Attachment 006 Operation and Maintenance Contract USDA-NCAUR, Peoria, IL
12/14/2020
001 12/31/2013
002-CLEAN-D 12/18/2008
003 5/14/2014
004 5/14/2014
005 5/14/2014
006 11/25/2014
006-A 12/31/2013
006-B 12/31/2013
007 10/9/2001
008 10/12/2001
008-REST 4/14/2016
010 10/9/2001
011 11/14/2012
12/14/2020
Task Instruction List National Center Agricultural Utilization Research
A. PULL WATER SAMPLE FROM TANK ONLINE & PERFORM HARDNESS DROP TEST
CONTACT THE OFFICE BEFORE ENTERING BUILDING 008
SAFETY NOTES:
RUBBER GLOVES AND SAFETY GLASSES
CLEANING OF RESTROOM AND SHOWER.
BEFORE CLEANING THIS RESTROOM YOU WILL HAVE TO GET PERMISSION FROM ASHLEY CRANFORD IN ORDER TO ENTER.
Instruction Code Date Last Edited
A. SEND TEST KIT OFF TO GET RE-CALIBRATED
B. SEND TO TEST GAUGE INDUSTRIES, 800 WEST CENTRAL ROAD, MT. PROSPECT, IL 60056
Instruction Code Date Last Edited
A. CHECK STEAM CONTROL VALVE PACKING FOR LEAKS
B. BLOW DOWN STRAINERS
C. LUBRICATE SEAM & OPERATE ALL VALVES ONE CYCLE
D. CHECK THERMOMETERS & GAUGES FOR DAMAGE
E. GENERATE A CM WORK ORDER AS NEEDED
Instruction Code Date Last Edited
A. CHECK UNIT FOR LEAKS & DAMAGE
B. CHECK OPERATION OF STEAM TRAPS
C. LUBRICATE STEAM & OPERATE ALL VALVES AT LEAST ONE CYCLE
TIGHTEN PACKING AS NEEDED
D. WITH SYSTEM SHUT OFF & BYPASS TO DRAIN OPEN FLUSH FOR 30 MINUTES
E. DURING FLUSH IF TEMPERATURE DROPS 8-10 DEGREES BUNDLE NEEDS TO BE CLEANED
F. GENERATE CM WORK ORDER FOR COIL CLEANING OR OTHER REPAIRS AS NEEDED
G. WIPE DOWN ENTIRE UNIT
Instruction Code Date Last Edited
REMOVE END BELLS OF THE CHILLER. USING GOODWAY MACHINE, CLEAN TUBES OF THE CHILLER. CHECK ALL TUBES AND END- BELLS FOR MECHANICAL INTEGRITY. IF NEEDED, REPLACE GASKETING MATERIAL. RE-INSTALL END BELLS. CHECK ALL PORTS
AND VALVES FOR PROPER OPERATION. START AND OPERATE CHILLER.
Instruction Code Date Last Edited CLEAN INTERIOR AND EXTERIOR OF COOLING TOWER, TOWER BASIN AND TOWER SUMP TO PREPARE FOR SUMMERTIME OPERATION.
CHECK OPERATION AND INTEGRITY OF TOWER STRUCTURE, TOWER CURTAINS, WATER BAFFLES, FILL VALVES, STRAINERS AND
MECHANICAL FILL VALVES AND DRAINS, INCLUDING SUMP PUMP.
Instruction Code Date Last Edited
Instruction Code Date Last Edited
Instruction Code Date Last Edited
Instruction Code Date Last Edited
Instruction Code Date Last Edited
Instruction Code Date Last Edited
1. KEEP ALL AISLES CLEAR OF DEBRIS.
2. KEEP SIDEWALKS AND ENTRANCE AREAS CLEAR OF SNOW AND ICE DURING WINTER SEASON.
3. KEEP ALL SAFETY CONTAINMENT AREAS CLEAR OF UNNECESSARY ITEMS. ONLY PROPER CHEMICAL ARE TO BE STORED THERE.
4. KEEP FLOORS CLEAN OF DEBRIS DAILY.
5. EMPTY GARBAGE DAILY.
6. KEEP FENCED IN YARD CLEAN OF DEBRIS.
Instruction Code Date Last Edited
Task Instruction List National Center Agricultural Utilization Research
Instruction Code Date Last Edited
012 6/30/2011
013 12/20/2011
015 10/9/2001
016 3/27/2015
12/14/2020 CHECK ALL LIGHTS TO SEE THAT THEY ARE WORKING PUSH TEST BUTTON ON LIGHT IF SO EQUIPPED.
GENERATE CM WORK ORDER FOR REPAIRS
BUILDING 001
NORTH WING
BASEMENT 20 LIGHTS
1ST FLOOR 12 LIGHTS
2ND FLOOR 22 LIGHTS
3RD FLOOR 16 LIGHTS
A. CHANGE FILTERS/CHECK COILS FOR DIRT
B. CHECK MOTOR BELT
C. LUBRICATE BEARINGS AS NEEDED
D. CHECK PIVOT ARMS, JOINTS & BOLTS FOR TIGHTNESS & WEAR
E. CHECK STEAM TRAPS FOR OPERATION, BLOW DOWN STRAINERS
F. CHECK VACUUM BREAKER
G. GENERATE CM WORK ORDER FOR ANY REPAIRS NEEDED
Instruction Code Date Last Edited
Task Instruction List National Center Agricultural Utilization Research
A. RUN FREE CHLORINE TEST ON SAMPLE TAKEN AFTER THE CARBON FILTER
B. RECORD ON PM
EQUIP# _________
FREE CHLORINE _________
EQUIP# _________
FREE CHLORINE
Instruction Code Date Last Edited
A. CHECK ALL ELECTRICAL CONNECTIONS
B. RUN BOTH SOFTNERS THROUGH COMPLETE CYCLES & CHECK ALL COMPONENTS FOR PROPER OPERATION
PAY SPECIAL ATTENTION TO THE BRINE SYSTEM
C. WIPE DOWN BOTH UNITS & BRINE TANKS
Instruction Code Date Last Edited
RECORD PPM HARDNESS ON PM SHEET
B. RECORD TANK ONLINE
C. CHECK UNIT FOR LEAKS
D. CHECK & FILL BRINE TANK WITH SALT TO REQUIRED LEVEL
E. PROPERLY DISPOSE OF TRASH. CLEAN ROOM IF NEEDED.
F. GENERATE CM WORK ORDER FOR REPAIRS AS NEEDED
HARDNESS TANK - BOILER ROOM
PPM ONLINE
PPM ONLINE
MONDAY _______ _______
TUESDAY _______ _______
WEDNESDAY _______ _______
THURSDAY _______ _______
FRIDAY _______ _______
SATURDAY _______ _______
HARDNESS TANK - NORTH WING
PPM ONLINE
MONDAY _______ _______
TUESDAY _______ _______
WEDNESDAY _______ _______
THURSDAY _______ _______
FRIDAY _______ _______
SATURDAY _______ _______
HARDNESS TANK
PPM ONLINE
MONDAY _______ _______
TUESDAY _______ _______
WEDNESDAY _______ _______
THURSDAY _______ _______
FRIDAY
017 2/17/2010
018 8/13/2012
018-CW 10/9/2012
12/14/2020
019 2/16/2010
ITEM MAKE ROOM SERIAL #
001 CONS 1106A 082911
002 CONS 1112A 090611
003 CONS 2106A 083111
004 CONS 2112A 082611
005 CONS 2118A 090211
006 CONS 3106A 090711
Instruction Code Date Last Edited
ITEM MAKE ROOM SERIAL#
001 AMSCO 3302 012499104
002 AMSCO 3302 010379202
003 AMSCO 3127 012739106
004 CONS 3106A 090711
005 AMSCO 2320 013390007
006 AMSCO 2303 012039210
007 AMSCO 2119 0112884008
008 CONS 2118A 090211
009 CONS 2112A 082611
010 CONS 2106A 083111
011 AMSCO 1328 0118291007
012 AMSCO 1113A-B 012259110
013 CONS 1112A 090611
014 CONS 1106A 082911
Instruction Code Date Last Edited
Task Instruction List National Center Agricultural Utilization Research
ATTIC 5 LIGHTS
CENTER WING
BASEMENT 9 LIGHTS
1ST FLOOR 6 LIGHTS
2ND FLOOR 6 LIGHTS
3RD FLOOR 6 LIGHTS
ATTIC 6 LIGHT
SOUTH WING
BASEMENT 7 LIGHTS
1ST FLOOR 2 LIGHTS
2ND FLOOR 2 LIGHTS
3RD FLOOR 2 LIGHTS
ATTIC 2 LIGHTS
GREENHOUSE 2 LIGHTS
ADMIN WING
BASEMENT 16 LIGHTS
1ST FLOOR 9 LIGHTS
2ND FLOOR 7 LIGHTS
3RD FLOOR 7 LIGHTS
ATTIC 5 LIGHTS
BUILDING 002 3 LIGHTS
BUILDING 003 2 LIGHTS
BUILDING 010 1 LIGHTS
NORTHWING LIGHTS CAN ONLY BE INSPECTED BY 2 PEOPLE.
