2 J01 Specifications.pdf

PDF 5 MB Posted

Attached to
Western Regional Multiple Award Construction Contracts (WRMACC) Federal contract opportunity
Solicitation number
80AFRC25R0001
Issued by
National Aeronautics and Space Administration Armstrong Flight Research Center

About this file

This document is a Request for Proposal (RFP) for a NASA Armstrong Flight Research Center project to repair aprons, taxiways, and underground fire suppression systems at Edwards Air Force Base in California. The project consists of a base bid and two additive options: the base bid involves repairing a concrete ramp and fire suppression system on the north side of Building 4802, Additive 1 involves constructing a new tow way, and Additive 2 involves repairing the southernmost end of an existing taxiway. The Designer-Builder is required to perform a full site survey, provide design submittals, demolish and remove existing infrastructure, repair fire suppression systems, relocate fire hydrants, place new concrete and asphalt sections, and stripe new pavement.

The project emphasizes maintaining continuous, safe aircraft operations throughout construction, with a performance objective that aircraft towing operations must not be interrupted. The Designer-Builder must develop and implement a temporary tow path solution within a designated area, ensuring adequate width, clearance, surface stability, and safety for aircraft movement. The project requires compliance with UFC and FAA standards, and the Designer-Builder must submit design packages at 35%, 65%, 100%, and final stages. The contract will use a design-build approach, with the contractor responsible for design, engineering, and construction activities to restore full operational capability to the designated ramp and taxiway areas.

View the file

Other files for this federal contract opportunity

Other files attached to Western Regional Multiple Award Construction Contracts (WRMACC), newest first.
File Type Posted
80AFRC25R0001_Amend 13.pdf PDF
80AFRC25R0001_Amend 12.pdf PDF
80AFRC25R0001_Amend 11.pdf PDF
80AFRC25R0001 Amend 10.pdf PDF
80AFRC25R0001 Amend 9.pdf PDF
80AFRC25R0001 Amend 8.pdf PDF
80AFRC25R0001 Rev3.pdf PDF
80AFRC25R0001 Amend 7.pdf PDF
80AFRC25R0001 Rev2.pdf PDF
1 J.7 Pool 1 N254 Pictures.pdf PDF
1 J.8 ACM Survey (for A15).pdf PDF
2 Pool 2 So Cal Rev 2.pdf PDF
80AFRC25R0001_Amend 6.pdf PDF
80AFRC25R0001_Amend 5.pdf PDF
80AFRC25R0001_Amend 3.pdf PDF
80AFRC25R001_Amend 2.pdf PDF
1 J.5a- N254 WD CA20250018_10JULY2025.pdf PDF
1 J.1a6-N254-Drawing-A254-1200-FP6.pdf PDF
1 J.6b N254-Roof Asbestos Survey.pdf PDF
2 Pool 2 So Cal Rev 1.pdf PDF
2 J02 Concept Design Rev1.pdf PDF
2 J-03 WD CA20250020_Mod 9.pdf PDF
WRMACC Amend 2 Q_A.pdf PDF
1 J.1a4-N254-Drawing-A254-1200-FP4.pdf PDF
1 J.1a5-N254-Drawing-A254-1200-FP5.pdf PDF
1 J.6c N254-Asbestos Survey Report Room 131.pdf PDF
2 J-02a As-builts 4802.pdf PDF
2 J-02b As-builts roads_ramps.pdf PDF
1 J.1a1-N254-Drawing-A254-1200-FP1.pdf PDF
1 J.1a2-N254-Drawing-A254-1200-FP2.pdf PDF
1 J.1a3-N254-Drawing-A254-1200-FP3.pdf PDF
1 J.6a N254- Asbestos survey Report-Ext.pdf PDF
2 J-02c Additional Drawings.pdf PDF
80AFRC25R001_Amend 1.pdf PDF
WRMACC VIRTUAL PREPROPOSAL_PRE-BID CONFERENCE - Attendance report 7-09-25.pdf PDF
J-05 Performance Assessment Questionnaire.pdf PDF
1 N254 Pool 1 Nor Cal.pdf PDF
1 J.3b-N254 Structural Calcs-HVAC Anchorage.pdf PDF
J-04 DRD 01 SHEMP.pdf PDF
1 J.3a-N254 Structural Calcs-UPS Anchorage.pdf PDF
2 Pool 2 So Cal.pdf PDF
2 J03 WD CA20250020_06JUN2025.pdf PDF
1 J.1a-N254 Drawings.pdf PDF
1 J.2a-N254 Permits.pdf PDF
1 J.2b-N254 Permit-Hold points.pdf PDF
1 J.4a-N254 Specifications.pdf PDF
1 J.5a- N254 WD CA20250018_06JUN2025.pdf PDF
80AFRC25R0001.pdf PDF
J-01 WRMACC SOW.pdf PDF
Solicitation Attachments 80AFRC25R0001.pdf PDF
Show all 50

