7-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf

PDF 93 KB Posted

Attached to
124 Easton Road Demolition 25-01189. 01
Solicitation number
Not on record
Issued by
Pennsylvania

About this file

This is a Measurement and Payment specification document for the 124 Easton Road Demolition project in Pennsylvania (Contract 25-01189.01). The document establishes the procedures and standards for measuring and paying for demolition work, including the removal of the Shelby Apartments building at 111-124 Easton Road, associated concrete patios, asphalt parking lot, and environmental remediation within the structure. The specification outlines measurement methodologies for various demolition activities, material removal, site restoration to match existing grading, and site stabilization requirements. Payment is structured based on completed work items measured according to specified standards, with compensation tied to the actual quantities of work performed and materials removed as verified by project inspection and measurement protocols.

The payment terms are contingent upon proper documentation and verification of completed work according to the measurement standards outlined in the specification. The document establishes the framework for contractor compensation based on unit prices or lump sum amounts for identified work items, ensuring that payment corresponds directly to measurable completion of demolition, environmental remediation, and site restoration activities. All payment is subject to compliance with measurement verification procedures and project specifications to ensure work quality and scope completion prior to final compensation.

View the file

Other files

File Type Posted
32-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
38-Doc 00 73 00 8 - Appendix C - 2700-FM-AQ0021 - Form.pdf PDF
8-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
23-Doc 00 73 00 4 - Appendix B - cover sht.pdf PDF
19-Doc 00 62 76 - Application for Payment.pdf PDF
36-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
25-Sec 31 23 33 - Excavation, Backfill and Compaction.pdf PDF
49-Doc 00 43 13 - BID BOND.pdf PDF
56-Doc 00 11 13 - ADVERTISEMENT FOR BIDS - 124 Easton Road Demo Revised.pdf PDF
14-Sec 02 41 16 - DEMOLITION.pdf PDF
39-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
51-Doc 00 73 00 3 - Appendix A - PA Wage Rate Determination.pdf PDF
18-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
3-Doc 00 73 00 14 - Appendix F - Universal Waste Report.pdf PDF
5-Doc 00 01 15 - TABLE OF CONTENTS - LIST OF DRAWINGS.pdf PDF
17-Sec 01 33 00 - SUBMITTALS.pdf PDF
6-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
9-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID - 2025.pdf PDF
47-Doc 00 73 00 12 - Appendix E - lead rpt-final.pdf PDF
26-Doc 00 65 19.16 - SUBCONTRACTORS RELEASE OF LIENS.pdf PDF
24-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
53-Doc 00 73 00 13 - Appendix F - cover sht.pdf PDF
43-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
54-Doc 00 01 10 - TABLE OF CONTENTS.pdf PDF
12-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
29-Doc 00 73 00 10 - Appendix D - ACM Survey Rpt-final.pdf PDF
40-Doc 00 73 00 7 - Appendix C - 2700-FM-AQ0021 - Instructions.pdf PDF
55-X 124 Easton Road Bid Set.pdf PDF
21-Doc 00 73 00 6 - Appendix C - cover sht.pdf PDF
4-Sec 01 57 13 Soil Erosion and Sediment Control.pdf PDF
2-Doc 00 91 13 - ADDENDA.pdf PDF
48-Sec 32 92 00 - Finish Grading, Seeding and Sodding.pdf PDF
35-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
27-Doc 00 45 10 - BIDDER’S ACKNOWLEDGEMENT FORM.pdf PDF
34-Doc 00 63 63 - Change Order.pdf PDF
28-Doc 00 73 00 9 - Appendix D - cover sht.pdf PDF
22-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
31-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
16-Doc 00 65 19.13 - SUBCONTRACTORS AFFIDAVIT.pdf PDF
46-Doc 00 73 00 2 - Appendix A - cover sht.pdf PDF
11-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
1-Sec 01 56 39. - LANDSCAPE PROTECTION.pdf PDF
13-Doc 00 21 13.1-Instr for Electronic Bidding.pdf PDF
42-Doc 00 73 00 5 - Appendix B - Public Works Employment Verification Form.pdf PDF
45-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
15-Doc 00 21 13.2 - PennBid - How To Submit a Bid.pdf PDF
33-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
37-Doc 00 41 00 - BID FORM - EBID.pdf PDF
50-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
44-Doc 00 73 00 11 - Appendix E - cover sht.pdf PDF
Show 40 more

Latest 50 of 55 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MEASUREMENT AND PAYMENT

01 22 00-1

SECTION 01 22 00

MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.01. SECTION INCLUDES

A. Measurement and payment criteria applicable to the Work performed under a unit price payment method.

1.02. PROCEDURE

A. All measurements for payment will be based on completed work, performed in strict accordance with the Drawings and Project Manual, and with the Agreement’s “Schedule of Bid Items”.

