required telecommunications systems and components. This room will provide a cross-connect for building backbone cabling, a horizontal cross-connect for distribution of all horizontal data and voice cabling on the 2nd floor, and space for required voice and data equipment.

3.10.5. For any 1st floor Telecommunications Spaces in the new Medical/Dental Building: Provide a minimum space of 176 SF with no floor dimension less than 11 feet finished. This room will locate at least four (4) telecommunications equipment racks and all required telecommunications systems and components. This room will provide a cross-connect for outside plant cabling, a cross-connect for building backbone cabling, a horizontal cross-connect for distribution of all horizontal data and voice cabling on the 1st floor, and space for required voice, data, and public address equipment.

3.10.6. For any 2nd floor Telecommunications Spaces in the new Medical/Dental Building: Provide a minimum space of 176 SF with no floor dimension less than 11 feet finished. This room will locate at least four (4) telecommunications equipment racks and all required telecommunications systems and components. This room will provide a cross-connect for building backbone cabling, a horizontal cross-connect for distribution of all horizontal data and voice cabling on the 2nd floor, and space for required voice and data equipment

3.10.7. SIPRNET Server Room: Provide a minimum space of 100 SF with no floor dimension less than 10 feet finished. This room will locate one (1) equipment rack, and associated equipment, safes, and personnel to support the secure custodial missions of the command center.

3.11. Grounding and Bonding

3.11.1. Provide a Primary Bonding Busbar (PBB) in the 1st floor telecommunications space. Provide a Secondary Bonding Busbar (SBB) in the Communications Center, Telecommunications Entrance Facility, and all additional telecommunications spaces. The PBB and SBBs shall be installed in accordance with the TIA-607 standard.

3.11.2. The PBB shall be a ¼-inch by 4-inch (nominal width) by 20-inch (minimum length) flat copper stock.

Each SBB shall be a ¼-inch by 4-inch (nominal width) by 12-inch (minimum length) flat copper stock. The PBB and each SBB shall be drilled to accept two-hole bolt-on compression lugs. The PBB and each SBB shall be isolated from its mounting hardware and any building structural metal. Provide space for four spare ground lugs on the PBB and on each SBB.

3.11.3. Bond all appropriate components (communications consoles, equipment racks, metal conduits, raceways, raceway segments, and raised panel flooring) to the ground system. Provide two-hole bolted type ground lugs for connection of each ground connector. Provide bonding between each SBB and the PBB IAW the TIA-607 standard. Total resistance from the PBB to ground shall be 25 ohms or less. Tie the PBB to the universal building ground or electrical main IAW the NFPA 70 and the TIA-607 standard. Where a single electrode consisting of a rod, pipe, or plate does not have a resistance to ground of 25 ohms or less, an additional electrode shall be installed. Attachment to a cold water pipe is an unacceptable source of ground and shall never be used.

3.11.4. Bond all SBBs to PBB using Telecommunications Bonding Backbone (TBB) sized IAW the TIA-607 standard. Bond multiple SBBs on top floor and at a minimum of every third floor in between. Where a panel board (electrical power panel) is located with the same space as a SBB, bond the alternating current equipment ground (ACEG) to the SBB. Grounding equalizers and bonding conductors shall be sized IAW the TIA-607 standard and no smaller than the Telecommunications Bonding Backbone (TBB) connecting the PBB to the SBBs.

3.11.5. Provide a signal reference grid under the raised floor in the Command Center telecommunication space.

The signal reference grid shall consist of 2-inch wide, 26 gauge, copper strips arranged in a grid on 24-inch centers with welded intersections. Connect to raised floor pedestals at six-foot intervals. Provide a #4/0 AWG bare copper cable around the perimeter of all areas where signal reference grid is installed within six feet of the perimeter wall. Bond this perimeter cable to the signal reference grid at every intersection. Bond each signal reference grid to the building perimeter ground ring with two #4/0 AWG bare copper cables connected at opposite ends of the grid.

3.12. Outside Plant (OSP) or Campus Pathways and Cabling

3.12.1. OSP Pathways

3.12.1.1. Provide all telecommunications OSP cabling, underground conduits, pathways, and access holes as required to the new facilities, piers and existing buildings. OSP pathways and cabling shall conform to the requirements of the TIA-758 standard, the NFPA 70, and the National Electrical Safety Code (NESC). All OSP conduits shall have a minimum diameter of 4 inches. All conduits shall be encased in concrete with a minimum 2500 lb/in² compressive strength and steel reinforcement where vehicular traffic is above the pathway.

3.12.1.2. Hand holes shall be properly sized, installed with removable covers at grade level, and typed for drainage provision. All conduit building penetrations shall be fire-stopped in accordance with the NFPA 70. All conduit runs, whether empty or utilized, shall have nylon pull tape installed. Pull tape shall have footage markings and a 200-pound minimum pull strength. Pull tape shall be secured at each end of the conduit.

3.12.1.3. Conduit run design shall factor in cable diameter, minimum cable bend radius, maximum cable pulling tension, and number of 90-degree bends. Conduits used in an OSP duct bank system for telecommunications cabling shall have no more than one 90-degree bend (90 degrees total) between pull points. The cabling run shall be no longer than 400 feet between pull points.

3.12.1.4. At boat or cutter moorings, provide hand hole, if one does not exist, at a common point where telecommunications cabling enters the boat or cutter moorings area.

3.12.1.5. Provide additional pathway capacity for 100% cabling growth, either by installing additional conduit, or by doubling the number of actual cables being installed and sizing the conduit to meet the increase in total cable count (both actual and potential growth).

3.12.1.6. Coordinate with telephone utilities and network service providers to provide adequate pathway for any services that will be disturbed/rerouted between any building Telecommunications Closet and the TELCO access provider street or property point of presence.

3.12.1.7. Provide two 4-inch conduits for telecommunications OSP cabling from the building 100 entrance facility, to the MULTI-MISSION building entrance facility. One 4-inch conduit shall be used for copper cabling runs, and the second 4-inch conduit shall be used for inner duct and fiber optic cable runs.

3.12.1.8. Provide two 4-inch conduits for telecommunications OSP cabling from the Medical/Dental building entrance facility to the closest manhole that allows a clear unobstructed pathway to building 100. One 4-inch conduit shall be used for copper cabling runs, and the second 4-inch conduit shall be used for inner duct and fiber optic cable.

3.12.1.9. Provide new 4” conduit pathway for communications lines to each shore tie location as required.

Provide a galvanized steel mounting stanchion for the enclosure and coordinate its location with the existing structures in the moorings area.

3.12.1.10. Provide one 4-inch conduit for telecommunications OSP cabling from building 100 entrance facility to the Gate Guard Shack. Existing pathway may be used if viable. This conduit shall be used for copper and fiber cabling runs.

3.12.2. OSP Copper Cable

3.12.2.1. Provide lightning protection/Building Entrance Terminals (BETs) at both termination points for all new copper OSP cabling to include shore-tie cable runs. Protector packs shall be loaded with 350V gas tube modules with 110 IN / 110 OUT style terminations. If non-plenum rated cabling is run for OSP, and the cabling exceeds 50 feet from the building penetration point to the termination point, then all inner-building OSP copper cabling shall be run in metallic conduit IAW the NFPA 70. Locate BETs on plywood backboard, and ground to nearest PBB, SBB, or electrical ground IAW the NFPA 70.

3.12.2.2. Provide a 50-pair, PE89/CAT3 copper cable from the building 100 entrance facility, to the new MULTI- MISSION building telecommunications entrance facility.

3.12.2.3. Provide a 50-pair, PE89/CAT5e copper cable from the building 100 to the new Medical/Dental Building entrance facility.

3.12.2.4. Provide new cabling to each shore-tie location per the Coast Guard C5I Shore Tie Cable Standards.

3.12.2.5. Provide a 25-pair, PE89/CAT3 copper cable from the building 100 entrance facility to the Gate Guard Shack.

3.12.3. OSP Fiber Optic Cable

3.12.3.1. All fiber optic cabling shall be indoor/outdoor, loose tube rated, single-mode (SM) OS2 fiber optic cable. Fiber installation shall be accomplished by establishing new pathway and utilizing blown fiber installation method. Each fiber run shall have a dedicated fiber distribution panel. Label fiber terminations on front panel covers.

3.12.3.1.1. The contractor shall install new blown fiber pathway and OSP SM fiber to each building that currently utilizes fiber in addition to the newly constructed facilities. Each building shall be provided with empty pathway to allow for future expansion.

3.12.3.2. New SM fiber will originate in building 100 for all buildings and the following final strand counts shall be provided for use in that building as follows:

Building 101: 24 Strands

New MULTI-MISSION Building: 24 Strands

FRC Building: 24 Strands

Building 110 (Shop): 12 Strand

Building 116 (Command): 12 Strand

Building 117 (Supply) 12 Strand

Building 124 (new Exchange): 6 Strand

Building 125 (new CGIS): 12 Strand Building 126 (Admin): 24 Strand New Medical/Dental Building: 24 Strand Building 127 (UPH): 12 Strand Building 128 (UPH): 12 Strand New Guard Shack Facility: 12 Strand

Terminations of both ends shall be with ceramic LC style connectors. Terminations in the all building telecommunications space shall be made to a rack mounted fiber optic panels with the possible exception being the Guard Shack which may use a wall-mounted fiber optic panel.

3.13. Building Backbone or Riser Pathways and Cabling

3.13.1. Backbone Pathways

3.13.1.1. Install all conduits in accordance with the TIA-569 standard. All conduit runs, whether empty or utilized, shall have nylon pull tape installed. Pull tape shall have footage markings and a 200-pound minimum pull strength. Pull tape shall be secured at each end of the conduit.

3.13.1.2. Conduit run design shall factor in cable diameter, minimum cable bend radius, maximum cable pulling tension, and number of 90-degree bends. Conduits used in building backbone raceway system for telecommunications cabling shall have no more than two 90-degree bend (180 degrees total) between pull points. The cabling run shall be no longer than 100 feet between pull points.

3.13.1.3. Provide two 4-inch conduits from the Multi-Mission Building 1st floor telecommunications space to the 2nd floor telecommunications space for riser cabling.

3.13.1.4. Provide two 2-inch conduits from the new MULTI-MISSION “Same Floor” telecommunications space to the underside (under raised flooring) of the Communications Center telecom equipment room. The cabling run within these conduits will be provided and installed by the Government.

3.13.1.5. Provide one 2-inch conduit from the new MULTI-MISSION building “Same Floor” telecommunications space to the underside (under raised flooring) of the SIPRNET Room. The cabling run within these conduits will be provided and installed by the Government.

3.13.1.6. Conduit ends shall be fit with an insulated bushing to eliminate sharp edges that can damage cables during installation or service.

3.13.2. Backbone Copper Cable

3.13.2.1. Provide 110-style termination blocks on plywood backboards for copper backbone cabling.

Termination blocks shall be color coded IAW the TIA-606 standard, and provided with high profile, hinged doors to accommodate colored bridging clips.

3.13.2.2. Terminate copper backbone cabling to 110-style termination blocks. Each backbone copper run shall have a dedicated termination block field.

3.13.2.3. Extend and terminate copper backbone cabling from the 110-style termination blocks to rack mounted patch panels with…