Appendix_6_FDOT_Preliminary_Engineering_Certification_Memo_03-6-2026.pdf
PDF 210 KB Posted
- Attached to
- Ridgemoor Blvd and Brooker Creek at Brooker Creek Bridge #154153 Bridge Replacement Project (PID 005749A)
- Solicitation number
- 26-0506-ITB-C
- Issued by
- Pinellas County, Clewiston City, Florida
About this file
This is a Preliminary Engineering Certification Memorandum from the Florida Department of Transportation (FDOT) to certify the completion of preliminary engineering (design) for a federal aid project in Pinellas County. The project involves the replacement of the Ridgemoor Boulevard Bridge over Brooker Creek, which will replace the existing 120-foot flat slab bridge with a 135-foot structure and include related roadway and drainage improvements. The preliminary engineering was funded through both state funds under Financial Project ID 445437-1-58-01 and federal funds authorized under Federal Aid No. D725-007-B. The memorandum, dated March 6, 2026, indicates that the preliminary engineering phase is open and will be closed after PS&E (Plans, Specifications, and Estimates) authorization.
The project is a federally funded Local Agency Program (LAP) administered through FDOT, with the project manager contactable at (813) 975-6164. The preliminary engineering certification is issued by Design Project Manager Eyra Cash and Federal Aid Programs Manager Sabrina Aubery. Additional related projects designed with the same preliminary engineering funds are identified under Financial Project IDs 445437-1-32-01, with corresponding Federal Aid Nos. D722-047-B. The preliminary engineering will remain closed for additional charges, and the financial project ID will remain open for other projects as needed. The Proposal/Contract ID is T7556.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MEMORANDUM
DATE:
TO: , Federal Aid Programs Manager
FROM: , Design Project Manager
COPIES:
SUBJECT: PRELIMINARY ENGINEERING CERTIFICATION (Federal Aid Projects Only)
Financial Project ID Proposal/Contract ID Federal Aid No.
County Project Description
Preliminary Engineering (design) was funded with:
State Funds under Financial Project ID Federal Funds authorized under, Federal Aid No.
Financial Project ID
The following projects, designed with the same Preliminary Engineering funds, will be strung to (awarded with) the subject project:
Federal Aid No. , Financial Project ID , Federal Aid No. , Financial Project ID .
The Preliminary Engineering for the subject project is open/ closed. If open, it will be closed after PS&E authorization, or it is a district wide project. Task order number for this project is closed.
The financial number will be open for other projects.
it will remain open for additional charges, as follows:
The FDOT Project Manager may be contacted at (phone):
Preliminary Engineering Certification Form 132
Form 132
| DATE: 3/6/26 |
| Name of Federal Aid Programs Manager: Sabrina Aubery |
| Name of Design Project Manager: Eyra Cash |
| COPIES: File |
| Financial Project ID: 445437-1-58-01 |
| ProposalContract ID: T7556 |
| Federal Aid No 1: D725-007-B |
| Federal Aid No 2: Pinellas |
| Project Description: RIDGEMOOR BLVD AND BROOKER CREEK AT BROOKER CREEK BRIDGE #154153 |
| State Funds: Yes |
| Financial Project ID_2: 445437-1-32-01 |
| Federal Aid No: D722-047-B |
| Financial Project ID_3: 445437-1-32-01 |
| Federal Aid No_2: |
| Financial Project ID_4: |
| Federal Aid No_3: |
| Financial Project ID_5: |
| PE is: Open |
| Preliminary Engineering Closed after PS&E: Yes |
| Preliminary Engineering a district wide project: Off |
| Task Order number: |
| Preliminary Engineering will remain open for additional changes: Off |
| Additional changes1: |
| Additional changes2: |
| FDOT Project Manager Phone: (813) 975-6164 |
| Federal Funds_1: Yes |