ONE PERSON GOES TO ROOM 2225 AND PRESSES TEST BUTTON
WHILE OTHER WALKS THE HALWAYS TO MAKE SURE LIGHTS ARE FLASHING ON EACH CORRESPONDING
FLOOR THAT IS BEING TESTED THERE ARE TEST BUTTONS FOR EACH FLOOR IN ROOM 2225
Instruction Code Date Last Edited
A. TURN ON EXHAUST SYSTEM
B. WHEN NEW THE GUAGES WILL READ .45 .75 1.0
C. IF THEY NEED TO BE CHANGED GAUGES WILL READ .75 1.25 1.75
D. IF FILTERS NEED TO BE CHANGED
- WEAR D100 FILTRATION RESPIRATOR
- WEAR PROTECTIVE SUIT
- REMOVE & PLACE DIRTY FILTERS IN PLASTIC BAG, TAPE UP & TURN OVER TO MTX RESEARCH STAFF
E. DISCONNECT POWER & LOCKOUT
F. OPEN FAN HOUSING, CHECK BELT, CHECK SHIEVE, LUBRICATE MOTOR AS REQUIRED AND CLEAN OUT DIRT, DEBRIS & BIRD
NESTS
G. CLOSE & RECONNECT POWER SOURCE
H. GENERATE CM WORK ORDER FOR REPAIRS AS NEEDED
I. WHEN FILTERS ARE CHANGED TURN UNIT ON AND CHECK AND RECORD GAUGE PRESSURE
020 5/10/2011
021 10/9/2001
022 5/11/2011
023 5/11/2011
12/14/2020
A. CHECK EACH FLOAT TO VERIFY OPERATION OF EACH STAGE
A) ONE PUMP ON
B) TWO PUMPS ON
B. IF IN ALTERNATING MODE, CHECK TO MAKE SURE PUMPS ARE ALTERNATING
(SWITCH IS IN CONTROL PANEL)
C. CHECK ALL PIPING FOR LEAKS
D. CHECK PIT FOR DEBRIS
A. SHUT OFF UNIT
B. CLEAN CONDENSER
C. BLOW DOWN MANNUALLY
D. CHECK REFRIDGERANT
Instruction Code Date Last Edited
Task Instruction List National Center Agricultural Utilization Research
A. SHUT OFF POWER TO DOOR MECHANISM & L O C K I T O U T! !
B. REMOVE GUARDS & INSPECT ALL DRIVE MECHANISM COMPONENTS FOR PROPER ALIGNMENT, WEAR, DAMAGE, ETC.
C. TIGHTEN ALL MOUNTING BOLTS
D. VERIFY MOVING PARTS TURN FREELY
E. INSPECT DRIVE BELTS & REPLACE WORN & FRAYED BELTS
F. LUBRICATE BEARINGS, CHAINS & OTHER MOVING PARTS AS NEEDED
G. TURN ON POWER & OPERATE DOOR TO OPEN POSITION, LUBRICATE TRACK
H. REPLACE GUARDS & CHECK OPERATION OF SAFETY STRIP
I. OPERATE DOOR TO FULL CLOSED & FULL OPEN POSTIONS & VERIFY AUTOMATIC SHUT OFF POINTS ARE SATISFACTORY, IF NOT ADJUST CUT OUT CONTROLS
J. VERIFY ALL PUSH BUTTONS WORK FREELY & PROPERLY
Instruction Code Date Last Edited
A. CLEAN TRACKS & LUBRICATE ROLLERS, GEARS & CHAINS
B. TIGHTEN LOOSE BOLTS, SCREWS & HANDLES
C. CHECK CONDITION OF ROPES, CABLES & LOCKS
D. GENERATE CM WORK ORDER FOR REPAIRS AS NEEDED
Instruction Code Date Last Edited
CAR DATE HOURS ODOMETER LOF DUE
A320016 ________ ________ ________ ________
A320025 ________ ________ ________ ________
A281059 ________ ________ ________ ________
A350215 ________ ________ ________ ________
A350224 ________ ________ ________ ________
A350251 ________ ________ ________ ________
A314824 ________ ________ ________ ________
A314825 ________ ________ ________ ________
A257836 ________ ________ ________ ________
A342884 ________ ________ ________ ________
A344981 ________ ________ ________ ________
A319985 ________ ________ ________ ________
A344986 ________ ________ ________ ________
A319988 ________ ________ ________ ________
A319999 ________ ________ ________ ________
024 5/11/2011
025 10/9/2001
026 5/11/2011
027 10/9/2001
028 10/9/2001
029 1/13/2012
030 5/8/2013
031 6/18/2019
032 3/15/2002
12/14/2020
A. CLEAN DAMPER BLADES
B. LUBRICATE LINKAGE JOINTS
C. TIGHTEN SET SCREWS AS NEEDED
D. CHECK OPERATION OF ACTUATOR
1. STROKE FULL OPEN TO FULL CLOSED
2. LISTEN FOR DIAPHRAGM LEAKAGE
3. CHECK FOR HOSE WEAR & LEAKAGE
4. CHECK OUR INTENTORY OF SPARE DIAPHRAGMS & ORDER TO MAINTAIN TWO OF EACH SIZE IN STOCK
5. CHECK CONTROL PANEL TRANSDUCERS & HOSES FOR LEAKAGE
A. USE SAFETY HARNESS IN JLG
B. REMOVE PROTECTIVE WEATHER HOOD
C. CHECK FAN BLADES FOR FREE ROTATION
D. CHANGE V-BELT, A60 BELT
E. LUBRICATE BEARINGS AS REQUIRED
F. CHECK AMPERAGE DRAW ON MOTOR
G. CHECK FOR ANY LOOSE BOLTS, SCREWS, NUTS, ETC. & TIGHTEN
H. REPLACE HOOD & CLEAN UP
Instruction Code Date Last Edited
Task Instruction List National Center Agricultural Utilization Research
A. BLOW DOWN NOT WATER STRAINER
B. LUBRICATE STEMS & OPERATE VLAVES ONE FULL CYCLE,
TIGHTEN PACKING (IF NEEDED)
C. GENERATE CM WORK ORDER FOR REPAIRS AS NEEDED
D. WIPE DOWN UNIT
Instruction Code Date Last Edited
A. REPLACE FILTER ELEMENT WHEN PRESSURE DROP REACHES 10 PSI
(INDICATOR IN RED ZONE)
B. REORDER SPARE FILTER ELEMENTS FOR STOCK
C. USES REPLACEMENT ELEMENT OR-485
Instruction Code Date Last Edited
A. REMOVE LID FROM TRAP
B. REMOVE ALL DIRT, SLUDGE, MUD & DEBRIS FROM TRAP
C. CLEAN BAFFLES
D. CLEAN & CHECK LID GASKET FOR DAMAGE
E. REINSTALL LID
F. CLEAN UP AREA
Instruction Code Date Last Edited
A. OPEN & CLOSE VALVES ONE CYCLE, TIGHTEN PACKINGS, LUBRICATE STEMS
B. CLEAN OUT STRAINERS
C. CHECK OPERATION OF SYSTEM CONTROL VALVES
D. CHECK OPERATION OF STEAM TRAPS
Instruction Code Date Last Edited
A. REMOVE GRATING OR LID & CLEAN OUT SUMP PIT
B. CHECK CONDITION OF POWER CORD TO PUMP
C. ADD WATER TO SUMP PIT & VERIFY PROPER OPERATION OF PUMP & CHECK VALVE
D. REPLACE GRATING & GENERATE A CM WORK ORDER FOR REPAIRS AS NEEDED
Instruction Code Date Last Edited
A. CHECK FLOAT OPERATION
B. SHUT OFF & LOCK OUT POWER SOURCE
C. CHECK CONDITION OF WIRING
D. CHECK CONDITION OF PIT LID
E. CLEAN SUBMERSIBLE MOTOR, LID & AREA
F. GENERATE CM WORK ORDER FOR REPAIRS AS NEEDED
G. MARCH AND SEPTEMBER OPEN UP AND HOSE DOWN FLOAT SWITCHES ON SUMP PUMP 03.
NOTE: ON ANNUAL PM INCLUDE CLEANING PIT, MOTOR & PUMP OF ACCUMILATED DIRT & DEBRIS
Instruction Code Date Last Edited
E. CHECK COVER ALIGNMENT OVER PIT
Instruction Code Date Last Edited
A. PUMP DOWN PIT AS FAR AS POSSIBLE
B. CLEAN PUMPS OF SURFACE BUILD UP
C. CHECK POWER SUPPLY CORDS & SEALS FOR DAMAGE
D. CHECK CONDITION OF FLOAT SWITCH CORDS
E. SCRAPE ALL BUILD UP FROM TRENCH & PIT WALLS
F. REMOVE ALL SLUDGE FROM BOTTOM OF PIT
G. CHECK CONDITION OF COVERS, LIDS & GRATING
H. REASSEMBLE & PLACE BACK IN SERVICE
I. GENERATE A CM WORK ORDER FOR REPAIRS AS NEEDED
033 10/9/2001
034 1/17/2012
035 10/11/2001
036 10/23/2001
037 10/17/2011
038 5/21/2012
039 10/12/2011
12/14/2020
041 10/25/2001
A. CLEAN GREASE & DIRT FROM PUMPS EXCHANGES & PIPING.
B. CHECK ENTIRE UNIT FOR LEAKS OR DAMAGE.
C. LUBRICATE PUMPS & CONTROL VALVES PER MANUFACTURES RECOMMENDATIONS.
D. CYCLE ALL VALVES OFF & ON ONE CYCLE & CHECK PACKINGS FOR LEAKS.
E. BLOW DOWN BOTTOM OF AIR SEPERATOR & PUMPS SUCTION DIFFUSERS AND STRAINERS
F. CHECK STEAM TRAP FOR PROPER OPERATION.
G. GENERATE A CM WORK ORDER FOR NEEDED REPAIRS.
Instruction Code Date Last Edited
A. SHUT OFF ELEVATOR
B. SHUT OFF EXHAUST FAN
C. COVER HOLE FOR WINTER
A. COLLECT WATER SAMPLES FROM ALL CLOSED LOOP SYSTEMS FOR TESTING.
B. ASSIST WATER TREATMENT SUPPLIER WITH TESTING.
C. MAKE CORRECTIVE ADJUSTMENTS IN CHEMICAL LEVELS OF EACH CLOSED LOOP SYSTEM PER WRITTEN
RECOMMENDATION OF SUPPLIER.
