Appendix_5_UWS_Frontier.pdf

PDF 353 KB Posted

Attached to
Ridgemoor Blvd and Brooker Creek at Brooker Creek Bridge #154153 Bridge Replacement Project (PID 005749A)
Solicitation number
26-0506-ITB-C
Issued by
Pinellas County, Clewiston City, Florida

About this file

This is a Utility Work Schedule developed by the Florida Department of Transportation (FDOT) for Frontier Florida LLC in coordination with the Ridgemoor Boulevard Bridge Replacement Project in Pinellas County, Florida. The schedule outlines the relocation and adjustment of Frontier's telecommunications utilities to accommodate the bridge replacement project over Brooker Creek. Frontier's work consists of two primary phases: 79 calendar days of utility work prior to FDOT project construction and 21 calendar days during construction. The activities include installing a proposed 30x60 hand hole and temporary 4-inch duct, splicing temporary cables, removing old cables and conduits, placing new conduits with cables into customer-provided hand holes, and removing temporary infrastructure. Key activities have dependent relationships, with material procurement and engineering/permitting each requiring 30 days following Notice to Proceed.

The utility work schedule is based on FDOT plans dated February 10, 2025, and was executed on February 19, 2026. Frontier's point of contact is Tony Wheeler (Project Representative) and Vince Theodosis (Field Representative). Frontier operates under normal business hours of 8:00 AM to 5:00 PM, Monday through Friday, with any work outside these hours requiring a minimum 72-hour advance notice. Frontier requires 60 days for engineering, budget approval, material procurement, and permitting before construction for conflict resolution. The utility agency must obtain a utility permit and comply with the 2017 Utility Accommodation Manual requirements. The schedule was approved by FDOT District Utilities Administrator Erin Long and attested by Engineer of Record Timothy Wineberg, P.E. Frontier is entitled to access throughout the project duration to monitor and protect its facilities and maintain service capability.

View the file

Other files

File Type Posted
Ridgemoor_Blvd_and_Brooker_Creek_at_Brooker_Creek_Bridge_#154153_Bridge_Replacement_Project_(PID_005749A)_(Addendum_#1_Revision).pdf PDF
Ridgemoor_Blvd_and_Brooker_Creek_at_Brooker_Creek_Bridge_#154153_Bridge_Replacement_Project_(PID_005749A).pdf PDF
Appendix_6_Geotechnical_Exploration_–_Structures_Report_03-05-2026.pdf PDF
Appendix_5_UWS_Pinellas_County_Utilities.pdf PDF
Appendix_6_FDOT_Right_of_Way_Certification_Memo_12-10-2025.pdf PDF
Appendix_6_FDOT_Engineering_“No-Rise”_Certification_Memo_11-12-2025.pdf PDF
PLANS_-_Sediment_and_Erosion_Control.pdf PDF
Appendix_6_Construction_Project_Requirements_Memo_02-27-2026.pdf PDF
Appendix_6_FDOT_Spectrum_Clear_Letter_3-27-2026.pdf PDF
Appendix_5_UWS_Clearwater_Gas.pdf PDF
Appendix_5_UWS_MCI_Metro_Access_Transmission_Services.pdf PDF
Appendix_6_FDOT_Environmental_Certification_Memo_01-30-2024.pdf PDF
Appendix_4_-_Special_Notices_6.23.pdf PDF
Appendix_6_FDOT_Preliminary_Engineering_Certification_Memo_03-6-2026.pdf PDF
Appendix_5_UWS_Duke.pdf PDF
Appendix_6_FDOT_WOW_Clear_Letter_8-2-2024.pdf PDF
Appendix_6_FDOT_Permit_Certification_Memo__02-24-2026.pdf PDF
Appendix_6_FDOT_Environmental_Certification_Memo_02-5-2026.pdf PDF
Appendix_6_FDOT_Utility_Certification_Memo_02-25-2026.pdf PDF
Appendix_6_FDOT_Railroad_Certification_Memo_12-19-2025.pdf PDF
PLANS_-_ROADWAY.pdf PDF
PLANS-STRUCTURES.pdf PDF
Sample_Performance_and_Payment_Bonds_26-0506.pdf PDF
Section_7_-_County_Specifications.pdf PDF
FDOT_Specifications_Package.pdf PDF
APPENDIX_1-Permits_.pdf PDF
Sample_Application_for_Payment.pdf PDF
Sample_Change_Order.pdf PDF
QUALIFICATION-SUBMITTAL-FORM_FDOT.pdf PDF
Affdavit_of_Release_and_Guarantee.pdf PDF
Pricing_Proposal_ITB_26-0506(reference_only).pdf PDF
OpenGov_Fillable-_Final.pdf PDF
E-Verify_Affidavit.pdf PDF
Florida_Trench_Safety_Form.pdf PDF
Appendix_1-Permits_.pdf PDF
Sample_Agreement-26-0506.pdf PDF
2025_Pinellas_County_Supplemental_Specifications_.pdf PDF
SBE_Compliance_Form.pdf PDF
QUALIFICATION_SUBMITTAL_FORM_4-26-2026.pdf PDF
FDOT_Division_Specification_(FY2026-27)-ebook(signed)_(For_Legistar_only).pdf PDF
Airport_Security_Program.pdf PDF
Bid_Submittal_Form-JOC.pdf PDF
Pricing_Proposal_(for_Review_Only).xlsx XLSX spreadsheet
Non-Competitive_Oversight_Committee_Justification_Form.docx DOCX document
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Rule 14-46.001 F.A.C

