12-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf

PDF 109 KB Posted

Attached to
124 Easton Road Demolition 25-01189. 01
Solicitation number
Not on record
Issued by
Pennsylvania

About this file

This is a Material and Equipment specification document (Section 01 60 00) for a Pennsylvania state and local contract opportunity involving the demolition of the Shelby Apartments building located at 111-124 Easton Road, including associated concrete patios and asphalt parking lot, with environmental remediation and site restoration to match existing grading and stabilization. The specification establishes requirements for all materials and equipment to be used on the project, including products, transportation and handling procedures, storage and protection protocols, and provisions for product options and substitutions. Materials and equipment must comply with manufacturer instructions and contract document specifications; materials removed from existing premises are prohibited unless explicitly permitted. All products must be transported, handled, stored, and protected in accordance with manufacturer guidelines to prevent damage, soiling, or disfigurement, with sensitive products requiring weather-tight, climate-controlled storage and loose granular materials stored on solid, well-drained surfaces. Products must maintain intact seals and labels during storage and be arranged to permit periodic inspection.

The specification provides three categories for product specification: products meeting referenced standards or descriptions (allowing any compliant product), products specified by manufacturer name (no substitutions allowed), and products specified by manufacturer name with substitution provisions available. Substitution requests must be submitted during the bidding period as outlined in the Instructions to Bidders document and require submission of three copies with complete supporting documentation including shop drawings, product data, and certified test results demonstrating equivalence. The contractor bears the burden of proof for substitution compliance and must represent that the proposed product meets or exceeds quality standards, provide equal warranties, coordinate installation at no additional cost to the owner, and waive claims for additional costs or time extensions. The Engineer reserves the right to require use of listed manufacturers' equipment items for specified equipment and will provide written notification of substitution decisions.

View the file

Other files

File Type Posted
32-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
38-Doc 00 73 00 8 - Appendix C - 2700-FM-AQ0021 - Form.pdf PDF
8-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
23-Doc 00 73 00 4 - Appendix B - cover sht.pdf PDF
19-Doc 00 62 76 - Application for Payment.pdf PDF
36-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
25-Sec 31 23 33 - Excavation, Backfill and Compaction.pdf PDF
49-Doc 00 43 13 - BID BOND.pdf PDF
56-Doc 00 11 13 - ADVERTISEMENT FOR BIDS - 124 Easton Road Demo Revised.pdf PDF
14-Sec 02 41 16 - DEMOLITION.pdf PDF
39-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
51-Doc 00 73 00 3 - Appendix A - PA Wage Rate Determination.pdf PDF
18-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
3-Doc 00 73 00 14 - Appendix F - Universal Waste Report.pdf PDF
5-Doc 00 01 15 - TABLE OF CONTENTS - LIST OF DRAWINGS.pdf PDF
17-Sec 01 33 00 - SUBMITTALS.pdf PDF
6-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
9-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID - 2025.pdf PDF
47-Doc 00 73 00 12 - Appendix E - lead rpt-final.pdf PDF
26-Doc 00 65 19.16 - SUBCONTRACTORS RELEASE OF LIENS.pdf PDF
24-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
53-Doc 00 73 00 13 - Appendix F - cover sht.pdf PDF
43-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
54-Doc 00 01 10 - TABLE OF CONTENTS.pdf PDF
29-Doc 00 73 00 10 - Appendix D - ACM Survey Rpt-final.pdf PDF
40-Doc 00 73 00 7 - Appendix C - 2700-FM-AQ0021 - Instructions.pdf PDF
55-X 124 Easton Road Bid Set.pdf PDF
21-Doc 00 73 00 6 - Appendix C - cover sht.pdf PDF
4-Sec 01 57 13 Soil Erosion and Sediment Control.pdf PDF
2-Doc 00 91 13 - ADDENDA.pdf PDF
48-Sec 32 92 00 - Finish Grading, Seeding and Sodding.pdf PDF
35-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
27-Doc 00 45 10 - BIDDER’S ACKNOWLEDGEMENT FORM.pdf PDF
34-Doc 00 63 63 - Change Order.pdf PDF
28-Doc 00 73 00 9 - Appendix D - cover sht.pdf PDF
22-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
31-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
16-Doc 00 65 19.13 - SUBCONTRACTORS AFFIDAVIT.pdf PDF
46-Doc 00 73 00 2 - Appendix A - cover sht.pdf PDF
11-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
1-Sec 01 56 39. - LANDSCAPE PROTECTION.pdf PDF
13-Doc 00 21 13.1-Instr for Electronic Bidding.pdf PDF
42-Doc 00 73 00 5 - Appendix B - Public Works Employment Verification Form.pdf PDF
45-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
7-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
15-Doc 00 21 13.2 - PennBid - How To Submit a Bid.pdf PDF
33-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
37-Doc 00 41 00 - BID FORM - EBID.pdf PDF
50-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
44-Doc 00 73 00 11 - Appendix E - cover sht.pdf PDF
Show 40 more

Latest 50 of 55 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MATERIAL AND EQUIPMENT

01 60 00-1

SECTION 01 60 00

PART 1 - GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Products.

2. Transportation and handling.

3. Storage and protection.

4. Product options.

5. Substitutions.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Document 00 21 13: Instructions to Bidders.

2. Section 01 40 00: Quality Control.

1.03 PRODUCTS

A. Do not use materials and equipment removed from existing premises, except as specifically permitted by the Contract Documents.

B. Provide interchangeable components of the same manufacturer for components being replaced.

1.04 TRANSPORTATION AND HANDLING

A. Transport and handle Products in accordance with manufacturer's instructions.

B. Promptly inspect shipments to assure that Products comply with requirements, quantities are correct, and Products are undamaged.

C. Provide equipment and personnel to handle Products by methods to prevent soiling, disfigurement, or damage.

1.05 STORAGE AND PROTECTION

A. Store and protect Products in accordance with manufacturers’ instructions.

B. Store with seals and labels intact and legible.

C. Store sensitive Products in weather tight, climate controlled, enclosures in an environment favorable to Product.

D. For exterior storage of fabricated Products, place on sloped supports above ground.

E. Provide off-site storage and protection when site does not permit on-site storage or protection.

F. Cover Products subject to deterioration with impervious sheet covering. Provide ventilation to prevent condensation and degradation of Products.

G. Store loose granular materials on solid flat surfaces in a well-drained area. Prevent mixing with foreign matter.

H. Provide equipment and personnel to store Products by methods to prevent soiling, disfigurement, or damage.

01 60 00-2

I. Arrange storage of Products to permit access for inspection. Periodically inspect to assure Products are undamaged and are maintained under acceptable condition.

1.06 PRODUCT OPTIONS

A. Products Specified by Reference Standards or by Description Only: Any product meeting those standards or description.

B. Products Specified by Naming One or More Manufacturers: Products of manufacturers named and meeting specifications, no options or substitutions allowed.

C. Products Specified by Naming One or More Manufacturers with a Provision for Substitutions:

Submit a request for substitution for any manufacturer not named in accordance with the following Article.

1.07 SUBSTITUTIONS

A. Instructions to Bidders specify time restrictions for submitting requests for Substitutions during the bidding period to requirements specified in this section.

B. Substitutions may be considered when a Product becomes unavailable through no fault of the Contractor.

C. Document each request with complete data substantiating compliance of proposed Substitution with Contract Documents.

D. A request constitutes a representation that Contractor:

1. Has investigated proposed Product and determined that it meets or exceeds the quality level of the specified Product.

2. Will provide the same warranty for the Substitution as for the specified Product.

3. Will coordinate installation and make changes to other Work which may be required for the Work to be complete with no additional cost to Owner.

4. Waives claims for additional costs or time extension which may subsequently become apparent.

5. Will reimburse Owner and Engineer for review or redesign services associated with re-approval by authorities.

E. Substitutions will not be considered when they are indicated or implied on shop drawing or Product data submittals, without separate written request, or when acceptance will require revision to the Contract Documents.

F. Substitution Submittal Procedure:

1. Submit three copies of request for Substitution for consideration. Limit each request to one (1) proposed Substitution.

2. Submit Shop Drawings, Product data, and certified test results attesting to the proposed Product equivalence. Burden of proof is on proposer.

3. Engineer will notify Contractor in writing of decision to accept or reject request.

G. For each equipment item in which the manufacturer was listed on the Bid Form, Engineer reserves the right to require Contractor to use the equipment item of the listed manufacturer.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION

File details come from the government source that posted it. Updated .