This is a Past Performance Questionnaire used by the Bureau of Engraving and Printing (BEP) to evaluate contractor performance for the Cooling Towers project/requirement.

The questionnaire requires offerors to submit references from at least three assessors who have provided relevant services within the last five years. Relevant services are defined as similar in size, scope, and complexity to BEP's cooling tower requirement. The offeror completes Section II with contract details, and the assessor(s) validate this information and complete Sections III and V. Assessors must email completed questionnaires directly to Laqulla.Williams@bep.gov no later than 12:00 PM Central Time on Friday, October 9, 2026. Section II requires information including contractor name and address, contract number, contract type, initial and final contract values, period of performance, project description, contracting role (prime or subcontractor), and termination history (convenience, default, or N/A). Section III captures assessor information including name, organization, title, phone/email, and the assessor's role in contract administration with their period of involvement. Section V contains a performance evaluation matrix assessing the contractor across Business Relations, Timeliness, Quality, and Cost categories using a six-point scale: Exceptional, Very Good, Satisfactory, Marginal, Unacceptable, and Not Applicable. The questionnaire concludes with a yes/no question regarding whether the assessor would award the contractor another contract, with space for explanation if the answer is no, and a general comments section requiring the assessor's signature and date.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PAST PERFORMANCE QUESTIONNAIRE

Instructions:

The Bureau of Engraving and Printing (BEP) requests recent past performance. Recent is defined as within the last 5 years.

Offeror shall send the questionnaire to at least three (3) Assessors for which services were provided. Services must be relevant to BEP’s requirement. Relevant is defined as similar in size, scope, and complexity to the BEP’s requirement identified in the Performance Work Statement.

Offeror shall complete Section II prior to submitting the questionnaire to Assessor(s).

The Assessor(s) shall validate/confirm Section II information and complete Sections III and

V.

The Assessor(s), NOT THE OFFEROR, shall email the completed questionnaire to the contracting office point of contact no later than the date and time indicated below.

Message to the Assessor: Your assistance is requested by the BEP to assist with establishing the performance history for the Contractor named below. Please validate/confirm Section II information, complete Sections III and V, and sign the questionnaire. Completed questionnaire shall be emailed to Laqulla.Williams@bep.gov no later than 12:00 PM Central Time (CST), Friday, October 9, 2026.

I. Solicitation Data (for the proposed effort)

Solicitation Number Project/Requirement Cooling Towers

II. Current or Historical Contract Information Assessor: The performance data submitted by the Offeror is correct or incorrect.

Name of Company Reference is for: _____________________________________________________

CONTRACTOR NAME &

ADDRESS:

Contract No

Type of Contract Initial Final

Contract Value

Period of Performance/Delivery Schedule

Project/Requirement Description

Please select from the following as it applies to this contract:

Contracting Role PRIME SUBCONTRACTOR

Termination History Convenience Default N/A

III. Assessor Information

Assessor Name

Organization

Title Phone Number/Email Address

Identify your role in the contract award or administration and the period of your involvement.

Role Period of Involvement

Procuring Contracting Officer (PCO)

Administrative Contracting Officer (ACO)

Contract Specialist

Contracting Officer’s Representative (COR)

Technical Project Lead/Project Manager

Quality Assurance Specialist

Defense Contract Audit Agency (DCAA) Auditor

Other:

IV. Evaluation Definitions

The following definitions should be used in your assessment of Contractor performance.

EXCEPTIONAL

Contractor’s performance significantly exceeded most or all contract requirements. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the Contractor were highly effective.

VERY GOOD

Performance meets contractual requirements and exceeds some to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the Contractor were effective.

SATISFACTORY

Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the Contractor appear or were satisfactory.

MARGINAL

Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the Contractor has not yet identified corrective actions. The Contractor’s proposed actions appear only marginally effective or were not fully implemented.

UNSATISFACTORY

Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problems(s) for which the Contractor’s corrective actions appear or were ineffective..

NOT APPLICABLE

(N/A)

Performance information not recent or relevant as defined in the Solicitation. Unable to provide assessment.

V. Performance Evaluation

E xc ep ti on al

V er y G oo d

S at is fa ct or y

M ar gi na l

U na cc ep ta bl e

N /A

BUSINESS RELATIONS

The referenced contractor was responsive to the customer’s needs.

The contractor’s personnel were qualified to meet the requirements.

TIMELINESS

The contractor’s ability to ensure, to the extent of its responsibility, that all tasks were completed within the requested time frame.

Time required for vendor to respond to emergencies and service requests.

Timeliness in Meeting Milestones and deliverables (if applicable)

QUALITY

What is your OVERALL assessment of the quality of the contractor’s performance? Were your specifications and expectations met by the contractor?

Quality of the finished product; please note any specific issues.

Conformance to Contract Requirements

Standards of Good Workmanship (technical, professional, environmental, safety, etc.)

COST

The contractor’s ability to accurately estimate cost.

COST/PRICE ESTIMATES—(ability to meet proposed costs and whether actual costs/rates realized reflect negotiated costs/rates)

INVOICING—accuracy and timeliness of submission

Based on this Contractor’s overall performance, would you award this Contractor another contract?

Yes________ No___________

If no, please explain:

General Comments:

Assessor’s Signature Date