This is a Utility Work Schedule prepared by the Florida Department of Transportation (FDOT) for MCI Metro Access Transmission Services to relocate and adjust utilities along Ridgemoor Boulevard in Pinellas County, Florida as part of a bridge replacement project (Financial Project ID: 445437-1-52-01). The schedule establishes the timeline and procedures for MCI's utility work activities based on FDOT plans dated February 10, 2025. The utility work involves installing high-density polyethylene (HDPE) conduit, fiber optic cable (FOC), and associated infrastructure along the project corridor from station 585+28 to station 591+48. MCI's work is divided into nine distinct activities including permitting, placement of two 2-inch HDPE pipes, placement of 24 and 96 strands of FOC, splicing operations, and removal of existing facilities. The total project timeline includes 30 calendar days of work prior to FDOT project construction and 35 calendar days during FDOT construction. The utility permit must be submitted no later than April 20, 2026.
MCI Metro Access Transmission Services, represented by Senior Engineer Michael Krol and Field Representative Christian Maldonado, must comply with the 2017 Utility Accommodation Manual requirements and notify FDOT and the contractor in writing prior to starting, stopping, resuming, and completing work activities. Special conditions require MCI to be contacted 48 hours prior to activities and when work occurs within 2 feet of MCI facilities, maintain access throughout the project duration to monitor and maintain its facilities, and install relocated facilities in permanent locations after construction completion. The Engineer of Record is Timothy Wineberg, PE, and the FDOT District Utility Administrator is Erin Long. The document was digitally signed on February 16, 2026, and approved on February 25, 2026.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rule 14-46.001 F.A.C
FLORIDA DEPARTMENT OF TRANSPORTATION
UTILITY WORK SCHEDULE
December 14, 2016
Pursuant to Section 337.403 F.S., the UAO and FDOT agree to the UAO’s need for relocation or adjustment to its utilities and FDOT’s need for a schedule for the UAO to effect the relocation or adjustment. This utility work schedule is based on FDOT plans dated in the project information box below. Any deviation by FDOT or its contractor from these plans, may void this utility work schedule. Upon notification by FDOT of a change to these plans, the UAO may negotiate a new utility work schedule. The UAO agrees to notify FDOT and the contractor in writing prior to starting, stopping, resuming, and completing work in accordance with this utility work schedule. The UAO shall obtain a utility permit and comply with requirements of the 2017 Utility Accommodation Manual (UAM) for all work done under this utility work schedule. The UAO is not responsible for events beyond the control of the UAO that could not be reasonably anticipated by the UAO and which could not be avoided by the UAO with exercise of due diligence at the time of the occurrence.
FDOT PROJECT INFORMATION
Financial Project ID: 445437-1-52-01 Federal Project ID: N/A
State Road Number: N/A (Ridgemoor Blvd) County: Pinellas
FDOT Plans Dated: 02/10/2025 District Document No.: N/A
UTILITY AGENCY/OWNER (UAO)
Utility Company: MCI Metro Access Transmission Services
UAO Project Rep: Michael Krol Phone: (813) 410-4803 E-mail: michael.krol@verizon.com
UAO Field Rep: Christian Maldonado Phone: (727) 296-5803 E-mail: christian.maldonado@lambertcable.com
UTILITY SIGNATURE
I have reviewed the FDOT plans referenced above and submit this utility work schedule in compliance with UAM Section 5 and agree to be bound by the terms of this utility work schedule.
UAO Rep. Date 2 / 16 / 2026
Name Michael Krol
Title Senior Engineer Spec-Outside Plant
ENGINEER OF RECORD SIGNATURE
I attest this utility work schedule is compatible with the FDOT plans referenced above.
EOR. Date / /
Name Timothy Wineberg, PE
Title Engineer of Record
APPROVAL BY DISTRICT UTILITIES
This utility work schedule is complete and acceptable to FDOT.
FDOT Rep. Date / /
Name Erin Long
Title District Utility Administrator
SECTION A: SUMMARY OF UTILITY WORK
The below days are the total numbers of days shown for all activities in Section C of this utility work schedule. The breakdown of how these days are to be incorporated into the FDOT project and the dependence of these days upon the completion of other activities by the UAO or others is shown in Section C.
Days prior to FDOT project construction: 30 Days during FDOT project construction: 35
Digitally signed by Michael Krol Date: 2026.02.16 08:52:26-05'00'
Timothy P Wineberg
2026.02.24 14:03:17-05'00'
Docusign Envelope ID: 50010B39-2791-4760-9CAF-F4BD1FE4F53C
02/25/2026 | 9:05 AM EST
FLORIDA DEPARTMENT OF TRANSPORTATION
Financial Project ID: 445437-1-52-01
Utility Company: MCI Metro Access Transmission Services
FDOT Plans Dated: 02/10/2025
SECTION B: UAO SPECIAL CONDITIONS/CONSTRAINTS
1. MCI requests to be contacted 48 hours prior to Activities as listed in Section C and when work is being performeed within 2' of MCI facilities.
2. MCI requests access throughout the duration of the project to monitor and maintain its facilities for the ability to provide service and will coordinate with the Road Contractor.
3. Permit for the work listed in Section C of this Utility Work Schedule will be submitted no later than 04/20/2026.
4. MCI will install the facilities listed in Section C in a permanent location after construction has been completed for the project.
FLORIDA DEPARTMENT OF TRANSPORTATION
Financial Project ID: 445437-1-52-01
Utility Company: MCI Metro Access Transmission Services
FDOT Plans Dated: 02/10/2025
SECTION C: UAO’s WORK ACTIVITIES
Act.
No.
Utility Facility
(type, size, material, status)
From
Station/
Offset
To
Station/Offset
Utility Work Activity
Description
Dependent
Activity
TCP
Phase
Consecutive
Calendar Days
Prior to During
Const. Const.
1 Permitting 585+28
26’ RT
591+48
26’ RT
Permitting N/A N/A 30 0
2 (2) 2” HDPE
585+28
26’ RT
585+85
26’ RT
Place (2) 2” HDPE
Proposed Frontier
30x60 hand hole is placed
Phase 1 0 1
3 (2) 2” HDPE
585+28
26’ RT
585+28
63’ LT
Place (2) 2” HDPE
Proposed Frontier
30x60 hand hole is placed
Phase 1 0 1
4 (2) 2” HDPE
585+28
63’ LT
591+40
51’ LT
Place (2) 2” HDPE None Phase 1 0 1
5 (2) 2” HDPE
591+40
51’ LT
591+48
26’ RT
Place (2) 2” HDPE None Phase 1 0 1
6 24 FOC
585+85
26’ RT
591+48
26’ RT
Place FOC in new conduit
Placement of new conduit and temporary Frontier conduit
Phase 1 0 1
7 Splicing 585+85
26’ RT
591+48
26’ RT
Splicing Placement of FOC Phase 1 0 15
8 96 FOC
585+85
26’ RT
591+48
26’ RT
Remove existing FOC
Splicing complete on the new FOC Phase 1 0 1
9 (2) 2” HDPE
585+85
26’ RT
591+48
26’ RT
Remove existing HDPE where accessible. Fill with grout and place OOS under the pavement
Splicing complete on the new FOC Phase 1 0 14