Western Regional Multiple Award Construction Contracts (WRMACC) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NATIONAL AERONAUTICS AND SPACE ADMINISTRATION

ARMSTRONG FLIGHT RESEARCH CENTER

EDWARDS, CALIFORNIA

FY25 Repair Aprons and Taxiways, DR 634

June 18, 2025

FY25 CoF Repair Aprons and Taxiways DR 634 NASA Armstrong Flight Research Center

STANDARD TEMPLATE - PART TWO - GENERAL REQUIREMENTS - Page 1

PART TWO - GENERAL REQUIREMENTS

FY25 CoF Repair Aprons and Taxiways Phase 1 DR634

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 14 00 WORK RESTRICTIONS

01 20 00.00 20 PRICE AND PAYMENT PROCEDURES

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES

01 35 14.11 40 AFRC SAFETY REQUIREMENTS

01 35 40.00 20 ENVIRONMENTAL MANAGEMENT

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.05 20 DESIGN AND CONSTRUCTION QUALITY CONTROL

01 45 00.10 40 CONTRACTOR QUALITY CONTROL

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 75 00.00 40 AFRC STARTUP AND COMMISSIONING

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

01 86 12.07 40 RELIABILITY CENTERED ACCEPTANCE FOR MECHANICAL SYSTEMS

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Salvage Plan; G

1.2 CONSTRUCTION SCHEDULE AND PERIOD OF PERFORMANCE

Contractor shall commence and complete all work within the contract period of performance of 150 days for the base bid, 180 days for additive option 1, and 270 days for additive option 2.

The following reflects the number of calendar days that will be allowed for construction activities. Items marked with an asterisk reflect option items which may or may not be awarded.

Activity Calendar Days Duration

NTP 0

Base Bid 150

Additive Option 1 180

Additive Option 2 270

Total 600

1.3 WORK SCHEDULING

Allow for a maximum of 11 calendar days in the construction schedule where construction activity is prohibited due to NASA operations.Government will provide 24 hour notification each time the restrictions are invoked.

Normal duty hours are defined in Section 01 14 00 "WORK RESTRICTIONS" Requests for additional work requires written approval from the Contracting Officer 7 days in advance of the proposed work period.

1.4 OCCUPANCY OF PREMISES

Building(s) will be occupied during performance of work under this Contract.

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

SECTION 01 11 00 Page 1

1.5 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.6 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT

There will be no Government-Furnished Property for this contract.

1.7 REQUIRED OPERATIONAL SYSTEMS AND ROADS

The center will be occupied during the entire performance period of work under this contract. Therefore, Contractor shall install temporary mechanical system(s) as necessarybypass system with necessary valves, provide temporary services during the period of construction and remove only after permanent services have been installed, tested, commissioned, are under full controllable operation and have been accepted by the government. For any temporary installation that requires an outage coordinate in advance with the COR to select a solution to achieve continuity of service and follow 01 35 14.11 40 AFRC SAFETY REQUIREMENTS paragraph "Permit Required Operations" to obtain approval from the government prior to the outage.

The contractor shall maintain adequate clearances during construction to allow full access for all AFRC aircraft to continue operations.

Contractor shall be responsible for off hour operation of temporary systems and utilities, and shall be "on call" 24/7/365 for emergency service to keep existing or temporary system operational.

1.8 SALVAGE MATERIAL AND EQUIPMENT

Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located within 5 miles of the construction site.

Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Provide a system for property control in the salvage plan. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.

SECTION 01 11 00 Page 2

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 3

SECTION 01 14 00

WORK RESTRICTIONS

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. Submit the following in accordance with Section

01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals List of key Contact Personnel

Personnel List

Entry Approval For Employees

1.2 SPECIAL SCHEDULING REQUIREMENTS

The Taxiways, Tow ways, and Hangars will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.

1.3 CONTRACTOR ACCESS AND USE OF PREMISES

1.3.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations (see Section 01 35 14.11 40 for AFRC Safety Requirements). Contractor personnel shall keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, including delivery vehicles, are clearly identified with their company name.

1.3.1.1 Material and Equipment

The Contractor shall receive, unload, handle, and store all materials and equipment at the project staging area or the active work area. The Government will not accept deliveries on behalf of the Contractor or its subcontractors or assume responsibility for the security of materials,or equipment delivered to the site. The Contractor shall not have any material or equipment deliveries made to the AFRC shipping and receiving warehouse.

