Appendix E - Industry Standards for Const Docs.pdf

PDF 176 KB Posted

Attached to
Design/Build Rebuild Paint and Sandblast Facility at U. S. Coast Guard Base Miami Beach, Miami, FL.
Solicitation number
70Z04720RBASMIA00
Issued by

About this file

This document provides industry standards for construction documents related to a project to rebuild the Paint and Sandblast Facility at U.S. Coast Guard Base Miami Beach in Miami, Florida. The project includes demolishing the existing facility and constructing a new approximately 7,370 square foot Paint and Sandblast Facility, with an option to provide four multi-axis mast lifts, two for each paint and sandblast booth. The document outlines the requirements and level of detail needed for civil, architectural, structural, mechanical, electrical, and fire protection design drawings and calculations to be included in the final design submittal. This includes showing existing conditions and demolition plans, new site plans, floor plans, sections and elevations, schedules, riser diagrams, and other drawings, along with design calculations and coordination between disciplines.

View the file

Other files

File Type Posted
Amendment No. 0004.pdf PDF
10877504 Miami P_SB CAD Files.zip ZIP file
Appendix F - Individual Space Criteria Sheets.pdf PDF
AMENDMENT 0003.pdf PDF
Amendment 0002.pdf PDF
70Z04720RBASMIA00 AMENDMENT 0001.pdf PDF
1 10877504_Miami PSB Facility RFP Drawings.pdf PDF
Attachment A - Geotechnical Reference Documents.pdf PDF
Attachment J - Florida State Clearinghouse Correspondence.pdf PDF
General Wage Determination_FL20200215_Building.pdf PDF
Attachment I - Environmental Planning and Historic Preservation Decision Support System Project Approval.pdf PDF
Site Visit MAP.ppt PPT presentation
10877504_G100.pdf PDF
10877504_C103.pdf PDF
Attachment L - Spill Prevention Control and Countermeasures Plan.pdf PDF
10877504_O110.pdf PDF
Appendix A - ComputerGenDrwgs.pdf PDF
Appendix H - Construction Forms.pdf PDF
Attachment K - Air Emission Operating Permit.pdf PDF
Visitors Access List 70Z04720RBASMIA00.pdf PDF
Attachment H - DHS NEPA Record of Environmental Consideration for CatEx Actions.pdf PDF
Appendix J - Outfitting Items.pdf PDF
SPECIFICATIONS.pdf PDF
Attachment D - Boat Cradle.pdf PDF
10877504_A101.pdf PDF
Appendix B - Electronic Deliverables.pdf PDF
Appendix D - Design Narrative.pdf PDF
10877504_C104.pdf PDF
Appendix C - FDCC Adept File Naming.pdf PDF
10877504_C102.pdf PDF
Attachment F - USCG Base Miami Beach Asbestos Report.pdf PDF
Solicitation 70Z04720RBASMIA00 Final.pdf PDF
Attachment B - Homeporting FRC Miami Beach As-Builts.pdf PDF
Attachment M - Marine Facilities Annual Operating Permit.pdf PDF
Attachment G - USCG Base Miami Beach Lead Based Paint Report.pdf PDF
Attachment E - ICAM Data.pdf PDF
Appendix G - Operation and Maintenance.pdf PDF
Attachment C - Vessel Data 45RBM-601-001.pdf PDF
10877504_C101.pdf PDF
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Base Miami Paint & Sand Blast Facility Project Number: 10877504 USCG Base Miami, FL

Appendix E –Industry Standards 1 of 12 Revised Sept 2010

APPENDIX E

INDUSTRY STANDARDS FOR

CONSTRUCTION DOCUMENTS

Appendix E –Industry Standards 2 of 12 Revised Sept 2010

INDUSTRY STANDARDS FOR CONSTRUCTION DOCUMENTS

Civil Design

Drawings

Record Submittal: The submission should include all drawings required for final design submittal plus all necessary detail sheets to complete the civil engineering portion of the project. In addition, other sheets required showing such information as profiles and cross sections for roads and ditches, profiles of sewer and drainage systems, and details of all appurtenances shall be included. The designer should review all Specifications to be used in connection with the Civil Drawings. Most of the Specifications contain design information in notes that indicate what must be shown on the drawings for proper coordination with the specifications. Some Specifications contain standard details which must be included on the drawings if they are applicable to the project.