D. CLOSED LOOP CHILLED WATER - SEMI-WORKS FREEZE POINT - DEGREE
E. PROPER LEVEL OF 12L IN HOT WATER CLOSED LOOPS IN 1000PPM - 1200PPM
Instruction Code Date Last Edited
Task Instruction List National Center Agricultural Utilization Research
A. CHECK GENERAL CONDITION OF COMPONENTS & INSULATION.
B. ENERGIZE & VERIFY OPERATION OF SYSTEMS.
C. VERIFY ALL CONTROLS & THERMOSTATS HAVE POWER.
D. GENERATE CM WORK ORDER FOR ANY REPAIRS REQUIRED.
E. GENERATE A PURCHASE REQUISITION FOR ANY MATERIALS NEEDED FOR REPAIRS.
Instruction Code Date Last Edited
A. CLEAN ALL DIRT & CORROSION FROM ENTIRE UNIT.
B. CLEAN & LUBRICATE CIRCULATING PUMP.
C. MANUALLY CLOSE & REOPEN MARKED (GREEN TAGGED) VALVES ONE CYCLE.
D. CHECK UNIT FOR LEAKS & ALL VALVES FOR PACKING LEAKS.
E. CLEAN ANY CORROSION FROM VALVE STEMS & LUBRICATE.
F. LIFT RELIEF VALVE SEVERAL TIMES VERIFY CLOSURE.
G. READ AND CHECK ALL GAUGES & THERMOMETERS FOR DAMAGE.
H. GENERATE A CM WORK ORDER FOR NEEDED REPAIRS
I. READ +GFT+ __________
1. PSI __________
2. TEMP __________F
3. PSI __________
4. TEMP __________F
5. PSI __________
6. TEMP __________F
7. TEMP __________F
8. PSI __________
9. PSI __________
10. PSI __________
11. PSI __________
12. PSI __________
13. PSI
Instruction Code Date Last Edited
A. PERFORM PROPER LOCK OUT/TAG OUT PROCEDURES
B. SHUT OFF MAIN VALVE AT BACKFLOW PREVENTER IN 0330
C. INSTALL TIE-WRAP ON VALVE HANDLE WITH PRECAUTION NOTE TO NOT TURN ON
D. OPEN ALL VALVES & HYDRANT LEVER ON ALL FOUR YARD HYDRANTS
E. OPEN DRAIN VALVE IN MANHOLE NEXT TO GARDEN PLOTS
Instruction Code Date Last Edited
A. CLOSE DRAIN VALVE IN MANHOLE NEXT TO GARDEN PLOT
B. PRTIALLY OPEN MAIN SUPPLY VALVE IN 0330
C. VERIFY WATER FLOW TO EACH HYDRANT TO PURGE AIR, CLOSE VALVES WHEN ALL AIR IS PURGED
D. SLOWLY OPEN MAIN VALVE COMPLETLY
Instruction Code Date Last Edited
E. CHANGE ALL FILTERS
Instruction Code Date Last Edited
A. CHECK FOR PROPER OPERATION OF POWER LOUVERS
B. CHECK FOR PROPER OPERATION OF THERMOSTAT
C. CHECK FOR PROPER OPERATION OF EXHAUST FAN DISCONNECT & CONTROL RELAYS
D. CHECK FOR FAN BELT TIGHTNESS
E. CHECK ROOF TOP DISCONNECT FOR PROPER OPERATION
F. GREASE FAN SHAFT BEARINGS
G. MAKE SURE ROOF TOP LOUVERS ARE NOT STICKING
042 10/25/2001
043 4/30/2014
044 7/1/2011
045 10/31/2001
046 11/1/2001
12/14/2020 047 4/20/2015
COMPLETE ATTACHED DAILY/WEEKLY INSPECTION REPORT DAILY
CHECK OPERTAION OF:
A. SEAT BELT
B. HOOD/SEAT LATCHES
C. HORN, GAUGES, LIGHTS & ALARMS
D. HOIST, TILT & ATTACHMENTS
E. STEERING
F. BRAKES
G. TRANSMISSION/CLUTCH
A. COORDINATE SHUT DOWN WITH LAB SUPERVISOR!
B. USE PROPER LOCK OUT/TAG OUT PROCEDURES.
C. CHECK ALL WIRING CONNECTIONS FOR PROPER TIGHTNESS.
D. CHECK FOR PROPER GROUNDING.
E. CHECK RUNNING AMPS AGAINST THE DATA PLATE.
F. CHECK BEARING END PLAY & SHEAVE.
G. CHECK ALL MOUNTING FASTNERS FOR TIGHNESS.
H. LUBRICATE MOTOR AS REQUIRED.
I. CHECK COUPLING.
J. CLEAN & WIPE DOWN ENTIRE UNIT.
Task Instruction List National Center Agricultural Utilization Research
Instruction Code Date Last Edited
A. PERFORM LOCK OUT/TAG OUT PROCEDURES
B. CHECK BELT & REPLACE AS NEEDED
C. LUBRICATE BEARINGS & MOTOR AS REQUIRED
D. CHECK ALL BELTS, SCREW & FASTNERS FOR TIGHNESS
Instruction Code Date Last Edited A. PRIOR TO STARTING WORK COORDINATE OUTAGE WITH THE APPROPIATE LABORATORY SUPERVISOR!
B. OPEN & TAG OUT CIRCUIT BREAKER OR DISCONNECT SWITCH & VERIFY BLOWER MOTOR WON'T RUN
C. INSPECT BLOWER MOTOR & FAN DRIVE ASSEMBLY, CHECK FOR:
1. BELT CONDITION, REPLACE DRIVE BELTS THAT ARE CRACKED OR FRAYED
2. FREE ROTATION OF ALL ROTATING COMPONENTS
3. SCREWS, BLOTS, NUTS, ETC. SECURELY FASTENED
4. CORROSION OR OTHER DETERIORATION
5. PROPER ALIGNMENT OF COMPONENTS
6. PAPER OR TRASH IN BLOWER ASSEMBLY OR IN "VENT PIPES"
D. LUBRICATE MOTOR, SHAFT & BEARINGS AS APPROPIATE
E. VERIFY ALL DUCT WORK IS IN GOOD PHYSICAL CONDITION, SECURELY MOUNTED & PROPERLY SUPPORTED
F. VERIFY ALL LOUVERS OPERATE, LUBRICATE HINGE & PIVOT POINTS
G. CLEAN ALL COMPONENTS
H. CHECK MOTOR STARTER FOR:
1. SIGNS OF OVERHEATING
2. LOOSE WIRE CONNECTIONS
3. DAMAGED OR LOOSE COMPONENTS
4. DAMAGED CONTACTS
5. FREE ARMATURE MOVEMENT
I. CHECK START/STOP SWITCH FOR:
1. SIGNS OF OVERHEATING
2. LOOSE WIRE CONNECTIONS
3. DMAGED OR LOOSE COMPONENTS
4. FREE MOVEMENT OF SWITCH OR PUSH BUTTONS
5. VERIFY AUTO FAN CUTOUT WITH AIR HANDLER SHUTDOWN OPERATION
Instruction Code Date Last Edited
A. SHUT OFF ELEVATOR
B. UNCOVER HOLE
C. LUBE AS REQUIRED
D. TURN ON EXHAUST FAN & CHECK OPERATION
E. TURN ELEVATOR BACK ON
Instruction Code Date Last Edited
A. CHECK FOR PROPER OPERATION OF POWER LOUVERS
B. CHECK FOR PROPER OPERATION OF THERMOSTAT
C. CHECK FOR PROPER OPERATION OF EXHAUST FAN DISCONNECT & CONTROL RELAYS
D. CHECK FOR FAN BELT TIGHTNESS
E. CHECK ROOF TOP DISCONNECT FOR PROPER OPERATION
F. GREASE FAN SHAFT BEARINGS
G. MAKE SURE ROOF TOP LOUVERS ARE NOT STICKING
H. CLEAN LOUVERS AND GRILL
Instruction Code Date Last Edited
D. TURN ELEVATOR BACK ON
048 11/2/2001
049 11/17/2016
050 11/17/2016
12/14/2020
REMEMBER SAFETY FIRST!
LOCK OUT/TAG OUT
SPRING MAINTENANCE -(WHEN STARTING AIR CONDITIONING SYSTEM)
FAN MOTOR:
A. CLEAN FAN MOTOR HOUSING & VENT OPENINGS
B. FLUSH OUT OLD GREASE IN BEARINGS BY REMOVING DRAIN PLUG & PUMPING IN FRESH LITHIUM-BASE GREASE. REPLACE DRAIN
PLUG.
C. CHECK/TIGHTEN ELECTRICAL CONNECTIONS.
D. MEGGER & RECORD INSULATION RESISTANCE (MEGGER FROM LOAD SIDE OF MAGNETIC SWITCH WITH SWITCH OPEN.)
E. INSPECT & ADJUST OR REPLACE FAN BELTS AS REQUIRED. VERIFY BELT GUARD IS FUNCTIONING PROPERLY. (IF APPLICABLE)
F. TIGHTEN PULLEY SET SCREWS IF LOOSE.
BLOWER ASSEMBLY:
A. CHECK BLOWER HOUSING & FAN ASSEMBLY FOR DIRT.
B. FLUSH OUT OLD GREASE IN BEARINGS BY REMOVING DRAIN PLUG & PUMPING IN FRESH LITHIUM-BASE
GREASE. REPLACE DRAIN PLUG.
C. ROTATE FAN & MOTOR BY HAND TO VERIFY SMOOTH FREE OPERATION.
D. TIGHTEN PULLY SCREWS IF LOOSE.
COOLING COILS:
A. CLEAN COIL SURFACE WITH A NYLON BRUSH OR LOW (30 PSI OR LESS) AIR PRESSURE OR VACUUM CLEANER.
B. CLEAN CONDENSATE DRAIN PAN & VERIFY PAN DRAIN IS NOT OBSTRUCTED.
HEATING COIL:
A. CLEAN COIL SURFACE AS DESCRIBED FOR COOLING COIL.
B. REPAIR ANY LEAKS DISCOVERED DURING THE WINTER'S OPERATION.
MAIN FRAME:
A. CHECK MAIN FRAME FOR CORROSION, LOOSE COMPONENTS & GENERAL CONDITION. CHECK PIPE INSULATION & REPAIR OR
REPLACE AS NECESSARY.
B. VERIFY LOUVERS OPERATED FREELY, ARE CLEAN, FIRMLY ATTACHED TO SHAFTS, & THAT OPERATING RODS & LINKAGE ARE FREELY ADJUSTED. LUBRICATE AS NEEDED. CLEAN INTERIOR OF UNIT WITH A VACUUM CLEANER.
CONTROLS:
A. CHECK PNEUMATIC CONTROL PANLE & CONTROL ELEMENTS FOR AIR LEAKS.
OPERATIONAL CHECKS:
A. START UNIT & VERIFY SMOOTH QUITE OPERATION
B. CHANGE THERMOSTAT SETTING & VERIFY THAT CHILLED WATER CONTROL VALVE OPENS & CLOSES PROPERLY, THAT LOUVERS
OPERATE TO SELECT OUTSIDE AIR OR INSIDE AIR AS APPROPRIATE.