FLORIDA DEPARTMENT OF TRANSPORTATION

UTILITY WORK SCHEDULE

December 14, 2016

Pursuant to Section 337.403 F.S., the UAO and FDOT agree to the UAO’s need for relocation or adjustment to its utilities and FDOT’s need for a schedule for the UAO to effect the relocation or adjustment. This utility work schedule is based on FDOT plans dated in the project information box below. Any deviation by FDOT or its contractor from these plans, may void this utility work schedule. Upon notification by FDOT of a change to these plans, the UAO may negotiate a new utility work schedule. The UAO agrees to notify FDOT and the contractor in writing prior to starting, stopping, resuming, and completing work in accordance with this utility work schedule. The UAO shall obtain a utility permit and comply with requirements of the 2017 Utility Accommodation Manual (UAM) for all work done under this utility work schedule. The UAO is not responsible for events beyond the control of the UAO that could not be reasonably anticipated by the UAO and which could not be avoided by the UAO with exercise of due diligence at the time of the occurrence.

FDOT PROJECT INFORMATION

Financial Project ID: 445437-1-52-01 Federal Project ID: N/A

State Road Number: N/A (Ridgemoor Blvd) County: Pinellas

FDOT Plans Dated: 02/10/2025 District Document No.: N/A

UTILITY AGENCY/OWNER (UAO)

Utility Company: Frontier Florida LLC

UAO Project Rep: Tony Wheeler Phone: 727-359-1754 E-mail: tony.wheeler1@ftr.com

UAO Field Rep: Vince Theodosis Phone: 727-942-8326 E-mail: steve.theodosis@ftr.com

UTILITY SIGNATURE

I have reviewed the FDOT plans referenced above and submit this utility work schedule in compliance with UAM Section 5 and agree to be bound by the terms of this utility work schedule.

UAO Rep. Date 2 / 19 / 2026

Name Scott Hand

Title Network Engineer

ENGINEER OF RECORD SIGNATURE

I attest this utility work schedule is compatible with the FDOT plans referenced above.

EOR. Date / /

Name Timothy Wineberg, P.E.

Title Engineer of Record

APPROVAL BY DISTRICT UTILITIES

This utility work schedule is complete and acceptable to FDOT.

FDOT Rep. Date / /

Name Erin Long

Title District Utility Administrator

SECTION A: SUMMARY OF UTILITY WORK

The below days are the total numbers of days shown for all activities in Section C of this utility work schedule. The breakdown of how these days are to be incorporated into the FDOT project and the dependence of these days upon the completion of other activities by the UAO or others is shown in Section C.

Days prior to FDOT project construction: 79 Days during FDOT project construction: 21

Timothy P Wineberg

2026.02.24 13:58:26-05'00'

Docusign Envelope ID: 50010B39-2791-4760-9CAF-F4BD1FE4F53C

02/25/2026 | 9:05 AM EST

FLORIDA DEPARTMENT OF TRANSPORTATION

Financial Project ID: 445437-1-52-01

Utility Company: Frontier Florida LLC

FDOT Plans Dated: 02/10/2025

SECTION B: UAO SPECIAL CONDITIONS/CONSTRAINTS

Frontier and Frontier Contractors' normal business hours are from 8am to 5pm, Monday through Friday. (excluding Holidays)

Any work outside of normal business hours to be scheduled a minimum of 72 hours in advance.

Frontier inspector is to be the point of contact during construction and to be notified when working within 2' of Frontier faculties. Vince

Theodosis 727-942-8326 steve.theodosis@ftr.com

Frontier is to have access throughout the duration of the project to monitor, hold guard and protect facilities for the ability to provide service.

Frontier requires 60 days for Engineering, budget approval, material procurement and permitting before construction for conflict resolution.

Adjusting- To hand dig with shovel or small excavator to move Frontier facility horizontally or vertically to clear conflict.

The abbreviation "CPC" noted in Section C refers to "customer provided conduit"

FLORIDA DEPARTMENT OF TRANSPORTATION

FDOT Plans Dated: 02/10/2025

SECTION C: UAO’s WORK ACTIVITIES

Act.

No.

Utility Facility

(type, size, material, status)

From

Station/

Offset

To

Station/

Offset

Utility Work Activity

Description

Dependent

Activity TCP Phase

Consecutive

Calendar Days

Prior to During

Const. Const.

1 FTR (1) 30X60 HH

585+25, 64’ LT

585+28, 64’ LT

PROPOSED 30X60

HH TO BE PLACED

PRIOR TO CONST.

NTP

PRIOR TO

CONST

1 N/A

2 FRT (1) 4” DUCT

585+25

74’ LT

591+45, 74’ LT

PROPOSED

TEMPORARY 4”

DUCT W/ FOC & BT

PLACED PRIOR TO

CONST. OUTSIDE

CONST AREA

NTP

PRIOR TO

CONST

4 N/A

FTR SPLICING

TEMPORARY

CABLES

SPLICING

TEMPORARY

CABLES

NTP

PRIOR TO

CONST

10 N/A

FTR CONDUITS &

CABLES

585+25

74’ LT

591+45, 74’ LT

REMOVING OLD

CABLES &

CONDUITS

Activity 3 complete & activated

PRIOR TO

CONST

4 N/A

FTR (2) 4” CONDUIT

W/CABLES

585+25, 64’ LT

587+85

30’ LT

PLACING DUCT TO

CUSTOMER

PROVIDED HH

CPC & HH

PLACEMENT

PH IV N/A 3

FTR (2) 4” CONDUIT

W/CABLES

589+15, 31’ LT

591+25, 51’ LT

PLACING DUCT TO

CUSTOMER

PROVIDED HH

CPC & HH

PLACEMENT

PH IV N/A 4

FTR PLACING

FACILITIES IN CPC &

FTR CONDUIT

585+25, 64’ LT

591+45, 64’ LT

PLACE IN CPC 4”

DUCT ATTACHED

TO BRIDGE

CPC COMPLETED PH IV N/A 2

FTR TO SPLICE NEW

FACILITIES

SPLICING NEW

FACILITIES

Activities 6 & 7 completed

PH IV N/A 5

FLORIDA DEPARTMENT OF TRANSPORTATION

FDOT Plans Dated: 02/10/2025

SECTION C: UAO’s WORK ACTIVITIES

Act.

No.

Utility Facility

(type, size, material, status)

From

Station/

Offset

To

Station/

Offset

Utility Work Activity

Description

Dependent

Activity TCP Phase

Consecutive

Calendar Days

Prior to During

Const. Const.

FTR REMOVE BT,

BFOC AND CONDUIT

585+25

74’ LT

591+45, 74’ LT

REMOVAL OF

TEMPORARY

CONDUIT AND

CABLES

COMPLETION OF

SPLICING

PH IV 0 7

FTR MATERIAL

PROCUREMENT

NTP 30 N/A

ENGINEERING /

PERMITTING

NTP 30 N/A