Atch_12__Seed_TO_Price_Schedule.xlsx

XLSX spreadsheet 10 KB Posted

Attached to
Environmental Remediation Services MATOC Federal contract opportunity
Solicitation number
140A1625R0007
Issued by
Department of the Interior Bureau of Indian Affairs Central Office

About this file

This document appears to be the Seed Task Order Price Schedule for an Environmental Remediation Services Multiple Award Task Order Contract (MATOC) solicitation. The Seed Task Order Price Schedule establishes a firm fixed price for Phase 1 and additional binding rates for Phase 2 of the contract. The Phase 2 binding rates cover various remediation services including asbestos-containing material (ACM) removal, lead-based paint removal, mold removal, and drywall replacement. These binding rates may offer discounts to the rates in the IDIQ Binding Price Schedule based on project specifics and estimated quantities, but must not exceed the IDIQ rates. The overall Environmental Remediation Services MATOC solicitation has the number 140A1625R0007 and is being issued by the Department of the Interior, Bureau of Indian Affairs Central Office.

View the file

Other files for this federal contract opportunity

Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Seed Task Order Price Schedule
UnitQuantityUnit PriceExtended Price
Phase 1
Price for Phase 1Job1
Phase 2
Binding rate for:
ACM insulation/lining for pipes/electrical, removal and disposallinear feet50
ACM surfacing material, removal and disposalsquare feet13000
ACM flooring, removal and disposalsquare feet500
Lead-based paint, removal and disposalsquare feet500
Mold removal on surfacessquare feet5000
Dry wall replacementsquare feet13000
Radon Mitigation SystemJob for entire bldg1
Note: The IDIQ Binding Price Schedule establishes ceiling prices for all task orders. The Seed Task Order Price Schedule establishes a firm fixed price for Phase 1 and additional binding rates for Phase 2. These Seed Task Order binding rates for Phase 2 may offer discounts to the rates offered in the IDIQ Binding Price Schedule based on project specifics and estimated unit quantities. Seed Task Order binding rates MUST NOT exceed the rates in the IDIQ Binding Price Schedule.