C CHECK ALL TEMPERATURE GAUGES & VERIFY PROPER READINGS
A. LOCK OUT/TAG OUT
B. CHECK FAN BELT FOR TENSION & WEAR, REPLACE IF NEEDED
C. CHECK SHAFT FOR EXCESSIVE END PLAY OR UNUSUAL CONDITIONS
D. WIPE EXCESS GREASE OFF BEARINGS & UNIT
E. CHANGE FILTERS AS DICTATED BY PRESSURE DIFFERENTIAL OR NOTICEABLY DIRTY
F. CHECK CONDENSATE PAN FOR LEAKAGE & PROPER DRAINAGE
G. PLACE UNIT BACK IN OPERATION
H. CHECK ALL VALVES & CONTROL VALVES FOR PACKING LEAKS & CORROSION
I. CHECK FOR LEAKS & DAMAGE ON ALL PIPING, GAUGES, THERMOMETERS & INSULATION
J. CHECK OUTSIDE LOUVERS & BIRD SCREENS FOR CLEANLINESS
K. INSTALL ANY MISSING CONTROL COVERS, JUNCTION BOX COVERS OR ACCESS PANELS
L. GENERATE A CM WORK ORDER FOR REPAIRS AS REQUIRED
M. WIPE DOWN EXCESS DIRT FROM UNIT & SWEEP UNIT ROOM
N. CHECK MOTOR CONTROLLER (MCC OR START/STOP STAION) FOR PROPER LIGHTS. IF LIGHTS
ARE INOPERABLE OR BURNT OUT, REPLACE.
Instruction Code Date Last Edited
Task Instruction List National Center Agricultural Utilization Research
H. TIRES & WHEELS
I. CHECK FOR DAMAGE
J. CHECK HOUR METER/RECORD MONDAY MORNING
HOUR METER________________
K. CHECK FIRE EXTINGUISHER. IF O.K. ENDORSE SAFETY TAG ONCE PER MONTH.
Instruction Code Date Last Edited
A. CHECK WELDS FOR CRACKS
B. CHECK FOR BENT OR BROKEN COMPONENTS
C. FILE ANY SHARP EDGES SMOOTH
D. LUBRICATE ANCHOR BOLTS & FASTNERS AS NEEDED
E. CLEAN & PAINT RUSTED PARTS
F. CHECK CONDITION OF TOW CHAINS & WHEEL CHOCKS
051 11/2/2001
052 11/3/2001
12/14/2020
053 10/8/2012
054 10/8/2012
055 4/7/2014
12/14/2020
Task Instruction List National Center Agricultural Utilization Research
A. PUSH THE "PUSH TO TEST" BUTTON ON THE LIGHT HOUSING OR IF A NEWER MODEL PULL THE PLUG TO
ENSURE THE LIGHTS WORK.
B. INSPECT FOR ANY DAMAGE TO THE UNIT, LIGHTS, CORD, OR MOUNTING.
C. MAKE SURE THE LIGHT CAME ON!
D. GENERATE CM WORK ORDER FOR ANY REPAIRS NEEDED.
E. EMERGENCY LIGHTS ARE LOCATED AS FOLLOWS:
PRESSURE POWERED PUMP
A. OBSERVE PUMP THROUGH SEVERAL COMPLETE CYCLES FOR PROPER OPERATION.
B. CHECK SIGHT GLASS & CLEAN AS NEEDED, CHECK SIGHT GLASS PACKINGS & STOP
VALVE PACKING. (OMIT FOR CRU-NMR-01-0019)
C. CHECK FOR PROPER OPERATION OF CHECK VALVES.
D. CHECK ALL VALVE STEMS FOR LEAKAGE & CORROSION. CLEAN & LUBRICATE STEMS.
CYCLE EACH VALVE SHUT & OPEN.
E. CHECK & REPAIR DAMAGED INSULATION.
F. WIPE DOWN ENTIRE UNIT & CLEAN AREA.
Instruction Code Date Last Edited
PRESSURE POWERED PUMP
A. VALVE OUT CONDENSATE INLET, OUTELT & PUMP HEAD STEAM SUPPLY.
B. LOCK OUT/TAG OUT VALVES.
C. REMOVE POWER HEAD & CHECK CONDITION OF SPRINGS, SHAFTS, PINS, CHECK BALLS,
SEATS & FLOATS. IF REBUILD IS NEEDED REPLACE HEAD WITH SPARE POWER HEAD
& PLACE UNIT BACK IN SERVICE.
D. GENERATE CM WORK ORDER FOR REBUILDING POWER HEAD.
Instruction Code Date Last Edited
Task Instruction List National Center Agricultural Utilization Research
A. PERFORM START UP SEQUENCE.
B. CHECK ALL VALVE STEMS FOR CORROSION & LEAKS, CLEAN & LUBRICATE VALVE STEMS & TIGHTEN
PACKINGS AS NEEDED.
C. CHECK ALL PIPING THROUGH ENTIRE SYSTEM FOR LEAKS.
D. CHECK PRESSURE GAUGES & THERMOMETERS FOR DAMAGE.
E. CHECK INSULATION FOR DAMAGE.
F. SHUT DOWN SYSTEM
G. GENERATE A CM FOR REPAIRS.
H. CLEAN UP EQUIPMENT & AREA.
Instruction Code Date Last Edited
C. CHECK ALL TEMPERATURE GAUGES & VERIFY PROPER READINGS.
D. CHECK FOR & REPAIR ANY CHILLED WATER LEAKS DISCOVERED. (NOTE: CHILLED WATER CIRCULATION PUMP MUST BE ON &
CHILLED WATER CONTROL VALVES MUST BE OPEN FOR THIS CHECK.)
FALL MAINTENANCE - (WHEN STARTING STEAM HEATING SYSTEM)
HEATING COIL:
A. FLUSH CONDENSATE LINE WITH WATER.
B. CHECK COIL & PIPOMG FOR STEAM LEAKS.
MAIN FRAME:
A. PERFORM A GENERAL HOUSEKEEPING & CLEAN UP OF THE UNIT.
B. CHECK PIPE INSULATION & REPAIR OR REPLACE AS REQUIRED.
OPERATIONAL CHECKS:
A. CHECK OPERATION OF STEAM VALVE IN RESPONSE TO THERMOSTAT POSITION CHANGES.
B. CHECK OPERATION OF LOUVERS FOR SELECTION OF INSIDE OR OUTSIDE AIR.
C. CHECK ALL TEMPERATURE GAUGES FOR PROPER READINGS.
Instruction Code Date Last Edited
A. VISUALLY INSPECT FOR:
1. APPEARENCE
2. EXTERNAL DAMAGE
3. LEAKAGE
4. SECURE MOUNTING
B. TURN WATER ON & VERIFY:
1. WATER DRAINS PROPERLY
C. REMOVE COVER & INSPECT THE REFRIGERATION, PLUMBING & ELECTRICAL SYSTEMS FOR VISABLE DEFECTS
D. CLEAN THE CONDENSER COIL
E. VERIFY THAT THE UNIT RUNS PROPERLY & CYCLES OFF PROPERLY
F. REPLACE COVER ON THE UNIT & INSPECT THE AREA FOR ANY MESSES
056 2/14/2012
057 11/21/2012
058 6/20/2003
12/14/2020
Task Instruction List National Center Agricultural Utilization Research
INSPECTION OF OUTSIDE BUILDING LIGHTS FOR WALKWAYS & PARKING LOTS
A. AFTER DARK, WALK TO ALL DOOR ENTRANCES & VERIFY ALL OUTSIDE LIGHTS OPERATE PROPERLY.
NOTE ON CHECKLIST THOSE THAT DO NOT OPERATE.
B. CHECK WALK LIGHTS ON SIDE & IN FRONT OF BUILDING FOR PROPER OPERATION.
1. BUILDING 001
2. BUILDING 002
3. BUILDING 003
A. DISCONNECT ELECTRICAL PLUG & VERIFY EMERGENCY LIGHTS ILLUMINATE.
B. INSPECT CORD FOR DAMAGE.
C. LEAVE UNPLUGGED FOR 90 MINUTES
D. REPLACE ANY BATTERIES OF UNITS THAT GO DIM WITHIN 90 MINUTES
E. PLUG POWER CORD BACK IN & VERIFY LIGHTS GO ON & CHARGING INDICATOR LAMP COMES ON. SOME UNITS
WILL ALSO SHOW HIGH CHARGING RATE AT THIS TIME.
F. GENERATE A CM WORK ORDER FOR REPAIRS.
Instruction Code Date Last Edited
FUME HOOD TESTING
A. USE TESTING EQUIPMENT.
B. CHECK & VERIFY LIGHTS & HOOD FLOW IS WORKING PROPERLY ON ALL FUME HOODS LISTED ON
THE ATTACHED SHEETS. CHECK DRY ICE TEST & SMOKE TEST.
C. RECORD INTAKE & DATE INSPECTED ON STICKER ON HOOD.
HEAVY WORK GLOVES ONLY REQUIRED WHEN HANDLING DRY ICE.
NEED COMPARISION OF PRE BULB TO NEW BULB RATINGS.
Instruction Code Date Last Edited
NORTH WING:
MEN'S RESTROOM/SHOWER BASEMENT - X2
0214 - X3 0216 - X3 2218 - X2 2220 - X2 3232 - X1 3233 - X1 3236 - X1
3244 - X1 - DISCONNECTED AT PANEL - NOTE ON WALL
SOUTH WING:
0301 - X1 0309 - X1 0315 - X1 0329 - X1
GREENHOUSE - X2
BOILERHOUSE:
GROUND LEVEL - X11
BASEMENT - X1
ADMIN:
0042 - X1
NMR - X5
0019C - X1
HALL OUTSIDE NMR - X2
CAFETERIA - X1
BASEMENT SOUTH ADMIN STAIRWELL X1
3RD FLOOR SOUTH ADMIN. - X1
3RD FLOOR CENTER ADMIN. - X1
3056 - X1
AUDITORIUM - X2
3049 - X1
OUTSIDE 3049 - X1
SEMI-WORKS:
X6
BUILDING 10:
BUILDING 10B - X1
TUNNEL:
X4
059 11/6/2001
060 11/6/2001
061 11/6/2001
062 11/6/2001
063 11/6/2001
064 11/6/2001
12/14/2020
065 2/24/2004
A. OBSERVE UNIT IN OPERATION & VERIFY IT IS COOLING PROPERLY & OPERATING SATISFACTORILY
B. SHUT OFF UNIT & INSPECT AIR FILTER, CLEAN IF REQUIRED
C. VERIFY CONDENSATE IS DRAINING PROPERLY
D. RESTART UNIT & VERIFY THERMOSTAT FUNCTIONS PROPERLY
E. VISUALLY CHECK PHYSICAL CONDITION OF UNIT & CONDITION OF AIR SEAL AROUND UNIT
F. LUBRICATE UNIT AS REQUIRED
Instruction Code Date Last Edited
A. PERFORM PROPER LOCK OUT/TAG OUT PROCEDURES
B. CHANGE AIR FILTERS
C. CHECK FAN BELT FOR WEAR & TENSION
D. CHECK FAN SHAFT FOR EXCESSIVE END PLAY OR UNUSUAL CONDITIONS
E. LUBRICATE FAN SHAFT BEARINGS & MOTOR AS REQUIRED
F. WIPE OFF ALL EXCESS GREASE & OIL
G. CHECK CONDITION OF FREEZE STAT & CAP TUBE
H. CHECK ALL VALVES STEMS, TAPS, CONTROL VALVES, STRAINERS & PIPING FOR LEAKS & CORROSION I. CLEAN VALVE STEMS, LUBRICATE & CYCLE SHUT & OPEN SEVERAL TIMES TO INSURE PROPER OPERATION J. CHECK CONDITION OF INSULATION. REINSTALL ALL ACCESS PANELS, JUNCTION BOX COVERS & CONTROL
COVERS.