Drawings shall be fully coordinated with the other disciplines and the specifications.

Location Plan: Show project location in relation to MAJOR landmarks or features of the installation. Also show the proximity to related facilities which influence project operations. Use insets with an overall view of the station to show widely separated but related facilities. The General Location Plan shall include as much of the activity as necessary to convey meaningful information to someone who has not visited the facility. Show haul routes, borrow areas, disposal areas, laydown and storage areas and plant sites.

This drawing may also serve as a cover sheet and should include a vicinity map. An Index of Drawings is required and may be shown on this drawing.

Existing Site and Demolition Plan and Detail Drawings:

Show the following:

a. All items to be demolished clearly shown

b. Limits of removal

c. Complete description of items to be removed

d. Details, where necessary, of items to be removed

e. Depth and dimension of affected pipelines and foundations

f. Preloading of site

g. Storage areas for materials to be removed

Site Plan and Detail Drawings:

Show the following:

a. Site datum

b. All necessary layout dimensions

c. Street profiles

d. Pavement sections and joint layout and details

e. Handicapped provisions details

f. Parking and other pavement markings

g. Curb and gutter details

h. Walk details

i. Equipment pads

j. Temporary facilities, locations and services

k. Pavement repair details (i.e. utility crossings)

l. Guard post details

m. Fencing and gates location and details including security barriers for openings beneath fences and gates

n. Wheel stop details

o. Construction limits (if critical)

p. All existing aboveground features which are not to be demolished

q. Street sign details

Appendix E –Industry Standards 3 of 12 Revised Sept 2010

Grading and Storm Drainage Plans and Detail Drawings:

a. Existing and finish contours

b. Existing and finish spot elevations

c. Ditch profiles and sections

d. Erosion protection

e. Storm drainage piping layout, new and existing including security barriers

f. Storm drainage structure details including security barriers

g. Slopes and inverts of all pipes and profiles where necessary

h. Inverts and top elevations of all structures

i. Frames, grates and covers details

j. Class or gauge of pipe

k. Clearing and grubbing limits

l. Grassing limits

m. Benchmark information

n. SWM details

Utility Plans and Detail Drawings:

a. Overall layout of systems, showing line sizes

b. New and existing systems shown

c. Valve and fire hydrant locations

d. Trench details showing bedding, backfill and utility warning tape

e. Sizes of all components of systems indicated

f. Building services coordinated with building plumbing drawings

g. Separation of water and sewer lines

h. Back-flow preventers

i. Manhole spacing and details (including top and invert elevations)

j. Clean-out location

k. Pipeline profiles (gravity sewers normally, plus force main when required by State Permitting

Agency)

l. Manhole, frames and cover details

m. Pump station location and details

n. Air release valves location and details

o. Locations coordinated with existing and other utilities

p. Areas of hazardous material abatements

Calculations

Design Calculations: Revise the Schematic calculations and supplement as required for 100% design. Submit in same format as for Schematic submittal.

Computer outputs: Shall be identified similar to the calculations and may be referenced as an appendix or attachment

Appendix E –Industry Standards 4 of 12 Revised Sept 2010

Architectural Design

Record Submittal: The submission should include all drawings required for the final design submittal plus all necessary detail sheets to complete the architectural portion of the project. Drawings shall be fully coordinated with the other disciplines and the specifications.

Architectural Floor Plans:

Floor Plans Showing:

a. Complete dimensions.

b. Spaces labeled with doors and windows numbered and door swings indicated.

c. Enlarged plans/elevations/sections and details cross referenced per MIL-HDBK-1006/1

Reference Symbol guidance.

d. Wall and partition thickness, secure area partition type, partitions that extend to overhead structure, fire and acoustical rated partitions (show rating). Reference symbols for each related section/detail.

e. Water coolers, janitor sinks, floor drains, fire extinguisher cabinets, access ladders and hatches, "walk-off" mats in exterior entrances, public phones, signage directories, and built-in shelving and equipment.

f. Wall and floor expansion/crack control joints.

g. Boundaries of floor finish material changes and floor level transitions.

h. Ramps, steps, and stairs.

i. Necessary notes and schedules (use Key Notes for labels where practical).

j. Key Plans when an entire floor is not shown on a single sheet. Exterior Elevation reference symbols may be shown on Key Plan.

k. Clear designation between new and existing work.

l. Limits of demolition and hazardous material removal.

