8-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf

PDF 109 KB Posted

Attached to
124 Easton Road Demolition 25-01189. 01
Solicitation number
Not on record
Issued by
Pennsylvania

About this file

This is a Contract Considerations specification document for a Pennsylvania state and local contract opportunity involving the demolition of Shelby Apartments located at 111-124 Easton Road. The project scope includes demolition of an existing apartment building, associated concrete patios, and asphalt parking lot, along with environmental remediation within the building and site restoration to match existing grading and stabilization. The contractor must submit a preliminary Schedule of Values in duplicate within 10 days after the Effective Date of the Agreement, with monthly payment periods required thereafter. Applications for payment must be submitted in three copies using EJCDC Form C-620, and must include Payroll Certification forms and updated construction progress schedules with each submission. Final payment applications require a Waiver of Liens or Contractor's Affidavit, Contractor's Release, and Statement of Surety Company documentation.

The contract establishes specific procedures for change management, including Engineer-authorized minor changes issued as supplemental instructions, Proposal Requests requiring contractor estimates within 15 days, and multiple change order options including Stipulated Price Change Orders, Unit Price Change Orders, Work Change Directives on EJCDC Form C-940, and Time and Material Change Orders. Contractors proposing changes must submit detailed requests describing the proposed change and its full effects on contract price, contract time, and other contractors' work, with supporting documentation. The Schedule of Values must include direct proportional amounts of contractor overhead and profit within each line item, and must be revised to reflect approved Change Orders with each Application for Payment. No alternates are specified for this contract.

View the file

Other files

File Type Posted
32-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
38-Doc 00 73 00 8 - Appendix C - 2700-FM-AQ0021 - Form.pdf PDF
23-Doc 00 73 00 4 - Appendix B - cover sht.pdf PDF
19-Doc 00 62 76 - Application for Payment.pdf PDF
36-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
25-Sec 31 23 33 - Excavation, Backfill and Compaction.pdf PDF
49-Doc 00 43 13 - BID BOND.pdf PDF
56-Doc 00 11 13 - ADVERTISEMENT FOR BIDS - 124 Easton Road Demo Revised.pdf PDF
14-Sec 02 41 16 - DEMOLITION.pdf PDF
39-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
51-Doc 00 73 00 3 - Appendix A - PA Wage Rate Determination.pdf PDF
18-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
3-Doc 00 73 00 14 - Appendix F - Universal Waste Report.pdf PDF
5-Doc 00 01 15 - TABLE OF CONTENTS - LIST OF DRAWINGS.pdf PDF
17-Sec 01 33 00 - SUBMITTALS.pdf PDF
6-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
9-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID - 2025.pdf PDF
47-Doc 00 73 00 12 - Appendix E - lead rpt-final.pdf PDF
26-Doc 00 65 19.16 - SUBCONTRACTORS RELEASE OF LIENS.pdf PDF
24-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
53-Doc 00 73 00 13 - Appendix F - cover sht.pdf PDF
43-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
54-Doc 00 01 10 - TABLE OF CONTENTS.pdf PDF
12-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
29-Doc 00 73 00 10 - Appendix D - ACM Survey Rpt-final.pdf PDF
40-Doc 00 73 00 7 - Appendix C - 2700-FM-AQ0021 - Instructions.pdf PDF
55-X 124 Easton Road Bid Set.pdf PDF
21-Doc 00 73 00 6 - Appendix C - cover sht.pdf PDF
4-Sec 01 57 13 Soil Erosion and Sediment Control.pdf PDF
2-Doc 00 91 13 - ADDENDA.pdf PDF
48-Sec 32 92 00 - Finish Grading, Seeding and Sodding.pdf PDF
35-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
27-Doc 00 45 10 - BIDDER’S ACKNOWLEDGEMENT FORM.pdf PDF
34-Doc 00 63 63 - Change Order.pdf PDF
28-Doc 00 73 00 9 - Appendix D - cover sht.pdf PDF
22-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
31-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
16-Doc 00 65 19.13 - SUBCONTRACTORS AFFIDAVIT.pdf PDF
46-Doc 00 73 00 2 - Appendix A - cover sht.pdf PDF
11-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
1-Sec 01 56 39. - LANDSCAPE PROTECTION.pdf PDF
13-Doc 00 21 13.1-Instr for Electronic Bidding.pdf PDF
42-Doc 00 73 00 5 - Appendix B - Public Works Employment Verification Form.pdf PDF
45-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
7-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
15-Doc 00 21 13.2 - PennBid - How To Submit a Bid.pdf PDF
33-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
37-Doc 00 41 00 - BID FORM - EBID.pdf PDF
50-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
44-Doc 00 73 00 11 - Appendix E - cover sht.pdf PDF
Show 40 more

Latest 50 of 55 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT CONSIDERATIONS

01 29 00-1

SECTION 01 29 00

PART 1 GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Schedule of values.

2. Application for payment.

3. Change procedures.

4. Alternates.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Document 00 52 00: Agreement: Contract Price

2. Section 01 22 00: Measurement and Payment

3. Section 01 33 00: Submittals: Schedule of Values.

4. Section 01 60 00: Material and Equipment: Product substitutions and options.

1.03 SCHEDULE OF VALUES

A. Submit a printed schedule on Contractor's standard form or electronic media printout.

B. Submit preliminary Schedule of Values in duplicate within 10 days after Effective Date of the Agreement.

C. Format: See Supplementary Conditions

D. Include in each line item, the amount of allowance. For unit cost allowances, identify quantities taken from Contract Documents multiplied by the unit cost to achieve the total for the item.

E. Include within each line item, a direct proportional amount of Contractor's overhead and profit.

F. Revise schedule to list approved Change Orders, with each Application for Payment.

1.04 APPLICATIONS FOR PAYMENT

A. Submit three (3) copies of each application on EJCDC Form C-620.

B. Content and Format: Utilize Schedule of Values for listing items in Application for Payment.

C. Payment Period: Monthly

D. Waiver of Liens or Contractor's Affidavit, Contractor's Release and Statement of Surety Company (with Final Payment Application only)

E. Include Payroll Certification forms with each Payment Application.

F. Include an updated construction progress schedule.

1.05 CHANGE PROCEDURES

A. Engineer will advise of minor changes in the Work not involving an adjustment to Contract Price or Contract Time as authorized by Paragraph 9.5 of the General Conditions by issuing supplemental instructions.

01 29 00-2

B. Engineer may issue a Proposal Request which includes a detailed description of a proposed change with supplementary or revised Drawings and specifications. Contractor will prepare and submit an estimate within 15 days relative to changes in Contract Price and/or Contract Time.

C. Contractor may propose changes by submitting a request for change to Engineer, describing the proposed change and its full effect on the Work. Include a statement describing the reason for the change, and the effect on the Contract Price and Contract Time with full documentation and a statement describing effect on Work by any other contractors. Document any requested substitutions in accordance with Section 01 60 00.

D. Stipulated Price Change Order: Based on Proposal Request and Contractor's fixed price quotation or Contractor's request for a Change Order as approved by Engineer.

E. Unit Price Change Order: For contract unit prices and quantities, the Change Order will be executed on a fixed unit price basis. For unit costs or quantities of units of work which are not predetermined, the Change Order will be executed based on Contractor's proposed unit prices and quantities of units as approved by Engineer.

F. Work Change Directive: Engineer may issue a directive, on EJCDC Form C-940 Work Change

Directive signed by Owner, instructing Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order. Document will describe changes in the Work, and designate method of determining any change in Contract Price or Contract Time. Promptly execute the change.

G. Time and Material Change Order: Submit itemized account and supporting data after completion of change, within time limits indicated in the Conditions of the Contract. Engineer will determine the change allowable in Contract Price and Contract Time as provided in the Contract Documents.

H. Maintain detailed records of Work done on Time and Material basis. Provide full information required for evaluation of proposed changes, and to substantiate costs for changes in the Work.

I. Change Order Form: Doc 00 63 63 Change Order.

J. Execution of Change Orders: Engineer will issue Change Orders for signatures of parties as provided in the Conditions of the Contract.

1.06 ALTERNATES

A. None

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION

File details come from the government source that posted it. Updated .