K. CLEAN OUTSIDE BIB SCREENS & LOUVERS
L. PLACE UNIT BACK IN SERVICE & GENERATE CM WORK ORDER FOR REPAIRS
Instruction Code Date Last Edited
Task Instruction List National Center Agricultural Utilization Research
INSPECTION OF SUFACE DRAINAGE SYSTEMS
A. INSPECT STORM SEWER DRAINS IN ROADS & CURBS & VERIFY:
1. DRAINS ARE FREE OF SURFACE TRASH & DEBRIS THAT WOULD HAMPER DRAINAGE
2. DRAIN COVERS ARE INTACT & SAFE
B. GENERATE CM WORK ORDER FOR REPAIRS
Instruction Code Date Last Edited
INSPECTION OF FENCE, POSTS & GATES
A. WALK THE PERIMETER OF THE PROPERTY MARKED BY FENCES & NOTE THE FOLLOWING:
1. GENERAL CONDITION OF FNECE AS TO CORROSION & PHYSICAL DAMAGE
2. NOTE AREAS WHERE UNAUTHORIZED ENTRY COULD BE MADE THROUGH GAPS OR HOLES UNDER THE FENCE
3. VERIFY UNUSED GATES ARE SECURELY LOCKED
4. NOTE AREAS WHERE VEGETATION IS GROWING THAT COULD DAMAGE FENCE
5. IN AREAS VISIBLE TO PUBLIC VERIFY GRASS IS PROPERLY TRIMMED
6. REMOVE TRASH & DEBRIS FROM ALL FENCE LOCATIONS
7. ON FENCES WITH BARBED WIRE VERIFY WIRE IS SECURELY FASTENED TO PROPER SUPPORTS
B. GENERATE CM WORK ORDER FOR REPAIRS
Instruction Code Date Last Edited
INSPECTION OF ROADS & PARKING LOTS
A. INSPECT ROAD FOR:
1. POT HOLES & SURFACE CONDITION
2. DAMAGES CURBS
3. TRASH/DEBRIS ACCUMULATION
4. ADEQECY OF TRAFFIC MARKINGS
5. OTHER HAZARDS TO TRAFFIC OR PARKED VEHICLES
B. INSPECT PARKING AREA FOR:
1. POT HOLES & SURFACE CONDITIONS
2. PARKING SPACE MARKING LINES
3. TRASH/DEBRIS ACCUMULATION
4. HAZARDS TO PARKED VEHICLES
C. GENERATE CM WORK ORDER FOR REPAIRS
Instruction Code Date Last Edited
INSPECTION OF FACILITY GROUNDS
A. INSPECT ALL LAWN AREAS & CHECK FOR:
1. CONDITION OF GRASS (COLOR, HEIGHT, BARE SPOTS, ETC.)
2. SIGNS OF INSPECTS, WEEDS OR DISEASE PROBLEMS
3. CONDITION OF EDGES AROUND CURBS, SIDEWALKS, DRIVEWAYS, FENCES, ETC.
4. LEAVES, LIMBS, PAPER & OTHER DEBRIS
B. INSPECT, CULTIVATE & TRIM AS NEEDED SHRUBS & SHRUB BEDS
C. INSPECT ALL TREES FOR PROPER FOLIAGE & DEAD LIMBS
D. INSPECT ALL SIDEWALKS FOR DAMAGE AND/OR TRIP HAZARDS
(IF TRIP HAZARDS ARE FOUND PUT WARNING MARKERS OUT)
E. GENERATE CM WORK ORDER FOR REPAIRS
Instruction Code Date Last Edited
4. BUILDING 005
5. BUILDING 010
6. BUILDING 011
7. COOLING TOWERS
066 8/30/2004
067 8/8/2011
12/14/2020
QUARTERLY PM OF WATER SOURCE HEAT PUMP OR EVAPORATION UNIT
A. SHUT DOWN ELECTRICAL SOURCE & LOCK OUT
B. INSPECT CONDENSATE DRAIN PAN FOR PROPER DRAINAGE
IF EVIDENCE OF STANDING WATER OR CONDENSATE OVERFLOW EXISTS GENERATE CM WORK ORDER FOR
CORRECTIVE MEASURES
C. CHECK FOR MOLD GROWTH IN DRAIN PAN
IF EVIDENCE IS FOUND OF MICROBIAL (MOLD) GROWTH, CLEAN ALL SURFACES PER STEP 1-8 BEFORE
GOING ON TO THE NEXT UNIT
D. GENERATE A CM WORK ORDER AFTER CLEANING TO RECORD ADDITIONAL LABOR HOURS
STEP #1
DISCONNECT ALL ELECTRICAL POWER TO THE UNIT
STEP #2
DON THE APPROPIATE PERSONAL PROTECTIVE EQUIPMENT (PPE)
STEP #3
REMOVE ALL STANDING WATER
STEP #4
USE A SCRAPER OR OTHER TOOLS TO REMOVE ANY SOLID MATTER. REMOVE SOLID MATTER WITH A VACUUM DEVICE THAT UTILIZES HIGH EFFICIENCY PARTICULATE ARRESTANCE (HEPA) FILTERS WITH A MINIMUM
EFFICIENCY OF 99.97% AT 0.3 MICRON PARTICLE SIZE
STEP #5
THROUGHLY CLEAN THE CONTAMINATED AREA(S) WITH A MILD BLEACH & WATER SOLUTION OR AN EPA-APPROVED
A. USE TEST EQUIPMENT, BUCKET, SHOWER CURTAIN & MOP
B. NOTE MISSING EYEWASH CUPS & ANY CUPS NOT REMOVED BY PRESSURE
C. NOTE WATER STREAM OF 12" OF LESS FROM NOZZLES & NOT MEETING AT APEX
D. ON UNITS WITH TEMPERING VALVES, RUN WATER WHILE TURNING TEMPERING VALVE CONTROL
HANDLE SEVERAL TIMES THROUGH FULL RANGE. RUN WATER FOR 2 MINUTES OR LONGER
DEPENDING ON DISTANCE OR DISCHARGE FROM TEMPERING VALVE. CHECK TEMPERATURE OF DISCHARGE WATER AT GAUGE ON TEMPERING VALVE AND VERIFY AGAINST TEMPERATURE AT EYEWASH OR SHOWER TAKEN WITH A DIGITAL THERMOMETER
(TEMPERATURE SHOULD NOT EXCEED 90 DEGREES F.) 80 TO 90 DEGREES PREFERRED
E. CHECK FOR DRIPS, WATER ON FLOOR, ETC. MAKE ADJUSTMENTS AS NECESSARY.
F. WIPE OFF EYEWASH SPIGOTS & CUPS.
G. INITIAL AND DATE INSPECTION TAG.
H. IF TEST FAILED FOR ANY REASON TAG UNIT OUT OF SERVICE AND NOTIFY LAB PERSONNEL, MAINTENANCE SUPERVISOR &
NCAUR SAFETY.
I. GENERATE CM WORK ORDER FOR REPAIRS AS A PRIORITY 1.
J. WHILE TESTING OUT BUILDINGS, VERIFY PROPER OPERATION OF ALARMS AND EXTERNAL BLDG PHONES.
K. FILL OUT A DEFICIENCY REPORT EACH MONTH IN THE BOOK LOCATED IN THE MAINTENANCE OFFICE. IF THERE ARE NO
DEFICIENCIES, STATE SO IN THE REPORT FOR THE MONTH.