The Contractor shall protect and preserve materials, and equipment including property which may be Government-furnished or Government-owned.

Material or equipment to be salvaged and reinstalled by the Contractor shall be protected during removal and stored to prevent damage. Only

SECTION 01 14 00 Page 1 material and equipment designated for performance of contract work may be stored at the construction site or located in Government-controlled areas.

1.3.1.2 Subcontractors and Personnel Contacts

Provide a list of key contact personnel and personnel list of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.3.1.3 Identification Badges

Identification badges will be furnished by NASA without charge to the Contractor. Application for and use of badges will be as directed by NASA. Contractor shall submit for approval on NASA Enterprise Visitor Agency Management System (EVAMS), (Visit Request - US Citizen) or AFRC10736 (Visit Request - Foreign National/Legal Permanent Resident), at least 15 work days prior to the desired date of entry, a list of personnel who require entry into Government property to perform work on the project. Access for foreign nationals requires additional documentation and shall be requested at least 20 work days prior to the desired date of entry. Furnish a completed EMPLOYMENT ELIGIBILITY VERIFICATION (DHS FORM I-9) form for all personnel requesting badges. This form is available at https://www.uscis.gov/i-9. Immediately report instances of lost or stolen badges to the Contracting Officer.

1.3.1.4 Entry Approval For Employees

Failure to obtain entry approval shall not affect the contract price or time of completion.

A satisfactory Criminal History Check is required for access.

Photography of either flight line or lake bed is prohibited.

Firearms are prohibited on Edwards AFB and NASA facilities.

1.3.1.5 Access Levels

Contractor shall determine which individuals will require each level of access and submit necessary documentation for each individual.

PIV BADGE: A Personal Identity Verification (PIV) badge is required for unescorted access with escort privileges. Contractor shall request a PIV badge for unescorted access for personnel that will access the site during a period of 180 days or more.

BLUE/WHITE BADGE: A blue/white badge is required for unescorted access without escort privileges. Contractor shall request an Armstrong Access Control Card (AACC) blue badge or white badge for unescorted access for personnel that will access the site regularly for a period 179 days or less. Fingerprinting and two forms of ID are required for this access.

ORANGE/PINK BADGE: An orange/pink visitor badge has no access to the center unless escorted. Contractor shall request an orange or pink visitor badge for escorted access for personnel requiring temporary access to the site. Personnel with temporary access shall know who their escort is, maintain visual contact with their escort at all times, inform their escort of their activities and remain in close proximity of their escort.

If separated from escort return to the desk where badge was issued.

SECTION 01 14 00 Page 2

1.3.1.6 Escorting Privileges

A PIV badge is required for the privilege of escorting others that have 'escorted' access to the center. A current PIV by itself does not permit an individual to escort other contractor or subcontractor employees, the person escorting shall also:

A. Be knowledgeable of the purpose of the visit and restrictions on access to assets;

B. Introduce themselves to the visitor(s) and stay in line of sight of the visitor at all times to assist, control, and observe the visitor;

C. Be knowledgeable of procedures for reporting a visitor's unusual activity or interest;

D. Be knowledgeable of the safety and security procedures and requirements for the area(s) being visited; and

E. Be cognizant of their visitor's whereabouts and activities at all times and remain in close proximity of their visitor(s) to provide immediate assistance in an emergency, prevent a safety or security incident, and prevent unauthorized access to assets.

1.3.1.7 Personnel Entry Approval

Failure to obtain entry approval will not affect the contract price or time of completion.

1.3.1.8 No Smoking Policy

Smoking is prohibited within and outside of all buildings on NASA installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

1.3.2 NORMAL DUTY HOURS

AFRC is currently operating under a flexible work schedule, known as a 9/80 schedule, which allows for a non-work day every other Friday. Normal AFRC Work Hours are from 6:00 am to 5:30 pm Monday through Friday the first week of the AFRC pay period, and then from 6:00 am to 5:30 pm Monday through Thursday the second week of the AFRC pay period, excluding Federal Holidays. The Contractor shall plan work around the AFRC pay period.

Weekends, 9/80 non-work Fridays, and Government holidays are restricted for work unless otherwise directed by Contracting Officer. The Contractor's work shifts shall take place during "Normal AFRC Work Hours", except as requested by the Contractor, coordinated by the COR, and then approved by the CO per paragraph "Work Outside Normal AFRC Work Hours" below.

1.3.2.1 WORK OUTSIDE NORMAL AFRC WORK HOURS

When the Contractor needs to work outside normal duty hours, Contractor shall submit a request to the COR 14 calendar days prior to such work.