Reflected Ceiling Plans:

Reflected Ceiling Plans at same scale as floor plans showing:

a. All ceiling types (identified by note or legend) and acoustical ceiling tile grid(s).

b. Junctions of different ceiling finishes and ceiling level changes.

c. All partitions with fire walls and security/acoustical partitions which extend to structure above noted.

d. HVAC diffusers and returns.

e. Light fixtures.

f. Access Panels.

g. Ceiling mounted signage.

h. All required notes.

Roof Plans: Roof Plans showing:

a. Roof layout with all pertinent dimensions.

b. Parapet walls, expansion joints, crickets, overflow scuppers, roof drains, gutters, and downspouts.

c. Direction of roof slope and amount of slope (minimum 1/2" per foot desired). All valleys shall have positive slope.

d. All roof mounted equipment (coordinated with structural, mechanical, and electrical drawings). Mount air terminals (lighting rods) on parapet terminals.

e. All roof penetrations, vents, exhausts, skylights, monitors, and access hatches.

f. Reference symbols for wall sections, building sections, and details.

g. All necessary notes.

Appendix E –Industry Standards 5 of 12 Revised Sept 2010

Enlarged Floor Plans: Enlarged Floor Plans showing:

a. Enlarged toilet plans at 1/2" = 1'-0" with toilet fixtures (handicapped accessible and regular types) and toilet accessories labeled and special handicapped access clearances indicated.

b. Kitchen layout with dimensions and equipment.

c. Stairs with runs and widths, landings, and railings dimensioned.

d. All necessary notes.

Elevations:

Architectural Elevations showing:

a. All sides of building with vertical dimensions and floor level elevations.

b. All finish materials and special requirements labeled.

c. Expansion and crack control joints.

d. Exterior doors.

e. Windows with operating sash indicated.

f. Exhaust fans, louvers, and grills.

g. Gutters, downspouts, splash blocks, and overflow scuppers.

h. Roof mounted equipment, exhaust stacks, and antennas.

i. Reference symbols for section and detail cuts.

j. All necessary notes.

Building Sections: Building Sections (same scale as Architectural Floor Plans, when practical) showing:

a. Floor, wall, partition, ceiling, and roof information for a minimum of one transverse and one cross section through entire building.

b. Reference symbols for section and detail cuts.

c. Doors, windows, finish materials, expansion joints, casework, toilet partitions, ladders, and signage.

d. Lighting, HVAC registers and returns, built-in equipment

Interior Elevations: Interior Elevations/Sections showing:

a. Toilets with fixtures, vanities, partitions, finishes, and accessories with labels and reference symbols.

b. Kitchen/food preparation area with equipment outlined, electrical outlets and switches at proper heights, fire extinguishers, alarm bells/horns, and HVAC equipment and registers/ returns.

c. Janitor closets with shelving, wall hooks, and built-in equipment.

d. Stairs with dimensioned railings, treads, risers, nosings, and framing.

Wall Sections, Sections, and Details showing:

Wall Sections, Sections, and Details showing:

a. All sections and details (including flashing, drip moldings, weepholes, vents, etc.) necessary for construction.

b. Sections at minimum scale of 3/4"= 1'-0".

c. Isometric details for each roof flashing condition at minimum scale of 3"= 1'-0" and with all applicable notes.

d. Isometric detail of scuppers showing all flanges.

e. Joint covers for metal coping covers and gravel stops.

f. Roof crickets.

g. Wall and roof insulation with “R-values”.

h. Door and window frame “head, jamb, and sill” details. Also astragals, weatherstripping, thresholds, floor level changes (such as at entrances), and physical security features.

i. Toilet partition, shower pan, floor/roof/ balcony drains, and waterproofing details.

j. Expansion joints, crack control joints for stucco/brick/cmu/concrete/ceramic tile/plaster, and joints between different finish materials.

k. Stair/balcony railings and mounting brackets, wall-mounted doorstop bracing, vanity bracing, locker/ weapons rack mounts, curtain wall/ large window protective railings, and partition corner/corridor wall bumpers.

l. Signage construction and method of mounting.

m. Necessary notes.

n. Titles referenced by Reference Symbol convention to Plans, Elevations, and Building Sections.