Instruction Code Date Last Edited
Task Instruction List National Center Agricultural Utilization Research
SPRING MAINTENANCE (PRIOR TO START UP)
A. REMOVE ANY PLASTIC OR CLOTH COVERS & STORE THEM FOR FUTURE USE
B. UNPLUG ELECTRICAL CORD FOR SAFETY
C. VISUALLY CHECK UNIT FOR:
1. SECURE MOUNTING
2. CONDITION OF ELECTRICAL CORD
3. PHYSICAL APPEARENCE
4. TIGHT AIRSEAL AROUND UNIT
5. MISSING HARDWARE
6. CLEANLINESS OF DRIP PAN
D. INSPECT AIR FILTER & CLAEN IF REQUIRED
E. INSPECT EVAPORATOR COIL FINS FOR DAMAGE & CLEANLINESS, CORRECT ANY DISCREPANCIES F. VERIFY EVAPORATOR & CONDENSER FANS ROTATE FREELY, LUBRICATE FAN MOTOR BEARINGS IF APPLICABLE
G. VERIFY CONDENSATE DRAIN LINE IS UNOBSTRUCTED
H. PLUG IN POWER CORD & TURN ON FAN ONLY-VERIFY QUIET OPERATION & NORMAL AIR FLOW
I. TURN CONTROLS TO COOLING & VERIFY COMPRESSOR STARTS & UNIT BEGINS TO COOL
J. VERIFY PROPER OPERATION AT ALL CONTROL PANELS
K. MEASURE CURRENT USING CLAMP-ON AMPERE METER, COMPARE WITH NAME PLATE DATA
L. VERIFY THERMOSTAT IS FUNCTIONING PROPERLY
M. SET CONTROLS FOR NORMAL OPERATION & SHUT OFF UNIT
FALL MAINTENANCE (WHEN SECURING UNIT FOR WINTER)
A. OPERATE UNIT TO VERIFY IT IS OPERATIONAL
B. SHUT OFF UNIT & UNPLUG IT
C. CLEAN EVAPORATOR COIL AS REQUIRED
D. VISUALLY INSPECT UNIT FOR:
1. CONDITION OF POWER CORD
2. TIGHT AIR SEAL AROUND UNIT
3. MISSING HARDWARE
4. GENERAL PHYSICAL CONDITION
5 INSTALL WINTERIZING COVERS IF PROVIDED
068 8/4/2014
069 7/26/2011
070 10/17/2014
071 11/8/2001
072 11/8/2001
12/14/2020
073 11/8/2001
DAILY INSPECTION OF BOILERS
A. VISUALLY INSPECT ALL BOILERS FOR LEAKS
B. VISUALLY INSPECT ALL BOILERS FOR FIRE HAZARDS & REMOVE COMBUSTABEL HAZARDS FROM AREA
C. VERIFY PROPER WATER LEVEL ON ALL BOILERS
D. VERIFY PROPER STEAM PRESSURE ON ALL ON-LINE BOILERS
E. VISUALLY CHECK FLAME COLOR, STABILITY, & SHAPE ON ALL ON-LINE BOILERS
F. BLOWDOWN BOILER WATER COLUMNS (4) WHILE HOLDING LOW WATER TRIP CUT OUT BYPASS BUTTON ON
ALL ON-LINE BOILERS
G. BLOWDOWN BOILER MUD DRUM GIVE THREE TEN SECOND BLOWS ON ALL ON-LINE BOILERS
H. BLOWDOWN BOILER CONTINUOUS BLOWDOWN STRAINER ON ALL ON-LINE BOILERS
MONDAY _____
TUESDAY _____
WEDNESDAY _____
THURSDAY _____
FRIDAY _____
SATURDAY
Instruction Code Date Last Edited
WEEKLY INSPECTION OF BOILERS
A. CAREFULLY INSPECT EXTERIOR FOR SIGNS OF LEAKS
A. SHUT DOWN POWER SOURCE
B. CLEAN FAN & COILS
C. LUBRICATE FAN & MOTOR AS REQUIRED
D. CHANGE OR CLEAN FILTER ELEMENT
1. HOT WATER, CHILLED WATER OF STEAM TYPE
A. CHECK ALL PIPING FOR LEAKS
B. CHECK OPERATION OF CONTROL VALVES, TRAPS & MANUAL VALVES
C. CHECK CONDITION OF INSULATION
D. CHECK COILS FOR SIGNS OF LEAKAGE
2. ELECTRIC HEAT ELEMENT TYPE
A. CHECK CONDITION OF ELEMENT & CERAMIC CONNECTIONS
B. CHECK OPERATION OF ELEMENTS
C. CHECK FOR PROPER AMPERAGE DRAW PER OWNERS MANUAL
E. CHECK GENERAL CONDITION OF A CABINET & WIPE DOWN ENTIRE UNIT
Instruction Code Date Last Edited
Task Instruction List National Center Agricultural Utilization Research
A. INSPECT UNIT FOR LOOSE COMPONENTS, CORROSION, ETC.
B. CHECK ELECTRICAL CONNECTIONS FOR TIGHTNESS
C. CLEAN DRAINS
D. CHANGE THE REFRIDGERANT DRIER CORE AS REQUIRED
Instruction Code Date Last Edited
WEEKLY INSPECTION OF LIGHTS AND EMERGENCY LIGHT
1. IF THE LIGHT IS NOT OPERATIONAL CHANGE THE BULB (EMERGENCY BULB IN HALLWAY)
2. IF EMERGENCY LIGHT(S) IS STILL NOT OPERATIONAL CONTACT YOUR SUPERVISOR FOR A WO
3. INSPECT LIGHTS FOR ANY THAT MAY BE OUT (CM/ETC.)
(SOUTH WING ONLY)
1. CHECK OPERATION OF OXYGEN ALARM DIALER
2. VERIFY WITH OFFICE THAT ONLY A TEST
Instruction Code Date Last Edited
SANITIZER SPECIFICALLY DESIGNED FOR HVAC USE. CAREFULLY FOLLOW THE SANITIZER MANUFACTURE'S
INSTRUCTIONS REGARDING THE USE OF THE PRODUCT
STEP #6
IMMEDIATLY RINSE THE DRAIN PAN THROUGHLY WITH FRESH WATER TO PREVENT POTENTIAL CORROSIONS
FROM THE CLEANING SOLUTION OF THE PAN & DRAIN LINE COMPONENTS
STEP #7
ALLOW THE UNIT TO DRY THROUGHLY BEFORE PUTTING THE SYSTEM BACK INTO SERVICE
STEP #8
DETERMINE & CORRECT THE CAUSE OF THE MICROBIAL (MOLD) CONTAMINATION
Instruction Code Date Last Edited
A. CHECK & RECORD ROOM TEMPERATURE
B. CHECK REFRIGERANT SIGHT GLASS FOR COLOR & BUBBLES
C. CHECK UNIT FOR UNUSUAL NOISES, VIBRATIONS, ETC.
D. CHECK EVAPORATOR SECTION FOR EXCESSIVE ICE BUILD UP & PROPER DEFROSTING
E. CHECK EVAPORATOR SECTION FOR UNUSUAL NOISES, VIBRATIONS, ETC.
F. CHECK DRAINS FOR PROPER OPERATION & HEAT TRACING FOR PROPER OPERATION
G. CHECK CONDENSOR FOR CLEANLYNESS
074 11/8/2001
075 7/21/2011
076 11/8/2001
077 11/8/2001
078 11/8/2001
12/14/2020
079 11/8/2001
080 11/8/2001
081 11/8/2001 A. CHECK PUMP PERFORMANCE CURVE & AMP DRAW, AN ABNORMAL READING COULD MEAN DIRT OR BUILD UP
IMPELLERS, OR CLOGGED SUCTION & DISCHARGE LINES, CLEAN AS REQUIRED
A. FLUSH TANK DRAINS, EQUALIZING LINE & STRAINERS
B. CHECK INCOMING MAKE-UP STRAINERS FOR SCALE BUILD UP
Instruction Code Date Last Edited A. VERIFY PROPER LOW WATER CUT OFF & ALARM OPERATION. IF POSSIBLE THE DEAERATOR WATER LEVEL
SHOULD BE LOWERED TO DO THIS CONTROL CHECK
B. RAISE THE SAFETY RELIEF VALVE LEVER FOR A FEW SECONDS. THIS KEEPS THE VALVE CLEAN & FREE OF
SEDIMENT & SCALE
C. CHECK MAGNESIUM ANODE FOR LEAKAGE, REPLACE IF NEEDED
D. OPERATE ALL VALVES ONCE TO KEEP CLEAN & FREE OF BUILD UP, CHECK PACKINGS
Instruction Code Date Last Edited
Task Instruction List National Center Agricultural Utilization Research
A. KEEP DEAERATOR AREA CLEAN & FREE OF DEBRIS & CLUTTER
B. INSPECT DEAERATOR, VALVES & PIPING FOR LEAKS
C. CHECK PUMPS, MOTORS & STEAM REGULATOR FOR ABNORMAL CONDITIONS
D. MONITOR SEQUENCE OF OPERATION
E. CHECK PRESSURE, TEMPERATURE & WATER LEVEL CONDITIONS
Instruction Code Date Last Edited
MONTHLY WATER CHEMISTRY FOR CLOSED LOOP
A. PERFORM WATER ANALYSIS ON ALL CLOSED LOOP SYSTEMS FOR ADHERENCE TO RANGE PARAMETERS SET BY
WATER TREATMENT CONSULTANT
B. LOG RESULTS ON YEARLY LOG SHEET
C. RETEST AS NEEDED TO BRING SYSTEMS INTO PARAMETERS
CLOSED LOOP SYSTEMS
A. CHILLED WATER LOOP
B. PROCESS CHILLED WATER LOOP
C. HYDRONIC HEATING LOOPS SOUTH WING
D. HYDRONIC HEATING LOOPS NORTH WING (2)
E. GREENHOUSE FIN TUBE SYSTEM
Instruction Code Date Last Edited
ANNUAL TEAR DOWN & INSPECTION OF BOILERS
A. PERFORM TEAR DOWN & INSPECTION PER ATTACHED INSTRUCTIONS
B. ATTACH COPY OF FIRE MARSHALS INSPECTION TO COMPLETED PM
C. GENERATE A CM WORK ORDER FOR ANY REPAIRS OR CORRECTIONS
D. ATTACH COMPLETED INSPECTION FORM TO COMPLETED PM SHEET
Instruction Code Date Last Edited
DAILY WATER CHEMISTRY TESTING FOR BOILERS