SECTION 01 14 00 Page 3

Request shall include specific dates, hours, location, type of work to be performed, activity hazard analysis for work (including night work hazards when applicable), contract number and project title. The COR will then coordinate with AFRC Operations & Maintenance, AFRC Security Office, AFRC Safety Office, and building occupants to arrange for inspecting the work in progress. Based on the justification provided, the COR will coordinate with the CO who may approve the work outside normal duty hours. During periods of darkness, the different parts of the work shall be lighted by the Contractor in a manner approved by the Contracting Officer. Permission to work outside normal duty hours does not give permission to make utility cutovers, make cutovers only during outage periods approved through the outage permit process in section 01 35 14.11

40 AFRC SAFETY REQUIREMENTS.

1.3.2.2 CORE HOURS

Core Hours are the hours within Normal Duty Hours during which all flexible work schedules overlap. Regularly scheduled meetings with the Government shall be during Core Hours. Core Hours are 8:00 am to 3:00

pm. Non-Core Hours are any time before 8:00 am or after 3:00 pm.

1.3.3 Occupied and Existing Buildings

The Contractor shall be working in and around existing buildings which are occupied.

The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.

Provide dust covers or protective enclosures to protect existing work, and Government material that remains during the construction period.

Relocate movable furniture at least6 feet away from the Contractor's working area or as required to perform the work, protect the furniture, and replace the furniture in its original location upon completion of the work. Leave attached equipment in place, and protect them against damage, or temporarily disconnect, relocate, protect, and reinstall it at the completion of the work.

Before work is started, the Contractor shall arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

Government and other contractor personnel will be allowed access to the construction area and Contractor lay down or storage areas to perform routine or emergency maintenance on building systems and equipment. This includes communication, electrical, water, sewer, natural gas, mechanical, and fire protection systems.

1.3.4 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays or another time approved through the outage permit process at no additional cost to the Government. Conform to procedures required in paragraph WORK

OUTSIDE NORMAL AFRC WORK HOURS.

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

SECTION 01 14 00 Page 4

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, and UPS Backup are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS.

d. Operation of Center Utilities: The Contractor must not operate nor disturb the setting of control devices in the utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor shall notify the Contracting Officer giving advance notice as required in Section 01 35 14.11 40 paragraphs "PERMIT REQUIRED OPERATIONS" and "UTILITY OUTAGES/FACILITY CLOSURES." when such operation is required.

e. Connection to Existing Sanitary Sewer Line: Provide positive verification that the existing line conveys sanitary sewer; verify line is not incorrectly connected to a storm drain.

1.3.5 ENVIRONMENTAL CONSIDERATIONS

The Edwards AFB property, which NASA shares, is on the National Priorities List (NPL, or Superfund) due to known areas of soil and groundwater contamination. Known contamination in soil has been cleaned up, and known contamination in shallow groundwater is under treatment but not yet cleaned up. The Contractor shall be aware that all intrusive activities (excavation or digging greater than 6" deep) within the contaminated areas shown on the drawing require a dig permit, vapor monitoring (for possible TCE, Toluene, Ethylene, Xylene, Benzene, Nitrosodimethylamine, or Carbon Tetra-Chloride exposure), and use of Personal Protective Equipment (PPE) for personnel within these areas, unless waived by the Contracting Officer. Contractor shall provide all vapor monitoring equipment.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 14 00 Page 5

SECTION 01 20 00.00 20

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.1 SUBMITTALS

The following shall be submitted in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Schedule of Values; G

SD-11 Closeout Submittals

Contractor's Invoice shall be submitted in accordance with Paragraph "CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT"

1.2 SCHEDULE OF VALUES

1.2.1 Data Required

Within 15 calendar days after notice to proceed, the Contractor shall prepare and deliver to the Contracting Officer a schedule of values for approval. The Schedule of Values shall consist of a detailed breakdown of each contract activity. The value of each activity shall be identified as a percentage of the total contract value, and shall correlate with the activities in the Project Schedule.

Contracting Officer will determine whether items in the Schedule of Values are appropriate. Progress payments shall be based on the approved Schedule of Values.

1.2.2 Schedule Instructions

Payments will not be made until the Schedule of Values has been submitted to and accepted by the Contracting Officer. Identify the cost for site work, and include incidental work to the 5 ft line. Identify costs for the building(s), and include work out to the 5 ft line. Work out to the 5 ft line shall include construction encompassed within a theoretical line 5 ft from the face of exterior walls and shall include attendant construction, such as pad mounted HVAC cooling equipment, cooling towers, and transformers placed beyond the 5 ft line.

