About this file

This Contract Data Requirements List (CDRL) outlines requirements for an Item Unique Identification (IUID) Marking Plan deliverable under contract number W56HZV-19-R-0118 for the Family of All Terrain Cranes program. The contractor must develop and implement an IUID Marking Plan in compliance with DI-MGMT-81803A and MIL-STD-130N to mark all items identified in the IUID Candidate List with the appropriate IUID. The IUID Candidate List and any IUID Marking Plan updates must be submitted no later than 45 days prior to Critical Design Review and Production Readiness Review. The contractor must also submit updates if any material, process, or engineering changes occur. The deliverables are to be submitted electronically using the Multi-User ECP Automated Review System Integrated Data Environment to the Contracting Officer's Representative with copies to other identified recipients.

View the file

Other files

File Type Posted
A082 _ Tool Locator Guide.pdf PDF
A053 _ NMWR Data Summary.pdf PDF
A007 _ Integrated Product Support (IPS).pdf PDF
A071 _ Critical Task List-FOATC.pdf PDF
A056 _ Storage_ Exercise_ Care and Maintenance Plan.pdf PDF
Attachment 0014 _ Hazardous Materials Management Report _ HMMR.XLSX XLSX spreadsheet
A029 _ Safety Assessment Report _ SAR.pdf PDF
A005 _ Integrated Master Schedule (IMS).pdf PDF
Attachment 0027 _ LMI Summary Worksheet _ NMWR Data.pdf PDF
A074 _ New Equipment Training Classes.pdf PDF
Attachment 0009 _ Provisioning Requirements Statement.pdf PDF
A070 _ Training Material Format and Documentation.pdf PDF
Attachment 0025 _ EPCO Source File Requirements.pdf PDF
A017 _ Provisioning Pre-Procurement Screening.pdf PDF
A095 _ Test Support Package _ TSP.pdf PDF
A030 _ System Safety Program Plan _ SSPP.pdf PDF
A058 _ Provisioning Plan.pdf PDF
A036 _ Logistics Support Analysis (LSA).pdf PDF
Attachment 0037 _ Unique Item Identifier Raw Scan Report.xlsx XLSX spreadsheet
A055 _ Accountability Report.pdf PDF
Attachment 0001 - Type I FOATC PD - AT-PRF-0001 Type I FOATC PD 2020-10-08.pdf PDF
A028 _ Hazard Tracking System - HTS.pdf PDF
Attachment 0010 _ LMI Summary Worksheet _ Maintenance Analysis.pdf PDF
A038 _ Logistics Product Data Summary (LPDS).pdf PDF
A075 _ Training Course Completion Report-Student Training Administration.pdf PDF
A063 _ Logistics Product Data.PDF PDF
Attachment 0028 _ Attribute Selection Sheet.pdf PDF
Attachment 0007 _ Exhibit A CDRL DD Form 1423.pdf PDF
Attachment 0016 _ Level of Repair Analysis (LORA).pdf PDF
A089 _ Obsolescence Supportability Analysis Report.pdf PDF
A079 _ Sample IUID Data Plate Report.pdf PDF
A093 _ Analysis Requirement.pdf PDF
A001 _ Basic Issue Items (BII) List.pdf PDF
A062 _ Bill of Materials Report.pdf PDF
A052 _ NMWR Technical Manual.pdf PDF
Attachment 0006 _ Government Furnished Property (GFP) List.xlsx XLSX spreadsheet
Attachment 0012 _ Risk Management Scoring Criteria and Reporting Template.xlsx XLSX spreadsheet
A067 _ Field Level Maintenance New Equipment Training.pdf PDF
A020 _ Failure Mode _ Effects and Criticality Analysis (FMECA).pdf PDF
A065 _ Packaging Test Report.PDF PDF
A083 _ System Tracking and Shipping Report.pdf PDF
Attachment 0030 _ LMI Data Products Worksheet.pdf PDF
Attachment 0005 _ COTS Publications Requirements.pdf PDF
Attachment 0029 _ GEIA-STD-0007 Attribute Selection Worksheet.xlsx XLSX spreadsheet
Attachment 0038 _ TACOM IUID Data Plate Minimum Requirements.pdf PDF
A085 _ DMSMS Management Plan.pdf PDF
Attachment 0022 _ Copyright Release.pdf PDF
Attachment 0017 _ Deployment Equipment Publications Style Guide.pdf PDF
A027 _ Risk Tracking Report.pdf PDF
A037 _ Product Support Analysis (PSA) and Logistics Product Data (LPD) Objectives.pdf PDF
Show 40 more

Latest 50 of 133 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

Form Approved

OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

TBD

B. EXHIBIT

A

C. CATEGORY:

TDP TM OTHER X

D. SYSTEM/ITEM

Type I FOATC

E. CONTRACT/PR NO.

W56HZV-19-R-0118

F. CONTRACTOR

TBD

1. DATA ITEM NO.

A077

2. TITLE OF DATA ITEM

Item Unique Identification (IUID) Marking Plan

3. SUBTITLE

IUID Candidate List – IUID Marking Plan

4. AUTHORITY (Data Acquisition Document No.)

DI-MGMT-81803A

5. CONTRACT REFERENCE

C.11.2, C.11.3

6. REQUIRING OFFICE

SFAE-CSS-FP-C

7. DD 250 REQ

9. DIST STATEMENT

REQUIRED

D

10. FREQUENCY

ASREQ

12. DATE OF FIRST SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

A

11. AS OF DATE

N/A

13. DATE OF SUBSEQUENT

SUBMISSION

SEE BLK 16

Draft

Final

Reg Repro

16. REMARKS

BLK 4: The contractor shall develop and implement an IUID Marking Plan for compliance with DI-MGMT-81803A and MIL-STD-130N. The contractor shall mark all items identified by the finalized and Government approved IUID Candidate List with the appropriate IUID. The contractor shall deliver documents in Microsoft Office 2013 compatible format.

BLK 8: Government will inspect and approve/disapprove within 30 calendar days of receipt.

Contractor shall incorporate Government approval with comments; contractor shall incorporate Government disapproval with comments and resubmit not later than 21 calendar days of receipt of Government response.

BLK 9: DISTRIBUTION STATEMENT D. Distribution authorized to the Department of Defense and U.S. DoD contractors only (Administrative or Operational Use; 21-MAY-2015). Other requests shall be referred to PdM CE/MHE, 6501 E 11 Mile Rd, SFAE-CSS-FP-C; MS 401, Detroit Arsenal, MI 48397.

WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C., Sec 2751, et seq.) or the Export Administration Act of 1979, as amended, Title 50, U.S.C., App. 2401 et seq. Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25.

BLK 12 & 13: The contractor shall deliver in accordance with (IAW) CDRL A0XX – Integrated Master Schedule (IMS). The Item Unique Identification Candidate List shall be submitted to Government NLT 45 days prior to Critical Design Review and subsequent Production Readiness Review. Updates to the IUID Marking Plan baseline document shall be submitted concurrently with IUID Candidate List deliveries.

BLK 13: In the event that material, process change, Engineering Change Proposal (ECP) occurs following final report approval, the contractor must provide an update to capture the change and re-submit it for Government review along with the ECP. The Government will have 30 calendar days to review and provide comments to the contractor. The contractor is required to address and incorporate all Government comments and provide a final report for approval within 21 calendar days after receipt of Government comments.

BLK14: The contractor shall submit this deliverable in electronic format using Multi-User ECP Automated Review System (MEARS) Integrated Data Environment (IDE) https://mears1.redstone.army.mil, under PdM CE/MHE Type I FOATC Program, unless otherwise directed in BLK 14.

Upon submission, the contractor shall notify the Contracting Officer's Representative (COR) of the submission via email. The COR is identified in Attachment 0008 – Type I FOATC Point of Contact (POC) List*. The Government will identify the COR in the contact list provided at the Start of Work Meeting (SOWM).

Repro = Electronic Delivery

MEARS IDE 1 0 1

COR* 1 0 1

Logistics Manager* 1 0 1

APM* 1 0 1

15. TOTAL 4 0 4

G. PREPARED BY

Integrated Product Support Manager

H. DATE

23 April 20

I. APPROVED BY

Assistant Product Manager (APM)

J. DATE

18. ESTIMATED

TOTAL PRICE

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 1 of 1 Pages

17. PRICE GROUP