Appendix_5_UWS_Clearwater_Gas.pdf

PDF 416 KB Posted

Attached to
Ridgemoor Blvd and Brooker Creek at Brooker Creek Bridge #154153 Bridge Replacement Project (PID 005749A)
Solicitation number
26-0506-ITB-C
Issued by
Pinellas County, Clewiston City, Florida

About this file

This is a Florida Department of Transportation (FDOT) Utility Work Schedule document governing the relocation and adjustment of Clearwater Gas utility infrastructure in connection with the Ridgemoor Boulevard Bridge Replacement Project in Pinellas County, Florida. The schedule, dated December 14, 2016, and revised as of April 18, 2025, coordinates the installation and removal of 2-inch polyethylene natural gas mains along the project corridor. The utility work encompasses five primary activities: installation of a 2-inch PE natural gas main from station 61+84 2'RT with a 5-calendar-day timeline, installation of the same main within 6-inch PE casing across a 72-foot section requiring 15 calendar days, installation of an additional 2-inch PE main within casing requiring 5 calendar days, placement of the original main out of service dependent upon completion of prior activities within 2 calendar days, and removal of the out-of-service main during construction phase to accommodate gravity wall conflicts requiring 5 calendar days during construction. The utility work schedule allocates 227 total calendar days prior to FDOT project construction and 5 calendar days during construction, with all work contingent upon receipt of approved Florida Department of Environmental Protection (FDEP) permits to be submitted no later than June 15, 2025.

Clearwater Gas, represented by Gas Section Manager Jacinta Corcoba and Field Representative Matt Burgett, is responsible for executing all utility work in compliance with the 2017 Utility Accommodation Manual (UAM) and applicable Florida Administrative Code requirements. The schedule incorporates specific operational constraints requiring five working days' notice for non-emergency issues, on-site Clearwater Gas monitoring for work within three feet of gas lines, and emergency contact procedures via a 24-hour hotline at 727-462-6633. The utility work schedule has been reviewed and approved by Engineer of Record Timothy Wineberg, PE, and District Utility Administrator Pia Cormier, confirming compatibility with FDOT plans dated August 6, 2024, and Financial Project ID 445437-1-52-01. No pricing information, set-asides, or funding requirements are specified in this utility coordination document.

View the file

Other files

File Type Posted
Ridgemoor_Blvd_and_Brooker_Creek_at_Brooker_Creek_Bridge_#154153_Bridge_Replacement_Project_(PID_005749A)_(Addendum_#1_Revision).pdf PDF
Ridgemoor_Blvd_and_Brooker_Creek_at_Brooker_Creek_Bridge_#154153_Bridge_Replacement_Project_(PID_005749A).pdf PDF
Appendix_6_Geotechnical_Exploration_–_Structures_Report_03-05-2026.pdf PDF
Appendix_5_UWS_Pinellas_County_Utilities.pdf PDF
Appendix_6_FDOT_Right_of_Way_Certification_Memo_12-10-2025.pdf PDF
Appendix_6_FDOT_Engineering_“No-Rise”_Certification_Memo_11-12-2025.pdf PDF
PLANS_-_Sediment_and_Erosion_Control.pdf PDF
Appendix_6_Construction_Project_Requirements_Memo_02-27-2026.pdf PDF
Appendix_6_FDOT_Spectrum_Clear_Letter_3-27-2026.pdf PDF
Appendix_5_UWS_MCI_Metro_Access_Transmission_Services.pdf PDF
Appendix_6_FDOT_Environmental_Certification_Memo_01-30-2024.pdf PDF
Appendix_4_-_Special_Notices_6.23.pdf PDF
Appendix_6_FDOT_Preliminary_Engineering_Certification_Memo_03-6-2026.pdf PDF
Appendix_5_UWS_Duke.pdf PDF
Appendix_6_FDOT_WOW_Clear_Letter_8-2-2024.pdf PDF
Appendix_6_FDOT_Permit_Certification_Memo__02-24-2026.pdf PDF
Appendix_6_FDOT_Environmental_Certification_Memo_02-5-2026.pdf PDF
Appendix_6_FDOT_Utility_Certification_Memo_02-25-2026.pdf PDF
Appendix_5_UWS_Frontier.pdf PDF
Appendix_6_FDOT_Railroad_Certification_Memo_12-19-2025.pdf PDF
PLANS_-_ROADWAY.pdf PDF
PLANS-STRUCTURES.pdf PDF
Sample_Performance_and_Payment_Bonds_26-0506.pdf PDF
Section_7_-_County_Specifications.pdf PDF
FDOT_Specifications_Package.pdf PDF
APPENDIX_1-Permits_.pdf PDF
Sample_Application_for_Payment.pdf PDF
Sample_Change_Order.pdf PDF
QUALIFICATION-SUBMITTAL-FORM_FDOT.pdf PDF
Affdavit_of_Release_and_Guarantee.pdf PDF
Pricing_Proposal_ITB_26-0506(reference_only).pdf PDF
OpenGov_Fillable-_Final.pdf PDF
E-Verify_Affidavit.pdf PDF
Florida_Trench_Safety_Form.pdf PDF
Appendix_1-Permits_.pdf PDF
Sample_Agreement-26-0506.pdf PDF
2025_Pinellas_County_Supplemental_Specifications_.pdf PDF
SBE_Compliance_Form.pdf PDF
QUALIFICATION_SUBMITTAL_FORM_4-26-2026.pdf PDF
FDOT_Division_Specification_(FY2026-27)-ebook(signed)_(For_Legistar_only).pdf PDF
Airport_Security_Program.pdf PDF
Bid_Submittal_Form-JOC.pdf PDF
Pricing_Proposal_(for_Review_Only).xlsx XLSX spreadsheet
Non-Competitive_Oversight_Committee_Justification_Form.docx DOCX document
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Rule 14-46.001 F.A.C

FLORIDA DEPARTMENT OF TRANSPORTATION

UTILITY WORK SCHEDULE

December 14, 2016

Pursuant to Section 337.403 F.S., the UAO and FDOT agree to the UAO’s need for relocation or adjustment to its utilities and FDOT’s need for a schedule for the UAO to effect the relocation or adjustment. This utility work schedule is based on FDOT plans dated in the project information box below. Any deviation by FDOT or its contractor from these plans, may void this utility work schedule. Upon notification by FDOT of a change to these plans, the UAO may negotiate a new utility work schedule. The UAO agrees to notify FDOT and the contractor in writing prior to starting, stopping, resuming, and completing work in accordance with this utility work schedule. The UAO shall obtain a utility permit and comply with requirements of the 2017 Utility Accommodation Manual (UAM) for all work done under this utility work schedule. The UAO is not responsible for events beyond the control of the UAO that could not be reasonably anticipated by the UAO and which could not be avoided by the UAO with exercise of due diligence at the time of the occurrence.

FDOT PROJECT INFORMATION

Financial Project ID: 445437-1-52-01 Federal Project ID: N/A State Road Number: N/A (Ridgemoor Blvd) County: Pinellas FDOT Plans Dated: 08/06/2024 District Document No.: N/A

UTILITY AGENCY/OWNER (UAO)

Utility Company: Clearwater Gas - Revised UAO Project Rep: Jacinta Corcoba Phone: 727-422-9998 E-mail: jacinta.corcoba@clearwatergas.com UAO Field Rep: Matt Burgett Phone: 727 224 8489 E-mail: matt.burgett@clearwatergas.com

UTILITY SIGNATURE

I have reviewed the FDOT plans referenced above and submit this utility work schedule in compliance with UAM Section 5 and agree to be bound by the terms of this utility work schedule.

UAO Rep. Date 4 / 18 / 2025 Name Jacinta Corcoba Title CGS Gas Section Manager

ENGINEER OF RECORD SIGNATURE

I attest this utility work schedule is compatible with the FDOT plans referenced above.

EOR. Date / / Name Timothy Wineberg, PE Title Engineer of Record

APPROVAL BY DISTRICT UTILITIES

This utility work schedule is complete and acceptable to FDOT.

FDOT Rep. Date / / Name Pia Cormier Title District Utility Administrator

SECTION A: SUMMARY OF UTILITY WORK

The below days are the total numbers of days shown for all activities in Section C of this utility work schedule. The breakdown of how these days are to be incorporated into the FDOT project and the dependence of these days upon the completion of other activities by the UAO or others is shown in Section C.

Days prior to FDOT project construction: 227 Days during FDOT project construction: 5

Docusign Envelope ID: 3A53C71E-55AB-4408-A729-7EE881277D74

04/22/2025 | 11:12 AM EDT

04/22/2025 | 11:40 AM EDT

FLORIDA DEPARTMENT OF TRANSPORTATION

Financial Project ID: 445437-1-52-01 Utility Company: Clearwater Gas - Revised FDOT Plans Dated: 08/06/2024

SECTION B: UAO SPECIAL CONDITIONS/CONSTRAINTS

1. Please provide Matt Burgett with 5 working days' notice for all non-emergency issues or conflicts – monitor/adjust/removal activities.

2. When working within 3 feet of the gas lines, Clearwater Gas is to be on-site to monitor work.

3. For emergencies, please contact the 24-hour emergency hotline at 727-462-6633.

4. FDEP Permit to be submitted no later than June 15 2025.

FLORIDA DEPARTMENT OF TRANSPORTATION

Financial Project ID: 445437-1-52-01 Utility Company: Clearwater Gas - Revised FDOT Plans Dated: 08/06/2024

SECTION C: UAO’s WORK ACTIVITIES

Act.

No.

Utility Facility (type, size, material, status)

From Station/ Offset

To Station/ Offset

Utility Work Activity Description

Dependent Activity TCP Phase

Consecutive Calendar Days

Prior to During Const. Const.

1 2" PE NATURAL GAS

MAIN

61+84

2’RT

61+84 20’RT to be installed Receipt of approved

FDEP permit N/A 5 0

2 2" PE NATURAL GAS

MAIN within 6” PE casing

61+84

20’RT

72+00 86’RT to be installed Receipt of approved

FDEP permit N/A 15 0

3 2" PE NATURAL GAS

MAIN within 6” PE casing

72+00

86’RT

72+00 45’RT to be installed Receipt of approved

FDEP permit N/A 5 0

4 2" PE NATURAL GAS

MAIN

61+84

2’RT

72+00

45’RT

To be placed out of service Completion of Activity 1-3 N/A 2 0 out of service

2" PE NATURAL GAS

MAIN

61+84

2’RT

72+00

45’RT

To work with the contractor to be removed at the conflict locations (2 gravity walls)

Construction of the gravity walls Ph I 0 5

6 N/A N/A N/A Permitting N/A N/A 200 0 Total 227 5

2025-04-22T08:43:12-0700
Digitally verifiable PDF exported from www.docusign.com

File details come from the government source that posted it. Updated .