This document provides draft materials for a solicitation seeking a Family of All Terrain Cranes. The draft Section C outlines the scope of work to acquire the cranes. Draft attachments and contract data requirement lists are also included for industry review and comment by December 11, 2020. The Army Materiel Command TACOM Life Cycle Management Command will consider feedback and finalize the request for proposal to be posted on SAM.gov. The notice does not constitute a formal solicitation and the government does not intend to award based on its contents. Interested parties should monitor the formal RFP for required crane specifications and delivery timelines. The Army seeks this family of cranes to support its materiel needs.

View the file

Other files

File Type Posted
A082 _ Tool Locator Guide.pdf PDF
A053 _ NMWR Data Summary.pdf PDF
A007 _ Integrated Product Support (IPS).pdf PDF
A071 _ Critical Task List-FOATC.pdf PDF
A056 _ Storage_ Exercise_ Care and Maintenance Plan.pdf PDF
Attachment 0014 _ Hazardous Materials Management Report _ HMMR.XLSX XLSX spreadsheet
A029 _ Safety Assessment Report _ SAR.pdf PDF
A005 _ Integrated Master Schedule (IMS).pdf PDF
Attachment 0027 _ LMI Summary Worksheet _ NMWR Data.pdf PDF
A074 _ New Equipment Training Classes.pdf PDF
Attachment 0009 _ Provisioning Requirements Statement.pdf PDF
A070 _ Training Material Format and Documentation.pdf PDF
Attachment 0025 _ EPCO Source File Requirements.pdf PDF
A017 _ Provisioning Pre-Procurement Screening.pdf PDF
A095 _ Test Support Package _ TSP.pdf PDF
A030 _ System Safety Program Plan _ SSPP.pdf PDF
A058 _ Provisioning Plan.pdf PDF
A036 _ Logistics Support Analysis (LSA).pdf PDF
Attachment 0037 _ Unique Item Identifier Raw Scan Report.xlsx XLSX spreadsheet
A055 _ Accountability Report.pdf PDF
Attachment 0001 - Type I FOATC PD - AT-PRF-0001 Type I FOATC PD 2020-10-08.pdf PDF
A028 _ Hazard Tracking System - HTS.pdf PDF
Attachment 0010 _ LMI Summary Worksheet _ Maintenance Analysis.pdf PDF
A038 _ Logistics Product Data Summary (LPDS).pdf PDF
A075 _ Training Course Completion Report-Student Training Administration.pdf PDF
A063 _ Logistics Product Data.PDF PDF
Attachment 0028 _ Attribute Selection Sheet.pdf PDF
Attachment 0007 _ Exhibit A CDRL DD Form 1423.pdf PDF
A089 _ Obsolescence Supportability Analysis Report.pdf PDF
A079 _ Sample IUID Data Plate Report.pdf PDF
A093 _ Analysis Requirement.pdf PDF
A001 _ Basic Issue Items (BII) List.pdf PDF
A062 _ Bill of Materials Report.pdf PDF
A052 _ NMWR Technical Manual.pdf PDF
Attachment 0006 _ Government Furnished Property (GFP) List.xlsx XLSX spreadsheet
Attachment 0012 _ Risk Management Scoring Criteria and Reporting Template.xlsx XLSX spreadsheet
A067 _ Field Level Maintenance New Equipment Training.pdf PDF
A020 _ Failure Mode _ Effects and Criticality Analysis (FMECA).pdf PDF
A065 _ Packaging Test Report.PDF PDF
A083 _ System Tracking and Shipping Report.pdf PDF
Attachment 0030 _ LMI Data Products Worksheet.pdf PDF
Attachment 0005 _ COTS Publications Requirements.pdf PDF
Attachment 0029 _ GEIA-STD-0007 Attribute Selection Worksheet.xlsx XLSX spreadsheet
Attachment 0038 _ TACOM IUID Data Plate Minimum Requirements.pdf PDF
A085 _ DMSMS Management Plan.pdf PDF
Attachment 0022 _ Copyright Release.pdf PDF
Attachment 0017 _ Deployment Equipment Publications Style Guide.pdf PDF
A027 _ Risk Tracking Report.pdf PDF
A037 _ Product Support Analysis (PSA) and Logistics Product Data (LPD) Objectives.pdf PDF
A057 _ Maintainability Evaluation Planning.pdf PDF
Show 40 more

Latest 50 of 133 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 0016

LEVEL OF REPAIR ANALYSIS (LORA)

1. COMPASS. COMPASS is the Army approved system-level LORA model. This program is available to all U.S. Government offices and their contractors working under a current contract. The Contractor may obtain the COMPASS software at: https://www.logsa.army.mil/#/lec/compass

Software training on is available to the contractor. The Contractor may schedule training by contacting:

The Technical Support Branch: usarmy.redstone.LDAC.mbx.tsb-smartdesk@mail.mil

Data elements for the input spreadsheet shall be completed as indicated below.

Field Definition Status Applied To

Item Item type to be created in COMPASS database (must be

LRU, NLRU, SRU, or NSRU)

Required All

Nomenclature Item nomenclature, required if name preference is set to "Nomenclature" in input database

Required All

FGC

Item FGC, required if name preference is set to FGC" in input database "

Required All

Part Number

Item Part Number, required if name preference is set to Part Number" in input database "

Required All

NIIN

Item NIIN, required if name preference is set to NIIN" in input database "

Required if available All

CAGE CAGE code Required All

SMR

Source, Maintenance, and Recoverability code Optional All

Unit Price Item unit price Required All

False Removal

Rate Item false removal rate Required All

Washout Rate Item washout rate Required All

Unit Weight Item packaged shipping weight Required All

Avg Price of Parts Average price of piece (repair) parts for an item Required All

MTTR

Item Mean Time To Repair; part of item repair alternative Required All

Diagnostic Time Item Diagnostic Time; part of item repair alternative

Required All

TPS Dev Cost Test Program Set (TPS) Development

Cost; part of item repair alternative Required All

TPS Main Cost TPS Maintenance Cost; part of item repair alternative Required All

Pages of Doc Number of pages of technical documentation for an item; part of item repair alternative

Required All

LRU Association Name of LRU which the SRU/NSRU is associated

Required SRU/NSRU

MTBF Mean Time Between Failure for item Required NLRU/SRU/NSRU

2. Additional information for completing the LORA effort.

ATTACHMENT 0016

LEVEL OF REPAIR ANALYSIS (LORA)

a. The first step in the process is to develop a LORA candidate list; initial candidate list shall include all repairable items/components. A copy of this list shall be provided to the government.

b. The initial candidate list shall include all repairable items/components. If the repairable items/components are determined not to be viable LORA candidates when analyzed, these items/components shall be annotated as not applicable (N/A).

c. Levels of Maintenance – For the purpose of this effort the following levels shall be used: Field

Maintenance (DS), Sustainment Maintenance (DEPOT and Contractor).

d. Remove/Replace and Repair Time - The current commercial repair/replace times shall be used. If times are not available, times shall be estimated using MIL-HDBK-470A.

e. Failure Rates – The current commercial failure rates shall be used for the initial/baseline results.

The failure rates shall be increased as stated elsewhere in this attachment.

f. Unknown DATA - Elements that do not have current or known data shall use historical data for that item/component or a like item/component; data shall be either commercial or military.

g. Special Tools – All individual Special Tools needed for repair tasks shall be added under Support

Equipment. Support Equipment shall be incorporated in each evaluation.

h. All data shall be entered in COMPASS and be as complete as possible, this is to ensure that the evaluations are as accurate as possible.

3. Evaluations to be completed for this effort

a. Non-Economic Evaluation

b. Economic Evaluation

c. Sensitivity and Trend Analysis – The Parameters that are to be adjusted for these analyses are:

Mean Time Between Failure (MTBF) - shall be +/- 30 percent

Operating Hours – Shall be +/- 50 percent

Mean Time To Repair (MTTR) – shall be +/- 30 percent

For all Evaluations listed above the contractor shall provide a Front End Analysis (FEA) and

Maintenance Policy for each evaluation completed.