This is a Florida Department of Transportation (FDOT) Utility Work Schedule document governing the relocation and adjustment of Clearwater Gas utility infrastructure in connection with the Ridgemoor Boulevard Bridge Replacement Project in Pinellas County, Florida. The schedule, dated December 14, 2016, and revised as of April 18, 2025, coordinates the installation and removal of 2-inch polyethylene natural gas mains along the project corridor. The utility work encompasses five primary activities: installation of a 2-inch PE natural gas main from station 61+84 2'RT with a 5-calendar-day timeline, installation of the same main within 6-inch PE casing across a 72-foot section requiring 15 calendar days, installation of an additional 2-inch PE main within casing requiring 5 calendar days, placement of the original main out of service dependent upon completion of prior activities within 2 calendar days, and removal of the out-of-service main during construction phase to accommodate gravity wall conflicts requiring 5 calendar days during construction. The utility work schedule allocates 227 total calendar days prior to FDOT project construction and 5 calendar days during construction, with all work contingent upon receipt of approved Florida Department of Environmental Protection (FDEP) permits to be submitted no later than June 15, 2025.
Clearwater Gas, represented by Gas Section Manager Jacinta Corcoba and Field Representative Matt Burgett, is responsible for executing all utility work in compliance with the 2017 Utility Accommodation Manual (UAM) and applicable Florida Administrative Code requirements. The schedule incorporates specific operational constraints requiring five working days' notice for non-emergency issues, on-site Clearwater Gas monitoring for work within three feet of gas lines, and emergency contact procedures via a 24-hour hotline at 727-462-6633. The utility work schedule has been reviewed and approved by Engineer of Record Timothy Wineberg, PE, and District Utility Administrator Pia Cormier, confirming compatibility with FDOT plans dated August 6, 2024, and Financial Project ID 445437-1-52-01. No pricing information, set-asides, or funding requirements are specified in this utility coordination document.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rule 14-46.001 F.A.C
FLORIDA DEPARTMENT OF TRANSPORTATION
UTILITY WORK SCHEDULE
December 14, 2016
Pursuant to Section 337.403 F.S., the UAO and FDOT agree to the UAO’s need for relocation or adjustment to its utilities and FDOT’s need for a schedule for the UAO to effect the relocation or adjustment. This utility work schedule is based on FDOT plans dated in the project information box below. Any deviation by FDOT or its contractor from these plans, may void this utility work schedule. Upon notification by FDOT of a change to these plans, the UAO may negotiate a new utility work schedule. The UAO agrees to notify FDOT and the contractor in writing prior to starting, stopping, resuming, and completing work in accordance with this utility work schedule. The UAO shall obtain a utility permit and comply with requirements of the 2017 Utility Accommodation Manual (UAM) for all work done under this utility work schedule. The UAO is not responsible for events beyond the control of the UAO that could not be reasonably anticipated by the UAO and which could not be avoided by the UAO with exercise of due diligence at the time of the occurrence.
FDOT PROJECT INFORMATION
Financial Project ID: 445437-1-52-01 Federal Project ID: N/A State Road Number: N/A (Ridgemoor Blvd) County: Pinellas FDOT Plans Dated: 08/06/2024 District Document No.: N/A
UTILITY AGENCY/OWNER (UAO)
Utility Company: Clearwater Gas - Revised UAO Project Rep: Jacinta Corcoba Phone: 727-422-9998 E-mail: jacinta.corcoba@clearwatergas.com UAO Field Rep: Matt Burgett Phone: 727 224 8489 E-mail: matt.burgett@clearwatergas.com
UTILITY SIGNATURE
I have reviewed the FDOT plans referenced above and submit this utility work schedule in compliance with UAM Section 5 and agree to be bound by the terms of this utility work schedule.
UAO Rep. Date 4 / 18 / 2025 Name Jacinta Corcoba Title CGS Gas Section Manager
ENGINEER OF RECORD SIGNATURE
I attest this utility work schedule is compatible with the FDOT plans referenced above.
EOR. Date / / Name Timothy Wineberg, PE Title Engineer of Record
APPROVAL BY DISTRICT UTILITIES
This utility work schedule is complete and acceptable to FDOT.
FDOT Rep. Date / / Name Pia Cormier Title District Utility Administrator
SECTION A: SUMMARY OF UTILITY WORK
The below days are the total numbers of days shown for all activities in Section C of this utility work schedule. The breakdown of how these days are to be incorporated into the FDOT project and the dependence of these days upon the completion of other activities by the UAO or others is shown in Section C.
Days prior to FDOT project construction: 227 Days during FDOT project construction: 5
Docusign Envelope ID: 3A53C71E-55AB-4408-A729-7EE881277D74
04/22/2025 | 11:12 AM EDT
04/22/2025 | 11:40 AM EDT
FLORIDA DEPARTMENT OF TRANSPORTATION
Financial Project ID: 445437-1-52-01 Utility Company: Clearwater Gas - Revised FDOT Plans Dated: 08/06/2024
SECTION B: UAO SPECIAL CONDITIONS/CONSTRAINTS
1. Please provide Matt Burgett with 5 working days' notice for all non-emergency issues or conflicts – monitor/adjust/removal activities.
2. When working within 3 feet of the gas lines, Clearwater Gas is to be on-site to monitor work.
3. For emergencies, please contact the 24-hour emergency hotline at 727-462-6633.
4. FDEP Permit to be submitted no later than June 15 2025.
FLORIDA DEPARTMENT OF TRANSPORTATION
Financial Project ID: 445437-1-52-01 Utility Company: Clearwater Gas - Revised FDOT Plans Dated: 08/06/2024
SECTION C: UAO’s WORK ACTIVITIES
Act.
No.
Utility Facility (type, size, material, status)
From Station/ Offset
To Station/ Offset
Utility Work Activity Description
Dependent Activity TCP Phase
Consecutive Calendar Days
Prior to During Const. Const.
1 2" PE NATURAL GAS
MAIN
61+84
2’RT
61+84 20’RT to be installed Receipt of approved
FDEP permit N/A 5 0
2 2" PE NATURAL GAS
MAIN within 6” PE casing
61+84
20’RT
72+00 86’RT to be installed Receipt of approved
FDEP permit N/A 15 0
3 2" PE NATURAL GAS
MAIN within 6” PE casing
72+00
86’RT
72+00 45’RT to be installed Receipt of approved
FDEP permit N/A 5 0
4 2" PE NATURAL GAS
MAIN
61+84
2’RT
72+00
45’RT
To be placed out of service Completion of Activity 1-3 N/A 2 0 out of service
2" PE NATURAL GAS
MAIN
61+84
2’RT
72+00
45’RT
To work with the contractor to be removed at the conflict locations (2 gravity walls)
Construction of the gravity walls Ph I 0 5
6 N/A N/A N/A Permitting N/A N/A 200 0 Total 227 5