A. PERFORM WATER ANALYSIS ON BOILER WATER, MAKE UP WATER, FEED WATER & CONDENSATE FOR
ADHERENCE TO RANGE PARAMETERS SET BY WATER TREATMENT CONSULTANT
B. LOG ON MONTHLY TESTING LOG SHEET
C. ONCE A WEEK CHECK CHEMICAL LEVELS ON WET STORED BOILERS
MONDAY ______
TUESDAY ______
WEDNESDAY ______
THURSDAY ______
FRIDAY ______
SATURDAY
Instruction Code Date Last Edited
DAILY WATER CHEMISTRY TESTING FOR COOLING TOWERS
A. PERFORM WATER ANALYSIS ON CONDENSER WATER FOR ADHERENCE TO RANGE PARAMETERS
SET BY WATER TREATMENT CONSULTANT
B. LOG ON MONTHLY TESTING LOG SHEET
MONDAY _______
WEDNESDAY _______
SATURDAY
Instruction Code Date Last Edited
WITH FIRE UNDER BOILER
A. CHECK FLAME FOR PROPER COLOR
B. DRAIN WATER FROM FLOAT SWITCH. DRAIN & VERIFY FLAME GOES OUT FROM LOW WATER LEVEL SIGNAL
C. VERIFY FIRE REIGNITES WHEN VALVE IS CLOSED & WATER LEVEL RISES
D. VERIFY ALARM CALL OUT TO SECURITY
E. VERIFY PROPER WATER LEVEL IN SIGHT GLASS
F. OBSERVE UNIT THROUGH 1 OPERATING (ON-OFF) CYCLE & VERIFY PROPER OPERATION & TIMING SEQUENCES
G. VERIFY FLAME GOES OUT BY REMOVING FIREYE, VERIFY ALARM CALL OUT TO SECURITY
082 5/20/2009
083 11/9/2001
084 7/26/2011
085 7/16/2008
086 11/9/2001
087 11/9/2001
12/14/2020
088 11/9/2001
089 11/9/2001
BOILERHOUSE SUMP PUMPS
A. CHECK OPERATION OF CONTROL FLOATS FOR PROPER SEQUENCE & ALARMS (LOCAL & DIAL OUT)
B. CHECK PIPING FOR LEAKS
C. CHECK FOR BURNT OUT INDICATOR LAMPS
D. CHECK OPERATION OF BACK UP PUMPS
Instruction Code Date Last Edited
TUNNEL SUMP PUMPS
A. SWEEP & HOSE DOWN ENTIRE TUNNEL FLOOR
B. PULL GRATING & CHECK OPERATION OF EACH SUMP PUMP & CHECK VALVE
C. CHECK CONDITION OF POWER CORDS
Task Instruction List National Center Agricultural Utilization Research
BOILERHOUSE SUMP PUMPS
A. CHECK CONDITION OF PUMP CONTROL PANEL
B. TIGHTEN ELECTRICAL CONNECTIONS
C. CHECK AMP DRAW OF EACH PUMP
D. LOCK OUT BOILER BLOW DOWN SOURCES
E. PUMP DOWN PIT
F. REMOVE PUMPS FROM PIT
G. CHECK CONDITION OF FLOAT SWITCH CORDS & BRACKET
H. CHECK CONDITION OF PUMP POWER CORDS, SEALS, HOUSING & IMPELLER ACCORDING TO OWNERS MANUAL
GUIDELINES
I. CLEAN PIT OF ALL SCALE BUILD UP, MUD & DEBRIS (USE CONFINED SPACE PROCEDURES)
J. REINSTALL PUMPS, PRIME & TEST FOR OPERATION
K. CHECK OPERATION OF BACK-UP PNUEMATIC PUMP & LUBRICATE AS REQUIRED
L. GENERATE A CM WORK ORDER AS REQUIRED FOR REPAIRS
M. CLEAN UP AREA
Instruction Code Date Last Edited
CHEMICAL FEED PUMPS
A. CHECK UNIT FOR PIPE/TUBING CONNECTION LEAKS THROUGHOUT WHOLE SYSTEM
B. THROUGHLY CLEAN ALL PUMP SURFACES, BARRELS & CONTAINEMNT AREA OF CHEMICAL SPILLS & DIRT
C. GENERATE A CM WORK ORDER FOR LEAK REPAIRS
Instruction Code Date Last Edited
A. CALIBRATE CONDUCTIVITY METER
1. CHECK METER FOR CONDUCTIVITY WITH 4000 SOLUTION
B. CALIBRATE PH METER
1. CHECK PM LEVEL WITH NO.4 & 7 PH SOLUTION
C. CALIBRATION OF SAFE-T-MATE GAS MONITOR
1. TASK TO BE PERFORMED ONLY BY INDIVIDUAL PROPERLY TRAINED IN CALIBRATION OF UNIT
2. CALIBRATE AT INTERVALS SUGGESTED IN OWNERS MANUAL
Instruction Code Date Last Edited
FUEL OIL TANKS
A. READ OIL VOLUME LEVELS AT VEEDER ROOT MONITOR STATION
B. RECORD READINGS IN BOILER LOG BOOK
C. DURING HIGH USAGE PERIODS USE STICK GAUGE TO VERIFY LEVELS
D. ADD OIL STABILIZER AS NEEDED
E. ORDER OIL TO MAINTAIN A MINIMUM OF 25% CAPACITY
Instruction Code Date Last Edited
MAKE UP/FEEDWATER PUMPS
A. CHECK PSI AT D/A M/U GAUGE FOR 40 PSI WITH PUMP IN OPERATION
B. BLOW STRAINERS AT PUMPS
C. GREASE ZERTS
D. CHECK AMP CURVE WITH PUMP RUNNING
E. CHECK FOR LEAKS
F. MANUALLY ALTERNATE PUMPS TO CHECK OPERATION OR SWITCH
G. CLEAN PUMPS & AREA
Instruction Code Date Last Edited
B. INSPECT STEAM REGULATOR, PILOTS & TUBING FOR DIRT & DEBRIS, CLEAN AS REQUIRED
C. CLEAN SIGHT GLASSES & REPLACE WASHERS AS NEEDED
D. WIPE DOWN & CLEAN ENTIRE UNIT
Instruction Code Date Last Edited
GIVE GOV'T 2 WEEK NOTICE BEFORE WORK TO BE ACCOMPLISHED!!!!!!!!
A. CLEAN TANK INTERIOR THROUGHLY, REMOVE HAND HOLES, MAN HOLE & FLUSH SEDIMENT FORM TANK WALLS
INSPECT HEATER & SCRUBBER SURFACES FOR SCALE & CORROSION
B. INSPECT STEAM REGULATOR & PILOTS. CHECK FOR DIRTY OR PLUGGED AIR & CONTROL TUBING TO PILOTS, VALVES & CONTROLS. CLEAN AS REQUIRED
C. CHECK ALL INTERANL RODS, PROBES, ANODES, SURGE SHIELDS & BAFFLES FOR CORROSION. REPLACE AS
SOON AS POSSIBLE IF NEEDED
090 7/26/2011
091 9/19/2014
092 11/10/2001
12/14/2020
093 7/15/2011
094 11/10/2001
095 2/25/2013
A. EXERCISE CARE IN WORKING OVER LAB EQUIPMENT & CHEMICALS
B. USE STEP LADDER
C. CLEAN UP ANY FALLEN DEBRIS FROM CHANGING FILTER
D. CLEAN WALLS OF DIRT AND HAND PRINTS, ESPECIALLY TO THE SIDES OF THE FILTERS
E. DOCUMENT ROOMS WHERE FILTERS ARE CHANGED. DOCUMENT ROOMS WHERE FILTERS
NEED CHANGED, BUT OCCUPANTS DID NOT WANT THEM CHANGED. DOCUMENT ROOMS WHERE
PRV STATIONS
A. CHECK INLET, OUTLET, BYPASS VALVES FOR LEAKS & CORROSION
B. CLEAN VALVE STEMS OF ANY CORROSION & LUBRICATE STEM & THREADS
C. OPERATE VALVE THROUGH COMPLETE OPEN/CLOSE CYCLE UNITL OPERATING SMOOTHLY
D. TIGHTEN PACKINGS AS NEEDED
E. CLEAN PILOT, CONTROL LINES ON PRV AND CHECK AND CLEAN ORFICE
ON FITTINGS AND CHECK TUBING FOR BLOCKAGE
F. BLOW DOWN STRAINERS - CHECK TRAPS - CLEAN UNIT AND AREA
Instruction Code Date Last Edited TESTS ARE TO BE PERFORMED IN ACCORDANCE WITH APPLICABLE NFPA CODES & MANUFACTURER'S
RECOMMENDATIONS
Instruction Code Date Last Edited
Task Instruction List National Center Agricultural Utilization Research
HYDRONIC HEATING PUMPS
A. CHECK PUMP SEALS FOR LEAKAGE
B. LUBRICATE BEARINGS AS NEEDED
C. OPERATE VALVES, CHECK PACKING
D. FLUSH STRAINERS
E. CLEAN AREA
Instruction Code Date Last Edited
MONTHLY:
A. TRIP MANUAL SWITCH FROM REMOTE TO RUN GENERATOR
B. RUN UNIT FOR AT LEAST 15 MINUTES TO VERIFY OPERATION
VOLTAGE OUTPUT__________VOLTS
FREQUENCY OUTPUT__________HERTZ
C. CHECK OIL LEVEL
D. IF OIL COLOR INDICATES CONTAMINATION, CHANGE OIL & OIL FILTER
E. IF OIL FILTER & OIL ARE CHANGED, RESTART ENGINE AND RUN FOR
5 MINUTES. SHUT DOWN & CHECK OIL LEVEL
F. CHECK BATTERY WATER AND CONNECTIONS FOR CORROSION, ENSURE DRYNESS
G. CLEAN BATTERY AND TIGHTEN BATTERY TERMINALS
H. CHECK AIR FILTER
I. IF AIR FILTER IS DIRTY, REPLACE
J. CHECK FUEL (LP) LINES AND CONNECTION LEVEL AND RECORD __________%
K. IF MORE FUEL IS NEEDED (<40%), SUBMIT REQUEST FOR ORDER
L. INSPECT AND CLEAN LOUVERS
M. CHECK FOR VIBRATION, MOISE, LEAKAGE AND TEMPERATURE
SEMI-ANNUAL:
A. PERFORM ALL MONTHLY FUNCTIONS
B. CHECK CHARGE STATE AND REPLACE (IF NECESSARY)
C. CHECK ELECTROLYTE LEVEL (UNSEALED BATTERIES ONLY) AND REPLACE (IF NECESSARY)
ANNUAL:
A. PERFORM ALL MONTHLY AND SEMI-ANNUAL FUNCTIONS
B. CHECK AIR CLEANER AND REPLACE (IF NECESSARY)
C. CHECK SPARK PLUG(S) AND REPLACE (IF NECESSARY)
Instruction Code Date Last Edited
METER READING: __________
YEARLY
1. CLEAN THE ENCLOSURE.
2. CHECK THE TRANSFER SWITCH CONTACTS.
3. MAINTAIN TRANSFER SWITCH LUBRICATION. USE CASTROL ENDUREX 4000 LUBRICANT.
4. CHECK ALL CABLE CONNECTIONS AND RETIGHTEN THEM.
Instruction Code Date Last Edited
D. CHECK PIPING FOR LEAKS
E. CLEAN OUT EACH PIT OF ALL MUD & DEBRIS
096 11/10/2001
097 5/8/2012
098 11/10/2001
099 2/16/2010
100 2/16/2010
101 2/16/2010
12/14/2020 102 11/10/2001
103 11/24/2014
104 11/10/2001
105 5/1/2017
A. CHECK CORDS, HOSES, MOTOR & DRAIN CLEAN
B. RUN TO INSURE PROPER OPERATION
Instruction Code Date Last Edited
A. TURN ON EXHAUST SYSTEM
B. THE GAUGES WILL READ WHEN NEW .20 .40 1.0
C. IF THEY NEED TO BE CHANGED THE GAUGES WILL READ .75 1.25 1.75
D. IF FILTERS NEED TO BE CHANGED
A. CHECK ELECTRICAL CORD
B. CHECK BEARING
C. CHECK BRUSH
D. CHECK HOSES
E. CHEKC RUBBER SHOES ON FLOOR TOOL
Instruction Code Date Last Edited
A. CLEAN VAULT OF ANY DEBRIS, SWEEP FLOOR USING SWEEPING COMPOUND
B. INSPECT OUTSIDE LOUVERS FOR PROPER OPERATION SEAL FOR WINTER OPERATION
ROOM 0108
ROOM 0042
ROOM 0315
ROOM 0024
ROOM 1226
ROOM 0329
Instruction Code Date Last Edited
TORNADO FLOOR BURNISHER
A. CHECK CORD FOR WEAR
B. CHECK CONDUCTIVITY FROM GROUND & HOT SPADES ON PLUG TO FRAME
C. CHECK BRUSHES
D. LUBRICATE AS NEEDED
E. REMOVE COVERS & BLOW OUT WITH LOW PRESSURE AIR HOSE
F. WIPE EXCESS DUST FROM UNIT
Task Instruction List National Center Agricultural Utilization Research
Instruction Code Date Last Edited
A. LUBRICATE UNIT AS NEEDED
B. CHECK BRUSHES
C. CLEAN COMMUNICATOR
D. INSPECT CONNECTIONS ON WIRING
E. INSPECT CORD FOR DAMAGE OR WEAR
F. CHECK FOR PROPER OPERATION
Instruction Code Date Last Edited
A. CHECK CORD FOR WEAR
B. CHECK CONTINUITY FROM GROUND & HOT SPADES ON PLUG TO FRAME
C. LUBRICATE AS NEEDED
D. REMOVE COVERS & BLOW OUT WITH LOW PRESSURE AIR HOSE
E. WIPE EXCESS DUST FROM UNIT
Instruction Code Date Last Edited
A. CHECK ALL WIRING CONNECTIONS
B. MANUALLY TRIP THE ALARM SYSTEM TO ENSURE PROPER OPERATION
C. VERIFY PHONE IS IN WORKING ORDER
Instruction Code Date Last Edited
A. CHECK FRONT OF DRYER
B. CLEAN LINT FROM AROUND TUB
C. CLEAN OUTSIDE SURFACES OF DRYER
D. CLEAN LINT FILTER & CAVITY OF ALL LINT
E. CHECK DRIVE BELT CONDITION & TENSION
F. CHECK CYCLE TIMER FOR PROPER OPERATION
Instruction Code Date Last Edited
VENTS ARE BLOCKED OFF.
Instruction Code Date Last Edited
ELECTRICAL CHECK
A. CHECK ELECTRICAL CONNECTIONS FOR TIGHTNESS
B. RUN MACHINE ONE FULL CYCLE FOR PROPER OPERATION
C. CHECK CONDITION OF DRIVE BELT
PLUMBING CHECK
A. CLEAN OUT HOSE STRAINERS
B. CHECK CONDITION OF HOSES
C. CHECK DRAIN FOR PROPER DRAINAGE
D. CLEAN UNIT INSIDE & OUT
106 11/10/2001
107 2/4/2008
108 11/10/2001
109 8/22/2012
12/14/2020 110 8/1/2012
111 8/17/2012
112 7/10/2002
RECORD METER READINGS ON WATER METERS
WTR-METER-01 _______________
WTR-METER-02 _______________
Instruction Code Date Last Edited
MONTHLY:
FLUSH WATER HEATER TO PREVENT STAGNANT WATER
CHECK TEMPERATURE/PRESSURE RELIEF VALVE
Instruction Code Date Last Edited
National Center Agricultural Utilization Research Instruction Code Date Last Edited
A. VISUALLY INSPECT THE ICE MACHINE FOR:
1. APPEARANCE
2. EXTERNAL DAMAGE
3. DOOR & DOOR CLOSURE SLIDES
4. WATER LEAKAGE ON FLOOR
B. INSPECT THE WATER LINE & INSPECT WATER FLOAT SHUT OFF VALVE
C. REMOVE INSPECTION COVERS & INSPECT THE REFRIGERATION & ELECTRICAL SYSTEM FOR VISIBLE DEFECTS
D. ENSURE ALL NUTS, BOLTS, SCREWS & FASTENERS ARE SECURE
E. CLEAN THE CONDENSER COIL, FILTER
F. RUN THE SYSTEM TO CHECK FOR PROPER ICE DROPPING & ENSURE THE DRAIN IS OPEN
G. AFTER VARIFYING THE UNIT IS FULLY OPERATIONAL, CLOSE ALL INSPECTION COVERS & CLEAN UP ANY
MESS IN THE AREA
A. SHUT DOWN UNIT AND LOCK OUT
B. CHANGE OIL ON PRIME MOVER
C. CLEAN UP, UNLOCK UNIT & RESTART
Instruction Code Date Last Edited
ICE MACHINE #1 (ADMIN.):
A. CHANGE WATER FILTERS
B. CHECK SCALE BUILD UP ON WATER CURTAIN
C. DISTRIBUTION TUBE
D. WATER THROUGH ICE BIN
E. CHECK CONDENSER AIR FILTER
F. CLEAN WITH MANITOWOC CLEANER
G. CLEAN ICE BIN, FLOAT ASSEMBLY, WATER AND DRAIN HOSES, FAN MOTOR AND BLADE, AIR FILTER.
H. CLEAN EVAPORATOR WITH ICE MACHINE CLEANER.
I. TEST OPERATION.
ICE MACHINES #2-#15:
A. CHANGE WATER FILTERS
B. CHECK CONDENSER AIR FILTER
C. CLEAN WITH NU-CALGON CLEANER
D. CLEAN ICE BIN, FLOAT ASSEMBLY, WATER AND DRAIN HOSES, FAN MOTOR AND BLADE, AIR FILTER
E. CLEAN EVAPORATOR WITH ICE MACHINE CLEANER
F. TEST OPERATION
Task Instruction List
A. DISCONNECT POWER TO UNIT
B. CLEAN BLOWER, HEATER FINS & CABINET
C. CHECK OPERATION OF THERMOSTAT & HEATING ELEMENT
D. CLEAN EXTERIOR OF UNIT
Instruction Code Date Last Edited
A. CHECK OPERATION OF LOUVERS
B. CHECK FOR DIRTY SCREEN, CLEAN IF NEEDED
C. LUBRICATE LINKAGES/ADJUST AS NEEDED
D. CHECK PROER OPERATION THROUGH BMS SYSTEM
E. ADJUST AS NECESSARY FOR TIGHT SEAL WHEN 100% CLOSED
Instruction Code Date Last Edited
1. WEAR DUST MASK
2. WEAR PROTECTIVE SUIT
3. MAKE SURE THERE IS A 38X64 BODY BAG OVER THE FILTER HOUSING
4. REMOVE FILTER FROM OUTSIDE FILTER APPARATUS
5. PLACE FILTER DIRECTLY INTO FULL-SIZED BODY BAG 38X64 AND TAPE CLOSED
6. PLACE INTO ANOTHER FULL-SIZED BODY BAG AND TAPE CLOSED
7. PLACE ON MILLING TABLE IN 0321
8. HAVE OFFICE STAFF EMAIL DESIGNATED INDIVIDUALS THAT FILTER IS READY FOR TREATMENT
AS OF 2/24/17 DESIGNATED INDIVIDUALS ARE:
JACOB BROWN
CHRYTAL PROBYN
113 9/21/2012
114 1/11/2003
115 11/12/2004
116 1/30/2003
117 11/12/2004
118 10/26/2011
12/14/2020
119 9/5/2019
120 2/22/2003
CHANGE WATER FILTER
ROOM 2009:
FILTER - GRAINGER
29AH6Z- 1 EACH
29AH44- 1 EACH
ROOM 2032:
FILTER - 29AH6Z- 1 EACH
29AH44- 1 EACH
Instruction Code Date Last Edited
1. WORK VALVE THROUGH COMPLETE CYCLE
2. GREASE
3. LUBE STEM
Task Instruction List National Center Agricultural Utilization Research
1. INSPECT HYDRANT CONDITION FOR LEAKS, CRACKS, BREAKS AND OTHER DAMAGE.
2. OPEN HYDRANT FULLY, UNTIL ALL FOREIGN MATERIAL HAS CLEARED.
DO ONLY ANNUALLY IN AUGUST (NOT LESS THAN 1 MINUTE)
3. LUBRICATE ALL STEMS, CAPS, PLUGS AND ENSURE THREADS ARE IN PROPER CONDITION.
4. COMPLETE CORRECTIVE MAINTENANCE ACTION FOR WORK ON HYDRANT THAT CANNOT BE
COMPLETED AT THE TIME OF TEST AND INSPECTION.
MONTHLY VISUAL INSPECTION OF ALL FIRE HYDRANTS AND STANDPIPES.
HYDRANTS:
3 WEST PARKING LOT
1 NORTH, 1 CENTER, AND 1 SOUTH
1 NW WEST, 1 CW WEST, 1 SW WEST
STANDPIPES: 2 BETWEEN SEMIWORKS AND BOILERHOUSE.
Instruction Code Date Last Edited
1. CHECK FOR HYDRAULIC FLUID LEAKS.
2. TIGHTEN HYDRAULIC FITTINGS IF NECESSARY.
Instruction Code Date Last Edited
1. REPLACE THE HYDRAULIC OIL AND FILTER.
2. CHECK PRESSHEAD GUIDES FOR WEAR AND ADJUST APPROPRIATELY.
3. CHECK THE CYLINDER MOUNTING PINS FOR WEAR.
Instruction Code Date Last Edited
1. BLOW DOWN STRAINERS
2. CHECK FOR PROPER OPERATION
Instruction Code Date Last Edited
1. CLEAN ANY LOOSE MATERIAL FROM IN OR AROUND THE CART DUMPER AND POWER UNIT.
2. GREASE THE TURNBUCKLES FOR THE CONTAINER.
3. CHECK THE OIL LEVEL WITH THE PRESSHEAD FULLY RETRACTED.
4. CHECK ALL HYDRAULIC HOSES FOR RUBBING, CHAFING, DETERIORATION, DAMAGE AND LEAKS.
5. CHECK ALL HYDRAULIC FITTINGS FOR LOOSENING AND LEAKS.
6. CHECK THAT ALL SAFETY DECALS ARE PRESENT AND LEGIBLE.
Instruction Code Date Last Edited
WTR-METER-03 _______________
WTR-METER-04 _______________
WTR-METER-05
Instruction Code Date Last Edited
CHECK HOUR METER FOR EACH PIECE OF ATTACHED EQUIPMENT
RECORD HOUR METER AND DATE:
LIFT…