Appendix E –Industry Standards 6 of 12 Revised Sept 2010

Schedules: Schedules showing:

a. Doors and frames with fire and acoustical rating, physical security feature notes, and detail reference numbers.

b. Windows with frame material, glazing type, fire and acoustical rating, physical security feature notes, and detail reference numbers.

c. Louvers with frame, vane operation, fire rating, physical security feature notes, and detail reference numbers.

d. Interior finish materials for floor, base, walls, wainscot and ceiling with ceiling height. built-in cabinet finishes, window blinds, toilet partitions, bulletin boards and any other visible item attached to the building interior. Finishes for Systems Furniture shall be included. Also include exterior finish materials and color.

e. Signage with frame, mounting, letter style and height, finish, color, text, and location information.

f. Equipment.

Appendix E –Industry Standards 7 of 12 Revised Sept 2010

Structural Design

Record Submittal: The submission should include all drawings required for the final design submittal plus all necessary detail sheets to complete the structural portion of the project. Drawings shall be fully coordinated

General Conditions:

Show the following:

a. Design criteria for loads, materials, and references,

b. General notes for the project,

c. Material notes such as structural steel, concrete, masonry, etc.,

d. Bid information such as pile/caisson lengths,

e. Special load test requirements,

f. Special inspections requirements

g. Other information/instructions to contractor,

h. Abbreviations and symbols used for structural drawings.

Foundation Plan: Show the following:

a. Layout of foundation support systems showing all dimensions and elevations necessary for construction,

b. Size or schedule references for all foundation features such as footings, grade beams, piles, caissons, pile/caisson caps, etc.,

c. Control/expansion joints in floor slab and foundation walls,

d. Trenches, pits, openings, depressed/ thickened slabs,

e. Test pile/caisson location,

f. Special construction features - de-watering, excavation, bracing, under-pinning, etc.,

g. Special construction sequencing,

h. Existing site conditions/features,

i. North arrow (orient plans so that north is to the top or left of the sheet),

j. Graphic scales.

Framing Plans Show the following:

a. Layout of horizontal framing elements showing all dimensions, orientation and elevations necessary for construction – Elevations shall be referenced to some finished datum such as top of steel, slab, finished floor, concrete, etc.

b. Size or schedule references for all horizontal framing elements such as beams, joists, slabs, decks, grating, etc.,

c. Slab control/expansion joints,

d. Openings requiring special framing or reinforcing,

e. Location of splices, brackets, penetrations, sleeves, embedments, bracing, weldments, etc.,

f. Special temporary bracing, shoring or forming,

g. Other special requirements, such as equipment clearances, travel distances for hoists and cranes, etc.,

h. North arrow (orient plans so that north is to the top or left of the sheet),

i. Graphic scales.

Appendix E –Industry Standards 8 of 12 Revised Sept 2010

Elevations Show the following:

a. Layout of vertical framing elements showing all dimensions, orientations and elevations necessary for construction – reference elevations shall be consistent with framing plans.

b. Size or schedule references for all vertical framing elements such as column, walls, piers, beams, bracing, etc.,

c. Wall control/expansion joints,

d. Openings requiring special framing or reinforcing

e. Location of splices, brackets, penetrations, sleeves, embedments, bracing, weldments, etc.,

f. Special temporary bracing, shoring or forming,

g. Other special requirements such as equipment, clearances, travel distances for hoists and cranes, etc.,

h. Graphic scales.

Sections and Details:

a. Layout of all sections and details showing all parts, shapes, sizes, materials, dimensions, elevations, arrangement and orientation necessary for construction,

b. Standard connections or schedule references for forces, fasteners, welds, plates, clips, ties stirrups, pins, etc.,

c. All special connections completely detailed to a point where no further engineering is necessary,

d. Concrete/masonry wall reinforcement details showing size, clearances, placement, shape, etc.,

e. Lintel details or schedule references for loads, sizes, materials, arrangement, etc.,

f. Anchor bolts, base plates, bearing plates, or schedule reference for materials, size, thickness, welds, embedments, threaded parts, projections, etc.,

g. Diaphragm deck type, gauge, yield strength, minimum number of spans or length, fastener type and pattern,

h. Applicable special notes and instructions,

i. Graphic scales.

Structural Notes and Schedules:

a. Provide all information/instructions for fabrications, forming, placement, erection, installation, etc. necessary for construction.

b. Schedules for beams, lintels, joist, trusses, frames, piles, caissons, footings, pile/caisson caps, grade beams, slabs, etc.

c. Calculated column loads, beam shear/reaction and moments, footing pressures, pile/caisson capacities/loads (vertical and horizontal) etc.

d. Special instructions, materials, process, etc.

Other Drawings: a. Layout of structural systems for special fabrications and construction such as space trusses/frames, long span trusses, Vierendeel trusses, shells, towers, etc.

b. Temporary structures to be dismantled/relocated

Calculations: Calculations shall include the analysis and design of all (major cost contributing elements) beams, columns, walls, foundations, slabs, bracing, diaphragms, equipment supports, etc. and the connections to each other to provide a safe, stable, efficient and cost effective structural system. An adequate number of sketches with sufficient detail to make the designers intentions clear, concise and easily understandable shall be provided. All assumptions and references to codes, standards, criteria, drawings and computer outputs shall be noted as necessary.

Appendix E –Industry Standards 9 of 12 Revised Sept 2010

Mechanical Design

Submittal: The submission should include all drawings required for the final design submittal plus all necessary detail sheets to complete the mechanical portion of the project. Drawings shall be fully coordinated

General: Mechanical floor plans shall be not less than 1/8”=1’-0”. Floor plan scales of 1/4”=1’-0” should be considered when the complexity of the work results in overcrowding of the drawings, such as in mechanical room layout and in the design of hospitals.

Drawings: a. HVAC Floor Plans showing the location of major equipment and ductwork. All ductwork shall be shown double line, to scale.

b. Plumbing Floor Plans showing potable water, DWV, compressed air, etc.

c. HVAC and plumbing riser diagrams.

d. HVAC and plumbing equipment schedules, showing sizes of major equipment.

e. HVAC Design Conditions Schedule including tolerances of inside temperatures and relative humidities.

f. Basic HVAC control diagrams and written sequence of control.

g. Site layout showing points of utility connections, including sewer invert elevations at the five foot line.

h. Exterior piping including chilled/hot water, condenser water, plumbing/ sanitary, steam, fuel, compressed air and gas piping, etc.

i. Equipment locations.

j. Fuel storage general arrangement.

k. Roof Plans showing locations of equipment and ductwork

l. Large Scale Plans as need to show congested areas

m. Sections, elevations and details as required for MEP coordination

n. Control Diagrams and written sequence of control

o. Legends

p. HVAC equipment and Plumbing Fixture Schedules

q. Notes

r. Design Conditions

General: Corrected to include all previous submittal review comments and/or a clear statement why the review comment was not complied with.

Appendix E –Industry Standards 10 of 12 Revised Sept 2010

Fire Protection Design

Submittal: The submission should include all drawings required for the final design submittal plus all necessary detail sheets to complete the fire protection portion of the project. Drawings shall be fully coordinated with the other disciplines and the specifications.

Civil Drawings: a. Show all new and existing water piping including sizes.

b. Show new and existing valve and fire hydrant locations ensuring conformance with MIL-HDBK-

1008-B.

c. New valve and fire hydrants shall require an installation detail complete with guard posts.

d. Show the water line supplying the sprinkler riser with the connection into the building.

e. Show the location of any required fire pump or water storage tank.

Drawings:

a. Clearly show with details the location and rating of smoke and firewalls. Clearly indicate the specific hourly fire rating.

b. A detail of the fire and smoke wall construction must be provided along with the particular Underwriters' Laboratories listing obtained from the latest edition of the U.L. Fire Resistance Directory.

c. Provide details of any fire wall penetration for each type of wall construction, as outlined in the U.L. Building Materials Directory.

d. Detail type and size of fire extinguisher to be provided. Base Fire Department should be contacted for further information.

e. Provide the class and hour rating of fire doors on the door schedule.

