11-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf
PDF 91 KB Posted
- Attached to
- 124 Easton Road Demolition 25-01189. 01
- Solicitation number
- Not on record
- Issued by
- Pennsylvania
About this file
This is a Contract Closeout specification document (Section 01 70 00) for a Pennsylvania state and local contract opportunity involving the demolition of Shelby Apartments (111-124 Easton Road) and associated site restoration. The specification outlines the procedures and requirements contractors must follow during project closeout, including final cleaning, equipment adjustment, and submission of project documentation. The work encompasses execution of final cleaning procedures prior to project inspection, adjustment of all operating products and equipment to ensure proper functionality, maintenance of on-site record documents that accurately reflect actual revisions and products installed, and removal of all waste materials and construction facilities from the site. Contractors must submit written certification that the work is complete and ready for engineer review, comply with any punchlist items identified during final inspection, and complete all remaining items within the established contract time before final payment authorization.
Prior to final payment, contractors are required to submit comprehensive documentation including maintained record sets of all drawings, specifications, addenda, change orders, shop drawings, and manufacturer instructions with legible notations of actual products installed and field changes. Additional documentation must include payroll certifications, waivers of liens from all subcontractors and suppliers, maintenance bonds, any outstanding change orders with supporting documentation, and test or sample results as reasonably required by the engineer. Final payment will not be authorized until final completion and acceptance of work is confirmed, and all project record documents must be submitted with the final Application for Payment to the engineer for review and approval.
View the file
Other files
Show 40 more
Latest 50 of 55 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT CLOSEOUT
01 70 00-1
SECTION 01 70 00
PART 1 GENERAL
1.01 SECTION DESCRIPTION
A. The Work of This Section Includes:
1. Closeout procedures.
2. Final cleaning.
3. Adjusting.
4. Project record documents.
5. Operation and maintenance manual.
6. Spare parts and maintenance Products.
7. Other documentation.
1.02 RELATED SECTIONS
A. Related Work Specified Elsewhere:
1. Section 01 50 00: Construction Facilities and Temporary Controls: Progress cleaning.
1.03 CLOSEOUT PROCEDURES
A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for Engineer's review.
B. Engineer shall make a final inspection and prepare a punchlist of items remaining to be completed or corrected prior to final acceptance in accordance with Article 14, paragraph
14.06 of the General Conditions.
C. Complete all items on the punchlist, plus any new items that may be subsequently added, as soon as possible and within the Contract Time.
D. Provide submittals to Engineer that are required by governing or other authorities.
E. Submit final Application for Payment identifying total adjusted Contract Price, previous payments, and remaining amount due.
F. Final Payment will not be made until final completion and acceptance of the Work.
1.04 FINAL CLEANING
A. Execute final cleaning prior to final Project inspection.
B. Clean equipment and fixtures to a sanitary condition with cleaning materials appropriate to the surface and material being cleaned.
C. Clean or replace filters of operating equipment.
D. Clean debris from gutters and drainage systems.
E. Clean site; sweep paved areas, rake clean landscaped surfaces.
F. Remove waste and surplus materials, rubbish, and construction facilities from the site.
1.05 ADJUSTING
A. Adjust operating Products and equipment to ensure smooth and unhindered operation.
01 70 00-2
1.06 PROJECT RECORD DOCUMENTS
A. Maintain on-site one set of the following record documents; record actual revisions to the Work:
1. Drawings and Specifications.
2. Addenda.
3. Change Orders and other modifications to the Contract.
4. Reviewed Shop Drawings, Product data, and samples.
5. Manufacturer’s instructions for assembly, installation and adjusting.
B. Ensure entries are complete and accurate, enabling future reference by Owner.
C. Store record documents separate from documents used for construction.
D. Record information concurrent with construction progress.
E. Specifications: Legibly mark and record at each Product section description of actual Products installed, including the following:
1. Manufacturer's name and product model and number.
2. Product substitutions or alternates utilized.
3. Changes made by Addenda and modifications.
F. Record Drawings and Shop Drawings: Legibly mark each item to record actual construction including:
1. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.
2. Field changes of dimension and detail.
3. Details not on original Contract Drawings.
G. Submit documents to Engineer with claim for final Application for Payment.
1.07 OTHER DOCUMENTATION
A. Provide data and documentation properly completed and executed prior to final Application for Payment as Engineer may reasonably require including:
1. Payroll Certification forms by Contractor and all Subcontractors (if price exceeds $25,000).
2. Waiver of Liens by all Subcontractors and Suppliers or Contractor's Affidavit, Contractor's Release of Liens and Consent of Surety to Final Payment.
3. Maintenance Bond.
4. Any Change Orders with supporting documentation which remain to be submitted.
5. Test and/or sample results.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION