ATT1 SOI CM Fire Ops Center.xlsx

XLSX spreadsheet 14 KB Posted

Attached to
Huron Manistee NF Construct Cadillac-Manistee Fire Ops Center Federal contract opportunity
Solicitation number
12445523R0018
Issued by
Department of Agriculture Forest Service

About this file

This document package includes a bid sheet and related federal contract opportunity details. The bid sheet requests pricing for the construction of a new 6,000 square foot Cadillac-Manistee Fire Operations Center located in Wellston, Michigan, including base bid items for facility construction, services, and site work, as well as optional bid items. An alternate proposal is also included for a reduced 4,920 square foot footprint. The single award firm fixed price contract will be awarded before August 1, 2023 by the U.S. Department of Agriculture Forest Service to build the warehouse structure. Bidders should provide lump sum pricing for mobilization and the various construction elements. The response due date and other submission details are not provided.

View the file

Other files for this federal contract opportunity

Other files attached to Huron Manistee NF Construct Cadillac-Manistee Fire Ops Center, newest first.
File Type Posted
Decom Staff Office P7290030.JPG JPG image
Decom Staff Office Page 57 from Report.pdf PDF
Decom Staff Office Page 242 from Report.pdf PDF
Decom Staff Office P7290024.JPG JPG image
Decom Staff Office P7290031.JPG JPG image
Decom Staff Office P7290025.JPG JPG image
RFI log for Q and A 6-30-2023 FINAL.xlsx XLSX spreadsheet
099723 Concrete Sealer.pdf PDF
090403-ABL2022-0002-A421-A405 INTERI0R SIGN ELEVATIONS_REV01.pdf PDF
095123 Acoustical Tile Ceilings.DOC DOC document
RFI log for Q and A 6-28-2023.xlsx XLSX spreadsheet
Sol_12445523R0018_Amd_0003.pdf PDF
RFI log for Q and A 6-27-2023.xlsx XLSX spreadsheet
220063_01_230601_DRAWINGS.pdf PDF
220063_STAFFHOUSE_TABLE OF CONTENTS and SPECS.pdf PDF
Sign-in sheet.pdf PDF
329200 SEEDING and MULCHING.pdf PDF
RFI log for Q and A.xlsx XLSX spreadsheet
323113 Chain Link Fences and Gates.doc DOC document
090403-ABL2022-0002-A626-SCHEDULES_REV03.pdf PDF
Sol_12445523R0018_Amd_0002.pdf PDF
QandA 6-9-23.pdf PDF
ATT2 CADILLAC-MANISTEE FIRE OPERATIONS CENTER_SPECIFICATIONS_FINAL SUBMISSION_REV03.pdf PDF
ATT2 CADILLAC-MANISTEE FIRE OPERATIONS CENTER_SPECIFICATIONS_FINAL SUBMISSION_REV02.pdf PDF
Sol_12445523R0018_Amd_0001.pdf PDF
ATT1 SOI CM Fire Ops Center.pdf PDF
ATT3 2022-HM-CADILLAC-MANISTEE FIRE OPERATIONS CENTER-CD FINAL SUBMISSION v.02.pdf PDF
ATT9 C1-02_New Fire House Geometric Plan-REV01.pdf PDF
ATT11 C5-17 SEPTIC and WATER SYSTEM DETAILS-REV-001.pdf PDF
ATT5 090403-ABL2022-0002-A417-A401-WALL SECTIONS_REV01.pdf PDF
Sol_12445523R0018.pdf PDF
ATT7 090403-ABL2022-0002-A420-A404 INTERIOR ELEVATION_REV02.pdf PDF
ATT10 C1-16 SEPTIC DRAINFIELD and SEPTIC TANK-REV01.pdf PDF
ATT12 Wage Determination MI20230134.pdf PDF
ATT2 CADILLAC-MANISTEE FIRE OPERATIONS CENTER_SPECIFICATIONS_FINAL SUBMISSION_REV01.pdf PDF
ATT4 090403-ABL2022-0002-A214-EXTERIOR ELEVATION_REV01.pdf PDF
ATT6 090403-ABL2022-0002-A419-A403 INTERIOR ELEVATIONS_REV01.pdf PDF
ATT8 090403-ABL2022-0002-A626-SCHEDULES_REV02.pdf PDF
Show all 38