B. The Resident Project Representative shall take all measurements and compute quantities relative to all work completed under the Agreement in accordance with the methods included in this section. CONTRACTOR shall assist by providing necessary equipment and personnel as required.

C. In cases where the payment clause for an item in this section relating to any unit or lump sum price requires that the said unit or lump sum price cover and be considered compensation for certain work or material essential to the item, this same work or material shall not be measured or paid for under any other item which may appear elsewhere in this section.

PART 2 - PRODUCTS

Not Used

PART 3 - EXECUTION

3.01. DEMOLITION

A. Measurement is lump sum and constitutes furnishing all materials and equipment necessary to complete the work associated with this contract.

B. Payment shall be made at the contract unit price as determined in the Bid Schedule and in accordance with the schedule specified in Section 02 41 16 “Demolition”. This is a lump sum item for the entire contract. This price shall include furnishing all materials, labor and equipment necessary to complete the work associated with this contract. This item shall include demolition, removal and disposal of all buildings, including foundation slabs, concrete patio, and asphalt as necessary to complete the work. Backfill shall be free of debris, compacted, and free of voids so that settlement doesn’t occur.

3.02. ASBESTOS ABATEMENT

A. Measurement is lump sum and constitutes furnishing all materials and equipment necessary to complete the work associated with this contract and submission of PADEP form 2700-FM- BAQ0021. See Supplemental Conditions Appendix C for the DEP form and Appendix D for the Phase II report for the buildings.

B. Payment shall be made at the contract unit price listed in the Bid Schedule. This price shall include furnishing all materials, labor and equipment necessary to complete the work associated with this contract. This item shall include demolition, removal and disposal of asbestos containing material as necessary to complete the work. This item also includes

MEASUREMENT AND PAYMENT

01 22 00-2 submission of an Asbestos Abatement Specification by the CONTRACOR, for review and approval by the OWNER fourteen (14) days prior to the start of work.

3.03. TOPSOIL

A. There will be no separate line item for topsoil. The topsoil is to be placed in all areas where buildings, patios, retaining walls etc. have been removed. Topsoil shall be placed to provide proper drainage per direction of the Engineer. This shall be for furnishing all labor, materials, and equipment necessary for the installation and fine grading of the topsoil. Topsoil shall be in accordance with Section 32 92 00. All topsoil required to compete the work shall be included.

Payment for topsoil will not be made as it will be made incidental to all other work.

3.04. PERMANENT VEGETATION

A. There will be no separate line item for permanent vegetation. This shall constitute furnishing all labor, materials, equipment, to rake, seed, and fertilize mulch to establish vegetation for all disturbed areas and as directed by the Engineer. Work shall be in accordance with Section 32 92 00. All vegetation required to compete the work shall be included in this item. Payment for permanent vegetation will not be made as it will be made incidental to all other work.

3.05. HAULING AND DISPOSAL OF MATERIAL

A. There will be no separate line item for hauling of demolished and/or waste material from the site. There will be no separate line item for disposal of demolished and/or waste material.

Hauling and disposal includes all labor, materials, equipment, fees and permits to remove all demolished and/or waste material from the site and for proper disposal at a permitted facility.

The OWNER has not arranged a facility for disposal. Contractor shall be responsible for proper disposal of all demolished and/or waste materials. No demolished and/or waste material shall remain on the project site. Payment for hauling and disposal of material will not be made as hauling and disposal of material will be made incidental to all other work.

3.06. HAZARDOUS WASTE REMOVAL

A. Measurement is lump sum and constitutes furnishing all materials and equipment necessary to complete the work associated with this contract and submission of the following

(i) Site Specific Health and Safety Plan

(ii) 40 CFR 761 – Certificate of Disposal and/or Recycling.

(iii) Transporter certification of notification to EPA of their PCB waste activities (EPA Form 7710-53). See Appendix D for the Phase II report for the buildings.

B. Payment shall be made at the contract unit price listed in the Bid Schedule. This price shall include furnishing all materials, labor and equipment necessary to complete the work associated with this contract. This item shall include removal and disposal of hazardous materials as necessary to complete the work. This item also includes submission of the items listed above, for review and approval by the OWNER fourteen (14) days prior to the start of work.

END OF SECTION

File details come from the government source that posted it. Updated .