1.2.3 Design Services for Design Build Contracts

Design services shall be no more than 10% of the total contract value on the schedule of values. Any increase beyond 10% shall require justification and is at the discretion of the COR.

1.2.4 Mobilization and Demobilization Costs

The schedule of values shall include reasonable mobilization and demobilization costs. The value of demobilization shall be at least 50% of the mobilization cost.

SECTION 01 20 00.00 20 Page 1

1.3 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT

1.3.1 Content of Invoice

Requests for payment will be processed in accordance with the Contract Clause FAR 52.232-27. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies. Requests for payment in accordance with the terms of the contract shall consist of:

a. The Contractor's invoice on form AFRC80809 furnished by the Contracting Officer for this purpose, shall show in summary form the basis for arriving at the amount of the invoice. Be aware that a "No" on any performance evaluation criteria on this form will affect the amount recommended for payment.

b. The contract performance statement on the form furnished by the Contractor for this purpose and consistent with the approved Schedule of Values, shall show in detail the estimated percentage of completion for each Definable Feature of Work (DFOW). The format, content, and number of copies required will be prescribed by the Contracting Officer and will be subject to his/her approval.

c. Furnish a certificate to the CO with each payment request attesting that the work for which payment is requested, including stored material, is in compliance with contract requirements.

d. The Estimate for Voucher, showing in detail the percentage of completion for each of the construction activities listed on the Schedule of Values.

e. Updated Project Schedule and any reports required by the contract.

g. Contractor Safety Self-Evaluation Checklist

h. Weekly Certified Payroll Report

i. Solid Waste Disposal Report

j. Other supporting documents as requested

k. For Final Payment: All closeout submittals must be received prior to final payment. A final invoice and the Contractor's Final Release is the Contractor's request for final payment, including completed As-Built Drawings. If the Contractor is incorporated, the Final Release shall contain the corporate seal. An officer of the corporation shall sign and the corporate secretary or official designee shall certify the Final Release.

No separate payments will be made for protection efforts necessitated by the safety provisions.

1.4 PAYMENTS TO THE CONTRACTOR

Payments will be made on submission of itemized requests by the Contractor will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.

SECTION 01 20 00.00 20 Page 2

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 20 00.00 20 Page 3

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety -- Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. Submit the following in accordance with Section

01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

View Location Map

Progress and Completion Photographs

SD-04 Samples

Color Boards; G

Electronic Mail (E-Mail) Address; G

1.3 VIEW LOCATION MAP

For each project, submit to the Contracting Officer, prior to or with the first digital photograph submittals, Photograph Location & View Map (Site Plan or Building Plan) indicating the approximate location and direction (view) from which project photographs will be taken.Update as required if the locations are moved.

1.4 PROGRESS AND COMPLETION PHOTOGRAPHS

For each project, the Contractor shall photographically document site conditions before, during and after construction of the project. The Contractor's photographer shall be approved by the Contracting Officer;

upon request, the photographer shall provide examples of prior work and/or references, prior to taking the initial photographs. A minimun of twelve

(12) photographic taken from north, south, east and west views of the project site shall be taken before entry thereon by the Contractor, and again from the same views, after completion of all construction activities. During construction, six (6) views shall be photographed in each work area, each month or as determined by Contracting Officer

SECTION 01 30 00 Page 1 according to project scope and complexity showing the general progress of the construction work. Prior to enclosing any trench, wall, or structure, an additional four (4) interior views shall be photographed (this is in addition to the GPS survey of sub-surface utilities required in section 01 78 00 "Closeout Submittals"). The Contracting Officer shall be given the opportunity to designate what views are of interest. The Contractor shall provide digital photographs, 1600x1200x24 bit true color minimum resolution, calibrated for proper color / brightness / contrast; no manipulation of the image is permitted. Date of photography, name of Contractor / engineer / owner, plus unique digital file number keyed to the "Photograph Location & View Map", shall be embedded in the digital image file in a manner that is 'permanent' and clearly legible when the file is opened. Files will be saved at 72dpi resolution in JPEG file format with a maximum of 50 percent compression applied, and written to a compact disk (CD). Each CD shall bear a surface label which includes the photographer's name and contact information, name of the project, and description of the contents. Submit, with each invoice, one set of digital photographs on CD, cumulative of all photos to date, showing the sequence and progress of work. Photographs for each submittal shall be in a separate monthly directory and each file shall be named to indicate its location on the Photograph Location & View Map. The Photograph Location & View Map shall also be provided on the CD as a digital file. All file names shall include a date designator in YYYY-MM-DD format per ISO 8601.

Cross reference submittals in the appropriate daily report. Photographs shall be provided for unrestricted use by the Government.

1.5 SUPERVISION

1.5.1 Superintendent Qualifications

The Contractor shall provide at least one (1) qualified Project Manager and one (1) qualified on-site Project Superintendent. The Project Manager must have a minimum of 10 years experience as a Project Manager or Superintendent on projects like this contract or similar in size and complexity. The project superintendent shall have a minimum of10 years experience in construction with at least 5of those years as a superintendent on projects similar in size and complexity. The individual

(s) must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance.

The individual(s)shall complete the U.S. Army Corps of Engineers course entitled "Construction Quality Management for Contractors" prior to the start of construction. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent.

The Project Manager shall mean the individual with the responsibility for the overall management of the project and the Project Superintendent shall mean the individual with the responsibility for production. Both the Project Manager and Project Superintendent are subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders shall be made the subject of claim for extension of time for excess costs or damages by the Contractor.

Approval of Project Manager and on-site Project Superintendent is required prior to start of construction. Provide resumes for the proposed Project

SECTION 01 30 00 Page 2

Manager and on-site Project Superintendent describing their experience with references and qualifications to the Contracting Officer for approval. The Contracting Officer reserves the right to interview the proposed Project Manager and on-site Project Superintendent at any time in order to verify the submitted qualifications.

For projects where the superintendent is permitted to also serve as the Quality Control (QC) Manager as established in Section 01 45 00.10 40 CONTRACTOR QUALITY CONTROL,the superintendent must have qualifications in accordance with that section.

1.5.2 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work. In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.

1.5.2.1 ELECTRONIC MAIL (E-MAIL) ADDRESS

The Contractor shall establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments in Microsoft Office, Adobe Acrobat, and other similar formats.Contracting Officer will provide the contractor with the project group email, in which the contractor will use for all email communciations with the contracting officer (CO) or the contracting officer Representative (COR). Within 10 calendar days after contract award, the Contractor shall provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes, terrorist threats, etc. Multiple email addresses will NOT be allowed.

It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). The Contractor shall promptly notify the Contracting Officer, in writing, of any changes to this email address.

1.5.3 Duties

The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend daily tailgate meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.5.4 Non-Compliance Actions

The Project Superintendent, Quality Control Manager, Site Safety & Health Officer, and Project Manager are subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.

SECTION 01 30 00 Page 3

Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.6 PRECONSTRUCTION MEETING / CONFERENCE

Immediately after award, upon completion of design and design acceptance by the government , prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Conference . The meeting/conference must take place within prior to commencement of any work at the site. The purpose of this meeting / conference is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing. Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.

1.7 Weekly Project Meetings

The Contractor shall attend weekly project meetings scheduled by the Government. Discussion shall include at a minimum: safety issues, quality control, submittals, progress schedule, schedule of submittals, as-built drawings, deficiencies, material delivery, permits, equipment delivery, invoices, potential factors of delay, request for information (RFIs), changes, and functional tests.

1.8 FACILITY TURNOVER PLANNING MEETINGS

Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start planning the turnover process at the Pre-Construction Conference meeting with a discussion of the Red Zone process and convene at regularly scheduled NRZ Meetings beginning at approximately 75 percent of project completion.

Include the following in the facility Turnover effort:

1.9 PARTNERING

To most effectively accomplish this Contract, the Contractor and Government must form a cohesive partnership with the common goal of drawing on the strength of each organization in an effort to achieve a successful project without safety mishaps, conforming to the Contract, within budget and on schedule. The partnering team must consist of personnel from both the Government and Contractor including project level and corporate level leadership positions. Key Personnel from the Contractor, key subcontractors and the Designer of Record are required to participate in the Partnering process.

1.9.1 Facilitated (Formal) Partnering

a. Prior to the start of work, host a Formal Partnering session with key personnel from the project team including both Contractor and Government personnel. All costs associated with the Partnering

SECTION 01 30 00 Page 4 session including the third-party independent Facilitator Consultant, meeting room and other incidental items are the responsibility of the Contractor.

b. Before the Facilitated (Formal) Partnering session, coordinate with the Facilitator all requirements for incidental items (such as audio-visual equipment, easels, flipchart paper, colored markers, note pads, pens/pencils, colored flash cards) and have these items available at the Partnering session. Provide copies of any documents required for distribution to all attendees. Participants will bear their own costs for meals, lodging and transportation associated with Partnering .

c. The Initial Partnering Session must be a duration of one day minimum and be held at a location off the construction site as agreed to by the Contracting Officer. Partnering session may take place concurrently with the Pre-Construction /Meeting.

d. Facilitator must be experienced in conducting corporate Partnering sessions and must be a third-party independent facilitating consultant

- not an employee of the Contractor. The Facilitator is responsible for leading all aspects of the Partnering session necessary to achieve the Partnering goal.

e. An outcome of the Partnering session must be an escalation matrix agreed upon by both the Government and Contractor, which identifies key Government and Contractor decision makers by name and anticipated decision durations.

f. Host follow-on Partnering Sessions at three- to six-month intervals or more frequently if needed and lasting generally a half day or less.

Attendees need only be those required to resolve current issues. The same Facilitator used in the Initial Partnering session must lead the follow-on sessions unless an alternative is permitted by the Contractor Officer. All costs associated with follow-on Partnering sessions are the responsibility of the Contractor.

1.9.2 Team-Led (Informal) Partnering

a. The Contracting Officer will coordinate the initial Team-Led (Informal) Partnering Session with key personnel of the project team, including Contractor and Government personnel. The Partnering Session will be co-led by the Government Construction Manager and Contractor's Project Manager.

b. The Initial Team-led Partnering session may be held concurrently with the Pre-Construction / meeting. Partnering sessions will be held at a location mutually agreed to by the Contracting Officer and the Contractor, typically at a conference room on-site or at the Contractor's temporary trailer.

c. The Initial Team-Led Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by Contracting Officer.

d. The Partners will determine the frequency of the follow-on sessions.

e. Participants will bear their own costs for meals, lodging and transportation associated with Partnering.

SECTION 01 30 00 Page 5

1.10 MOBILIZATION

Contractor shall mobilize to the jobsite within 60 calendar days after acceptance of the final design. Mobilize is defined as having equipment AND having a physical presence of at least one person from the contractor's team on the jobsite.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 30 00 Page 6

SECTION 01 32 01.00 10

PROJECT SCHEDULE

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AACE INTERNATIONAL (AACE)

AACE 29R-03 (2011) Forensic Schedule Analysis

AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Project Scheduler Qualifications; G

Initial Project Schedule; G

Periodic Schedule Update; G

1.3 PROJECT SCHEDULER QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.

PART 2 PRODUCTS

2.1 SOFTWARE

The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.

2.1.1 Contractor Software

Scheduling software used by the contractor must be commercially available

SECTION 01 32 01.00 10 Page 1 from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The Contractor shall incorporate the principles of Three Phases of Quality Control, as further described in Section 01 45 00.10 40, into all applicable schedule items.

The scheduling of the entire project is required. The scheduling of design (if included in the contract) and construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Designers, Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules. Prepare each Project Schedule using the Precedence Diagram Method (PDM).

3.1.1 Approved Project Schedule

Use the approved Project Schedule to measure the progress of the work and to aid in evaluating time extensions. The schedule shall be cost loaded and activity coded. The schedule will provide the basis for all progress payments. The project schedule shall be capable of showing percent complete for each activity.

3.1.2 Schedule Status Reports

Provide a Schedule Status Report on at least a monthly basis. If the Contracting Officer determines that the Contractor has fallen behind the approved schedule, the Contracting Officer may require the Contractor to take steps necessary to improve its progress without additional cost to the Government.

3.2 PROJECT SCHEDULE DETAILED REQUIREMENTS

The computer software system utilized to produce and update the Project Schedule shall be capable of meeting all requirements of this specification.

3.2.1 Level of Detail Required

Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

3.2.1.1 PROGRESS SCHEDULE REQUIREMENTS

The Contractor shall prepare and submit to the Contracting Officer for approval a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor

SECTION 01 32 01.00 10 Page 2 contemplates starting and completing the major salient features of the work, including acquiring materials and equipment. The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. The Contractor shall:

a. Submit the progress chart in PDF format and three copies.

b. Prepare the progress chart in the form of a bar chart utilizing a form "Construction Progress Chart" or comparable format acceptable to the Contracting Officer.

c. Include no less than the following information on the progress chart:

1. Break out by major headings for each primary work activity.

2. A line item break-out under each major heading sufficient to track the progress of the work.

3. A line item showing contract finalization tasks which include punch list, clean-up, O&M data, and As-Built drawings.

4. The estimated percentage weight of total contract value for each line item on the chart. This shall be consistent with the Schedule of Values.

5. Separate line items for submittal preparation and reviews. These shall be consistent with the "Schedule of Submittals" required in Section 01 45 00.10 40, "CONTRACTOR QUALITY CONTROL". Submittal preparation and reviews are to show no associated costs. Ensure submit by date and approval needed by date are included and do not conflict with updated submittal register.