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table 1

Item
NumberDescriptionPay UnitQuantityUnit PriceTotal Price
PREFERRED ALTERNATE (6,000SF)
1Mobilization
Includes costs for mobilization of equipment, materials, and supplies, which are not included in a line item below. This would include but not limited to; bonding, insurance, permit fees, field office and staff, temporary utilities (phone, power, sanitation), site clean-up, waste disposal, field office vehicles and their operational costs, temporary utilities, superintendence, construction fencing, safety and QC costs, and any other project costs not directly associated with a line item below.LUMP SUM1
2FACILITY CONSTRUCTION SUBGROUP
Divisions 03 - 12LUMP SUM1
3FACILITY SERVICES SUBGROUP
Divisions 22 - 28LUMP SUM1
4SITE AND INFRASTRUCTURE SUBGROUP
Divisions 31- 33LUMP SUM1
TOTAL PRICE FOR BASE BID ITEMS
OPTIONAL BID ITEMS
ItemDescriptionPay UnitQuantityUnit PriceTotal Price
OP-1Interior Painting
Reference sheet A6-01 for optional "Finish Schedule"LUMP SUM1
OP-2CU-1, Grade Mounted Condesning Unit
Reference sheet H1-01 & H6-01 for details on optional air conditioning equipment.LUMP SUM1
OP-3Electric Duct Heater
Reference sheets H1-01 & H6-01 for details on optional duct heater equipemtn.LUMP SUM1
OP-4Refreshment Area Cabinetry
Includes upper & base cabinets and countertop. Reference sheet A1-01 & A4-04.LUMP SUM1
OP-5Fire Cache Enclosure
Reference sheets A1-01 & A4-04LUMP SUM1
OP-6Accordion Folding Partion
Reference sheets A1-01 & A5-02LUMP SUM1
OP-7Window Shades
Reference Divison 12 - Furnishings, 122400 Clutch-Operated Window Shades.LUMP SUM1
OP-8Landscape Amentities - Plantings
Reference "L" sheets, item includes plantings only.LUMP SUM1
OP-9Landscape Amenities - Concrete Walkway, Dumpster Screen, Signage, all other items not included with "Plantings"
Reference "L" sheets & A4-05LUMP SUM1
OP-10Demolition of Existing Facility
Decommissioning of exisitng fire module office located near main entrance. Separate plans provided.LUMP SUM1
TOTAL PRICE OF OPTION ITEMS
Item
NumberDescriptionPay UnitQuantityUnit PriceTotal Price
ALTERNATE #1, Reducded Footprint (4,920SF) See Sheets AA1-01 & AA2-01 for details
1AMobilization
Includes costs for mobilization of equipment, materials, and supplies, which are not included in a line item below. This would include but not limited to; bonding, insurance, permit fees, field office and staff, temporary utilities (phone, power, sanitation), site clean-up, waste disposal, field office vehicles and their operational costs, temporary utilities, superintendence, construction fencing, safety and QC costs, and any other project costs not directly associated with a line item below.LUMP SUM1
2AFACILITY CONSTRUCTION SUBGROUP

Divisions 03 - 12

Contractor repsonsible for calculating takeoffs for reduction in square footage for Alternate #1. See sheets AA1-01 & AA2-01 for details.LUMP SUM1
3AFACILITY SERVICES SUBGROUP

Divisions 22 - 28

For additional details on Aleternate #1 reductions for HVAC and electrical equipment reference sheets H1-01 & E1-03.LUMP SUM1
4ASITE AND INFRASTRUCTURE SUBGROUP

Divisions 31- 33

Contractor repsonsible for calculating takeoffs for reduction in square footage for Alternate #1. See sheets AA1-01 & AA2-01 for details.LUMP SUM1
TOTAL PRICE FOR BASE BID ITEMS
OPTIONAL BID ITEMS
ItemDescriptionPay UnitQuantityUnit PriceTotal Price
OP-1AInterior Painting
Reference sheet A6-01 for optional "Finish Schedule"LUMP SUM1
OP-2ACU-1, Grade Mounted Condesning Unit
Reference sheet H1-01 & H6-01 for details on optional air conditioning equipment.LUMP SUM1
OP-3AElectric Duct Heater
Reference sheets H1-01 & H6-01 for details on optional duct heater equipemtn.LUMP SUM1
OP-4ARefreshment Area Cabinetry
Includes upper & base cabinets and countertop. Reference sheet A1-01 & A4-04.LUMP SUM1
OP-5AFire Cache Enclosure
Reference sheets A1-01 & A4-04LUMP SUM1
OP-6AAccordion Folding Partion
Reference sheets A1-01 & A5-02LUMP SUM1
OP-7AWindow Shades
Reference Divison 12 - Furnishings, 122400 Clutch-Operated Window Shades.LUMP SUM1
OP-8ALandscape Amentities - Plantings
Reference "L" sheets, item includes plantings only.LUMP SUM1
OP-9ALandscape Amenities - Concrete Walkway, Dumpster Screen, Signage, all other items not included with "Plantings"
Reference "L" sheets & A4-05LUMP SUM1
OP-10ADemolition of Existing Facility
Decommissioning of exisitng fire module office located near main entrance. Separate plans provided.LUMP SUM1
TOTAL PRICE OF OPTION ITEMS