Mechanical Drawings: a. The location of sprinkler riser must be shown on the plumbing floor plan with a detail of the sprinkler riser also provided. (Note: Sprinkler piping layout is not shown)

b. Show any CO2 banks or clean agent tanks with a detail of the areas protected and a riser diagram.

c. Show the location of smoke and fire dampers with a detail.

d. Provide the physical layout of the fire pump and associated piping.

e. Show, on the HVAC Drawings, any required duct mounted smoke detectors and intertie to shut down system when an alarm is triggered.

f. Provide a fire stopping detail for penetrations of firewalls with reference.

Appendix E –Industry Standards 11 of 12 Revised Sept 2010

Mechanical Drawings: a. The existing base wide fire alarm system must be determined. If an exterior master box is required, the location must be shown. A detail of the master box pedestal must also be provided.

b. All fire alarm and suppression devices, including control panel, manual pull stations, automatic detectors, extinguishing system pressure switches, and audible devices, shall be located on an electrical floor plan.

c. A fire alarm riser and suppression system diagram showing the interconnection of all fire alarm equipment is required. Ensure the power supply and point of connection to base wide fire alarm is shown. (Note: Source of power to fire alarm control panel shall be taken prior to the main power disconnect.)

d. Emergency lighting locations shall be provided on the electrical floor plan with a detail of each type of emergency light fixture provided.

e. The fire alarm zone, suppression, and annunciation schedule shall be detailed. Complex fire alarm systems such as jet engine test cells and hush houses, aircraft hangars, etc. shall require a chart detailing a sequence of operations.

f. Fire stop details of electrical penetrations of fire wall with a note referring to the appropriate architectural sheet for fire wall location.

General Provide corrections to comments on previously reviewed calculations.

Appendix E –Industry Standards 12 of 12 Revised Sept 2010

Electrical and Telecommunications Design

Submittal: The submission should include all drawings required for the final design submittal plus all necessary detail sheets to fully present the scope of the electrical work required for the project. Drawings shall be fully coordinated with the other disciplines and the specifications.

Existing Site and Demolition Plan:

This drawing shall include all existing site information such as buildings, pavements and utilities that affect the demolition of the electrical portions of the project. The specifications should indicate the disposition of demolished materials and equipment. The limits of demolition must be clearly defined, i.e., if a portion of overhead line is to be removed, provide a detail showing how the remaining portion is to be terminated.

Site Plan and Details: This drawing shall show all new and existing aboveground and underground features such as buildings, pavements and utilities that affect or interface with the electrical portions of the project. As a minimum the following information shall be shown:

a. Primary and secondary electrical lines

b. Fire alarm and communications lines

c. Transformer or substation (located by dimensions from the building or other prominent feature)

d. Streets, parking area and other flood lighting

e. All other exterior electrical equipment, such as M.G. sets, A/C units, etc.

f. In congested areas a profile of duct lines may be required.

g. Site details (light pole bases, transformers pads, trench details)

Lighting Plans and

These drawings shall show the building's full floor plan (first, second, etc.) with the location and number of lighting fixtures, including the type and size of wiring serving these fixtures. Provide details of all lighting fixtures used, including mounting height and support details. Emergency, exit, and security lighting shall be included where required. Seismic restraint of fixtures shall be shown where required.

Power Plans and

These drawings shall show a building's full floor plan (first, second, etc.) as well as any large-scale plans necessary to prevent overcrowding. The power plans should show the location of receptacles and electrical equipment and the type, size and location of wiring required throughout the facility.

Riser Diagrams: All of the following:

a. Power - Single Line Diagram

b. Communications Plan

c. Telephone Riser Diagram

d. Computer network riser diagram and plan

e. Other Riser Diagrams for Television, Paging, IDS, etc.

f. Panel Schedules

g. Switchboards and Motor Control Center Schedules

h. Lighting Fixture Details

General: Corrected to include all previous submittal review comments or a clear statement why the review comment was not complied with.