6. Separate line items for mobilization and demobilization.

d. Update the progress schedule in 3 copies every 30 calendar days throughout the contract performance period. The updated schedule shall be submitted with the monthly payment request.

3.2.1.2 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Less than 2 percent of all non-procurement activities shall have durations greater than 20 work days or 30 calendar days. Where work or calendar days are not specified elsewhere in this specification, the term "days" shall refer to "calendar days", where the term "work days" refers to work days.

3.2.1.3 Procurement Activities

The schedule must include activities associated with the submittal, approval, procurement, fabrication and delivery of long lead materials, equipment, fabricated assemblies and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days. A typical procurement sequence includes the string of activities: submit, approve, procure, fabricate, and deliver.

3.2.1.4 Government Activities

Show Government and other agency activities that could impact progress.

SECTION 01 32 01.00 10 Page 3

These activities include, but are not limited to: approvals, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.

3.2.1.5 Design and Permit Activities

Include design and permit activities with the necessary conferences and follow-up actions and design package submission dates. Include the design schedule in the project schedule, showing the sequence of events involved in carrying out the project design tasks within the specific contract period. Provide at a detailed level of scheduling sufficient to identify all major design tasks, including those that control the flow of work.

Also include review and correction periods associated with each item.

3.2.1.6 Mandatory Tasks

Include the following activities/tasks in the initial project schedule and all updates.

a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).

b. Submission, review and acceptance of features require design completion Submission, review and acceptance of design packages.

c. Submission of mechanical/electrical/information systems layout drawings.

d. Long procurement activities

e. Submission and approval of O & M manuals.

f. Submission and approval of as-built drawings.

h. Submission and approval of installed and removed equipment lists.

k. Submission and approval of fire protection specialist.

s. Contractor's pre-final inspection.

t. Correction of punch list from Contractor's pre-final inspection.

u. Government's pre-final inspection.

v. Correction of punch list from Government's pre-final inspection.

w. Final inspection.

3.2.1.7 Government Activities

Show Government and other agency activities that could impact progress.

These activities include, but are not limited to: approvals, approval timeline for permits for outages and other permit required activities in section 01 35 14.11 40, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.

3.2.2 Scheduled Project Completion and Activity Calendars

The schedule interval shall extend from NTP date to the required contract

SECTION 01 32 01.00 10 Page 4 completion date. The contract completion activity (End Project) shall finish based on the required contract duration in the accepted contract proposal, as adjusted for any approved contract time extensions. The first scheduled work period shall be on or after the date indicated in the NTP letter received from the Contracting Officer. Schedule activities on a calendar to which the activity logically belongs. Activities may be assigned to a 7-day calendar when the contract assigns calendar day durations for the activity such as a Government Acceptance activity. If the Contractor intends to perform physical work less than seven days per week, schedule the associated activities on a calendar with non-work periods identified including weekends and holidays. Note as Weather Sensitive Installation those activities that are weather sensitive.

Durations must account for anticipated normal adverse weather. The Government will interpret all work periods not identified as non-work periods on each calendar as meaning the Contractor intends to perform work during those periods.

3.2.2.1 Design Start Date

The schedule shall start no earlier than the date on which the NTP was acknowledged. Include as the first activity in the project schedule an activity called "Start Design" (or Design NTP) with a start date equal to the date that the NTP was acknowledged, and a zero day duration.

3.2.2.1.1 Construction Start Date

The first scheduled construction activity shall start no earlier than the date on which the Construction NTP was acknowledged. Include as the first construction activity in the project schedule an activity called "Start Construction" (or Construction NTP) with a construction start date equal to the date that the construction NTP was acknowledged, and a zero day duration.

3.2.2.2 Schedule Constraints and Open Ended Logic

Constrain completion of the last activity in the schedule by the contract completion date. Schedule calculations shall result in a negative float when the calculated early finish date of the last activity is later than the contract completion date. Include as the last activity in the project schedule an activity called "End Project" with an end date equal to the contract completion date for the project, and with a zero day duration.

The schedule shall have no constrained dates other than those specified in the contract.

3.2.2.3 Early Project Completion

In the event the Initial project schedule calculates an early completion date of the last activity prior to the contract completion date, identify those activities that it intends to accelerate and/or those activities that are scheduled in parallel to support the Contractor's "early" completion. The last activity shall have a late finish constraint equal to the contract completion date and the schedule will calculate positive float. The Government is under no obligation to accelerate activities for which it is responsible to support a proposed early contract completion.

3.2.3 Milestones

The schedule must include milestone activities for each significant

SECTION 01 32 01.00 10 Page 5 project event including but not limited to: milestone…