11-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf

PDF 91 KB Posted

Attached to
124 Easton Road Demolition 25-01189. 01
Solicitation number
Not on record
Issued by
Pennsylvania

About this file

This is a Contract Closeout specification document (Section 01 70 00) for a Pennsylvania state and local contract opportunity involving the demolition of Shelby Apartments (111-124 Easton Road) and associated site restoration. The specification outlines the procedures and requirements contractors must follow during project closeout, including final cleaning, equipment adjustment, and submission of project documentation. The work encompasses execution of final cleaning procedures prior to project inspection, adjustment of all operating products and equipment to ensure proper functionality, maintenance of on-site record documents that accurately reflect actual revisions and products installed, and removal of all waste materials and construction facilities from the site. Contractors must submit written certification that the work is complete and ready for engineer review, comply with any punchlist items identified during final inspection, and complete all remaining items within the established contract time before final payment authorization.

Prior to final payment, contractors are required to submit comprehensive documentation including maintained record sets of all drawings, specifications, addenda, change orders, shop drawings, and manufacturer instructions with legible notations of actual products installed and field changes. Additional documentation must include payroll certifications, waivers of liens from all subcontractors and suppliers, maintenance bonds, any outstanding change orders with supporting documentation, and test or sample results as reasonably required by the engineer. Final payment will not be authorized until final completion and acceptance of work is confirmed, and all project record documents must be submitted with the final Application for Payment to the engineer for review and approval.

View the file

Other files

File Type Posted
32-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
38-Doc 00 73 00 8 - Appendix C - 2700-FM-AQ0021 - Form.pdf PDF
8-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
23-Doc 00 73 00 4 - Appendix B - cover sht.pdf PDF
19-Doc 00 62 76 - Application for Payment.pdf PDF
36-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
25-Sec 31 23 33 - Excavation, Backfill and Compaction.pdf PDF
49-Doc 00 43 13 - BID BOND.pdf PDF
56-Doc 00 11 13 - ADVERTISEMENT FOR BIDS - 124 Easton Road Demo Revised.pdf PDF
14-Sec 02 41 16 - DEMOLITION.pdf PDF
39-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
51-Doc 00 73 00 3 - Appendix A - PA Wage Rate Determination.pdf PDF
18-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
3-Doc 00 73 00 14 - Appendix F - Universal Waste Report.pdf PDF
5-Doc 00 01 15 - TABLE OF CONTENTS - LIST OF DRAWINGS.pdf PDF
17-Sec 01 33 00 - SUBMITTALS.pdf PDF
6-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
9-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID - 2025.pdf PDF
47-Doc 00 73 00 12 - Appendix E - lead rpt-final.pdf PDF
26-Doc 00 65 19.16 - SUBCONTRACTORS RELEASE OF LIENS.pdf PDF
24-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
53-Doc 00 73 00 13 - Appendix F - cover sht.pdf PDF
43-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
54-Doc 00 01 10 - TABLE OF CONTENTS.pdf PDF
12-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
29-Doc 00 73 00 10 - Appendix D - ACM Survey Rpt-final.pdf PDF
40-Doc 00 73 00 7 - Appendix C - 2700-FM-AQ0021 - Instructions.pdf PDF
55-X 124 Easton Road Bid Set.pdf PDF
21-Doc 00 73 00 6 - Appendix C - cover sht.pdf PDF
4-Sec 01 57 13 Soil Erosion and Sediment Control.pdf PDF
2-Doc 00 91 13 - ADDENDA.pdf PDF
48-Sec 32 92 00 - Finish Grading, Seeding and Sodding.pdf PDF
35-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
27-Doc 00 45 10 - BIDDER’S ACKNOWLEDGEMENT FORM.pdf PDF
34-Doc 00 63 63 - Change Order.pdf PDF
28-Doc 00 73 00 9 - Appendix D - cover sht.pdf PDF
22-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
31-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
16-Doc 00 65 19.13 - SUBCONTRACTORS AFFIDAVIT.pdf PDF
46-Doc 00 73 00 2 - Appendix A - cover sht.pdf PDF
1-Sec 01 56 39. - LANDSCAPE PROTECTION.pdf PDF
13-Doc 00 21 13.1-Instr for Electronic Bidding.pdf PDF
42-Doc 00 73 00 5 - Appendix B - Public Works Employment Verification Form.pdf PDF
45-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
7-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
15-Doc 00 21 13.2 - PennBid - How To Submit a Bid.pdf PDF
33-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
37-Doc 00 41 00 - BID FORM - EBID.pdf PDF
50-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
44-Doc 00 73 00 11 - Appendix E - cover sht.pdf PDF
Show 40 more

Latest 50 of 55 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT CLOSEOUT

01 70 00-1

SECTION 01 70 00

PART 1 GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Closeout procedures.

2. Final cleaning.

3. Adjusting.

4. Project record documents.

5. Operation and maintenance manual.

6. Spare parts and maintenance Products.

7. Other documentation.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Section 01 50 00: Construction Facilities and Temporary Controls: Progress cleaning.

1.03 CLOSEOUT PROCEDURES

A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for Engineer's review.

B. Engineer shall make a final inspection and prepare a punchlist of items remaining to be completed or corrected prior to final acceptance in accordance with Article 14, paragraph

14.06 of the General Conditions.

C. Complete all items on the punchlist, plus any new items that may be subsequently added, as soon as possible and within the Contract Time.

D. Provide submittals to Engineer that are required by governing or other authorities.

E. Submit final Application for Payment identifying total adjusted Contract Price, previous payments, and remaining amount due.

F. Final Payment will not be made until final completion and acceptance of the Work.

1.04 FINAL CLEANING

A. Execute final cleaning prior to final Project inspection.

B. Clean equipment and fixtures to a sanitary condition with cleaning materials appropriate to the surface and material being cleaned.

C. Clean or replace filters of operating equipment.

D. Clean debris from gutters and drainage systems.

E. Clean site; sweep paved areas, rake clean landscaped surfaces.

F. Remove waste and surplus materials, rubbish, and construction facilities from the site.

1.05 ADJUSTING

A. Adjust operating Products and equipment to ensure smooth and unhindered operation.

01 70 00-2

1.06 PROJECT RECORD DOCUMENTS

A. Maintain on-site one set of the following record documents; record actual revisions to the Work:

1. Drawings and Specifications.

2. Addenda.

3. Change Orders and other modifications to the Contract.

4. Reviewed Shop Drawings, Product data, and samples.

5. Manufacturer’s instructions for assembly, installation and adjusting.

B. Ensure entries are complete and accurate, enabling future reference by Owner.

C. Store record documents separate from documents used for construction.

D. Record information concurrent with construction progress.

E. Specifications: Legibly mark and record at each Product section description of actual Products installed, including the following:

1. Manufacturer's name and product model and number.

2. Product substitutions or alternates utilized.

3. Changes made by Addenda and modifications.

F. Record Drawings and Shop Drawings: Legibly mark each item to record actual construction including:

1. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.

2. Field changes of dimension and detail.

3. Details not on original Contract Drawings.

G. Submit documents to Engineer with claim for final Application for Payment.

1.07 OTHER DOCUMENTATION

A. Provide data and documentation properly completed and executed prior to final Application for Payment as Engineer may reasonably require including:

1. Payroll Certification forms by Contractor and all Subcontractors (if price exceeds $25,000).

2. Waiver of Liens by all Subcontractors and Suppliers or Contractor's Affidavit, Contractor's Release of Liens and Consent of Surety to Final Payment.

3. Maintenance Bond.

4. Any Change Orders with supporting documentation which remain to be submitted.

5. Test and/or sample results.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION