Appendix_5_UWS_Frontier.pdf
PDF 353 KB Posted
- Attached to
- Ridgemoor Blvd and Brooker Creek at Brooker Creek Bridge #154153 Bridge Replacement Project (PID 005749A)
- Solicitation number
- 26-0506-ITB-C
- Issued by
- Pinellas County, Clewiston City, Florida
About this file
This is a Utility Work Schedule developed by the Florida Department of Transportation (FDOT) for Frontier Florida LLC in coordination with the Ridgemoor Boulevard Bridge Replacement Project in Pinellas County, Florida. The schedule outlines the relocation and adjustment of Frontier's telecommunications utilities to accommodate the bridge replacement project over Brooker Creek. Frontier's work consists of two primary phases: 79 calendar days of utility work prior to FDOT project construction and 21 calendar days during construction. The activities include installing a proposed 30x60 hand hole and temporary 4-inch duct, splicing temporary cables, removing old cables and conduits, placing new conduits with cables into customer-provided hand holes, and removing temporary infrastructure. Key activities have dependent relationships, with material procurement and engineering/permitting each requiring 30 days following Notice to Proceed.
The utility work schedule is based on FDOT plans dated February 10, 2025, and was executed on February 19, 2026. Frontier's point of contact is Tony Wheeler (Project Representative) and Vince Theodosis (Field Representative). Frontier operates under normal business hours of 8:00 AM to 5:00 PM, Monday through Friday, with any work outside these hours requiring a minimum 72-hour advance notice. Frontier requires 60 days for engineering, budget approval, material procurement, and permitting before construction for conflict resolution. The utility agency must obtain a utility permit and comply with the 2017 Utility Accommodation Manual requirements. The schedule was approved by FDOT District Utilities Administrator Erin Long and attested by Engineer of Record Timothy Wineberg, P.E. Frontier is entitled to access throughout the project duration to monitor and protect its facilities and maintain service capability.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rule 14-46.001 F.A.C
FLORIDA DEPARTMENT OF TRANSPORTATION
UTILITY WORK SCHEDULE
December 14, 2016
Pursuant to Section 337.403 F.S., the UAO and FDOT agree to the UAO’s need for relocation or adjustment to its utilities and FDOT’s need for a schedule for the UAO to effect the relocation or adjustment. This utility work schedule is based on FDOT plans dated in the project information box below. Any deviation by FDOT or its contractor from these plans, may void this utility work schedule. Upon notification by FDOT of a change to these plans, the UAO may negotiate a new utility work schedule. The UAO agrees to notify FDOT and the contractor in writing prior to starting, stopping, resuming, and completing work in accordance with this utility work schedule. The UAO shall obtain a utility permit and comply with requirements of the 2017 Utility Accommodation Manual (UAM) for all work done under this utility work schedule. The UAO is not responsible for events beyond the control of the UAO that could not be reasonably anticipated by the UAO and which could not be avoided by the UAO with exercise of due diligence at the time of the occurrence.
FDOT PROJECT INFORMATION
Financial Project ID: 445437-1-52-01 Federal Project ID: N/A
State Road Number: N/A (Ridgemoor Blvd) County: Pinellas
FDOT Plans Dated: 02/10/2025 District Document No.: N/A
UTILITY AGENCY/OWNER (UAO)
Utility Company: Frontier Florida LLC
UAO Project Rep: Tony Wheeler Phone: 727-359-1754 E-mail: tony.wheeler1@ftr.com
UAO Field Rep: Vince Theodosis Phone: 727-942-8326 E-mail: steve.theodosis@ftr.com
UTILITY SIGNATURE
I have reviewed the FDOT plans referenced above and submit this utility work schedule in compliance with UAM Section 5 and agree to be bound by the terms of this utility work schedule.
UAO Rep. Date 2 / 19 / 2026
Name Scott Hand
Title Network Engineer
ENGINEER OF RECORD SIGNATURE
I attest this utility work schedule is compatible with the FDOT plans referenced above.
EOR. Date / /
Name Timothy Wineberg, P.E.
Title Engineer of Record
APPROVAL BY DISTRICT UTILITIES
This utility work schedule is complete and acceptable to FDOT.
FDOT Rep. Date / /
Name Erin Long
Title District Utility Administrator
SECTION A: SUMMARY OF UTILITY WORK
The below days are the total numbers of days shown for all activities in Section C of this utility work schedule. The breakdown of how these days are to be incorporated into the FDOT project and the dependence of these days upon the completion of other activities by the UAO or others is shown in Section C.
Days prior to FDOT project construction: 79 Days during FDOT project construction: 21
Timothy P Wineberg
2026.02.24 13:58:26-05'00'
Docusign Envelope ID: 50010B39-2791-4760-9CAF-F4BD1FE4F53C
02/25/2026 | 9:05 AM EST
FLORIDA DEPARTMENT OF TRANSPORTATION
Financial Project ID: 445437-1-52-01
Utility Company: Frontier Florida LLC
FDOT Plans Dated: 02/10/2025
SECTION B: UAO SPECIAL CONDITIONS/CONSTRAINTS
Frontier and Frontier Contractors' normal business hours are from 8am to 5pm, Monday through Friday. (excluding Holidays)
Any work outside of normal business hours to be scheduled a minimum of 72 hours in advance.
Frontier inspector is to be the point of contact during construction and to be notified when working within 2' of Frontier faculties. Vince
Theodosis 727-942-8326 steve.theodosis@ftr.com
Frontier is to have access throughout the duration of the project to monitor, hold guard and protect facilities for the ability to provide service.
Frontier requires 60 days for Engineering, budget approval, material procurement and permitting before construction for conflict resolution.
Adjusting- To hand dig with shovel or small excavator to move Frontier facility horizontally or vertically to clear conflict.
The abbreviation "CPC" noted in Section C refers to "customer provided conduit"
FLORIDA DEPARTMENT OF TRANSPORTATION
FDOT Plans Dated: 02/10/2025
SECTION C: UAO’s WORK ACTIVITIES
Act.
No.
Utility Facility
(type, size, material, status)
From
Station/
Offset
To
Station/
Offset
Utility Work Activity
Description
Dependent
Activity TCP Phase
Consecutive
Calendar Days
Prior to During
Const. Const.
1 FTR (1) 30X60 HH
585+25, 64’ LT
585+28, 64’ LT
PROPOSED 30X60
HH TO BE PLACED
PRIOR TO CONST.
NTP
PRIOR TO
CONST
1 N/A
2 FRT (1) 4” DUCT
585+25
74’ LT
591+45, 74’ LT
PROPOSED
TEMPORARY 4”
DUCT W/ FOC & BT
PLACED PRIOR TO
CONST. OUTSIDE
CONST AREA
NTP
PRIOR TO
CONST
4 N/A
FTR SPLICING
TEMPORARY
CABLES
SPLICING
TEMPORARY
CABLES
NTP
PRIOR TO
CONST
10 N/A
FTR CONDUITS &
CABLES
585+25
74’ LT
591+45, 74’ LT
REMOVING OLD
CABLES &
CONDUITS
Activity 3 complete & activated
PRIOR TO
CONST
4 N/A
FTR (2) 4” CONDUIT
W/CABLES
585+25, 64’ LT
587+85
30’ LT
PLACING DUCT TO
CUSTOMER
PROVIDED HH
CPC & HH
PLACEMENT
PH IV N/A 3
FTR (2) 4” CONDUIT
W/CABLES
589+15, 31’ LT
591+25, 51’ LT
PLACING DUCT TO
CUSTOMER
PROVIDED HH
CPC & HH
PLACEMENT
PH IV N/A 4
FTR PLACING
FACILITIES IN CPC &
FTR CONDUIT
585+25, 64’ LT
591+45, 64’ LT
PLACE IN CPC 4”
DUCT ATTACHED
TO BRIDGE
CPC COMPLETED PH IV N/A 2
FTR TO SPLICE NEW
FACILITIES
SPLICING NEW
FACILITIES
Activities 6 & 7 completed
PH IV N/A 5
FLORIDA DEPARTMENT OF TRANSPORTATION
FDOT Plans Dated: 02/10/2025
SECTION C: UAO’s WORK ACTIVITIES
Act.
No.
Utility Facility
(type, size, material, status)
From
Station/
Offset
To
Station/
Offset
Utility Work Activity
Description
Dependent
Activity TCP Phase
Consecutive
Calendar Days
Prior to During
Const. Const.
FTR REMOVE BT,
BFOC AND CONDUIT
585+25
74’ LT
591+45, 74’ LT
REMOVAL OF
TEMPORARY
CONDUIT AND
CABLES
COMPLETION OF
SPLICING
PH IV 0 7
FTR MATERIAL
PROCUREMENT
NTP 30 N/A
ENGINEERING /
PERMITTING
NTP 30 N/A