Attachment 0004- Use of Existing Government-Furnished Property.pdf

PDF 106 KB Posted

Attached to
Detroit Arsenal Construction MATOC
Solicitation number
W56HZV20RL812
Issued by

About this file

This document provides instructions for offerors to calculate a Government Furnished Property Price Adjustment for evaluation purposes as part of a solicitation from the U.S. Army Garrison - Detroit Arsenal for construction services. Offerors are to list existing Government property they plan to use and its acquisition cost, age, and type. For evaluation, the Government will calculate monthly rental rates ranging from 0.75% to 3% of the acquisition cost based on the property's age and Federal Supply Classification, and multiply that by the number of proposed months of use. If property will be used for other work as well, the adjustment is to be prorated based on proposed direct labor hours or other equitable measurement. Property is offered on an as-is basis, and the evaluation will also include costs to make it available F.O.B. loading dock. Offerors must provide all rental adjustment calculations with their proposals.

View the file

Other files

File Type Posted
DTA Construction MATOC RFP Questions as of 02 April 2020.pdf PDF
DTA Construction MATOC RFP Questions as of 27 March 2020.pdf PDF
W56HZV-20-R-L812 RFP Amendment 0003.pdf PDF
DTA Construction MATOC RFP Questions as of 25 March 2020.pdf PDF
W56HZV-20-R-L812 RFP Conformed through Amendment 0003.pdf PDF
DTA Construction MATOC RFP Questions as of 23 March 2020.pdf PDF
W56HZV-20-R-L812 Amendment 0002.pdf PDF
W56HZV-20-R-L812 Conformed Through Amendment 0002.pdf PDF
DTA Construction MATOC RFP Questions as of 13 March 2020.pdf PDF
DTA Construction MATOC RFP Questions as of 05 March 2020.pdf PDF
DTA Construction MATOC RFP Questions 04 March 2020.pdf PDF
W56HZV-20-R-L812 Conformed Through Amendment 0001.pdf PDF
W56HZV-20-R-L812 Amendment 0001.pdf PDF
Attachment 0005- STA Form 17.pdf PDF
Attachment 0012- QA Report Daily Log ENG FORM 2538-1.pdf PDF
Attachment 0016- Sample Design Build Task Order SOW.pdf PDF
Attachment 0006- Eng Form 4025.pdf PDF
Attachment 0014- HAZMART User Handbook (Appendix H).pdf PDF
Attachment 0019- BAS Standard Requirements Detroit Arsenal.pdf PDF
Attachment 0009- DD 1354 Real Property Transfer.pdf PDF
Attachment 0013- Construction Impact Notification Form.doc DOC document
Attachment 0001- Pricing Workbook.xlsx XLSX spreadsheet
Attachment 0011- Contractor Quality Control Report.pdf PDF
DTA MATOC RFP- W56HZV-20-R-L812.pdf PDF
Attachment 0007- RFI Form.doc DOC document
Attachment 0003- DBA wage Determination MI20200091 14 February 2020.pdf PDF
Attachment 0008- DPW Drawing Standards (Appendix C).pdf PDF
Attachment 0010- STA 1901 Camera Pass.pdf PDF
Attachment 0018- Environmental (Appendix A).pdf PDF
Exhibit A- CDRLS.pdf PDF
Attachment 0017- Sample Design Bid Build Task Order SOW.pdf PDF
Attachment 0015- New Equipment Checklist.pdf PDF
Attachment 0002- Past Performance Questionnaire.doc DOC document
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W56HZV‐20‐R‐L812

Attachment 0004 ‐ Use of Existing Government‐Furnished Property

Instructions

‐ Offerors are not to provide any inputs within this Attachment.

a) Rent‐free use of existing facilities, special test equipment, and/or special tooling, title to which is in the Government or to which the Government has the right to take title (all of which is herein described as property), including rent‐free use by prospective subcontractors, will be a consideration in the evaluation of responses to this solicitation. The offeror shall provide with its proposal, the list of Government Furnished Property (GFP), the acquisition cost, age, and type of GFP.

b) For purposes of evaluation only, the GFP Price Adjustment for each classification of property, computed as follows, shall be added by the Government to the Proposed Price. The

GFP Price Adjustment shall be computed by multiplying the acquisition cost of each item of property by the rental rates specified below, and then multiplying the product obtained by the number of months of use proposed. A minimum of one month of use shall be required for purposes of evaluation. Fractional portions of a month shall be counted as a full month. The final GFP Price Adjustment shall be separately set forth by the offeror under the proposed price.

c) Monthly Rental Rates:

(1) For land and land preparation, buildings, building installations, and land installations other than those items specified in (2) below: the prevailing commercial rate.

(2) For industrial plant equipment of the types covered by Federal Supply Classification Code Numbers 3405, 3408, 3410, 3411 through 3419 (machine tools), and 3441 through 3449

(secondary metal forming and cutting machines), the following rates shall apply:

Age of Equipment Monthly Rental Rates

0‐2 years 3.00%

Over 2 to 3 years 2.00%

Over 3 to 6 years 1.50%

Over 6 to 10 years 1.00%

Over 10 years 0.75%

(3) For personal property and equipment not covered in (1) and (2) above (including all production equipment not in the Federal Supply Classification Codes set forth above, and including special tooling and special test equipment), the following rates shall apply:

‐‐ Two percent (2.00%) per month for electronic test equipment and automotive equipment;

‐‐ One percent (1.00%) per month for special tooling and for all other property and equipment.

d) If any item of property is to be used on other work for which use has been authorized during the period such property is requested for use on any contract resulting from this solicitation, the GFP Price Adjustment shall be calculated in accordance with the following: the acquisition cost of each item of property shall be multiplied by the rental rates specified for the applicable classification of property set forth above, and the product obtained shall then be multiplied by the number of months of rent‐free use requested. The resulting product shall be multiplied by a fraction, the numerator of which is the amount of use of the property proposed under this solicitation, and the denominator of which is the sum of the previously authorized use of the property during the period of proposed use and the use proposed under this solicitation. The measurement unit for determining the amount of use to be considered in establishing the fraction referred to in the foregoing calculation shall be direct labor hours, sales, hours of use, or any other measurement unit which will result in an equitable apportionment of the GFP Price Adjustment. The measurement unit used and the amount of respective uses shall be set forth in sufficient detail to support the proration for each item of property.

e) For the purposes of determining the GFP Price Adjustment set forth above, the following definitions apply:

(1) The term acquisition cost means the total cost to the Government for an item of property, including the cost of (i) transportation, (ii) installation, (iii) accessories to be used with the item, and (iv) any rebuilding and modernization which has enhanced the original capability of the item;

(2) The age of an item of property shall be based on the year in which it was manufactured, with an annual birthday on 1 January of each year thereafter. On 1 January following the date of manufacture, the item shall be considered one year old; and on each succeeding January 1st, it shall become one year older (thus, an item manufactured on 15 July 1978 would be one year old on 1 January 1979, and over two years old on and after 1 January 1980).

f) Where this solicitation provides that the property is offered for use on an as‐is basis, F.O.B. loading dock at present location, the Government shall add to the Evaluated Cost, in addition to the GFP Price Adjustment described above, an adjustment, for purposes of evaluation, which will be composed of the costs to the Government of making such property available at the F.O.B. point, including the costs of disconnection, preparation for shipment, and placement on the loading dock.

‐ If the offeror is proposing to utilize Government‐Furnished Property (GFP) on a rent‐free basis in performance of this contract, then the offeror shall calculate the GFP Price