This document is a Standard Form 30 Amendment of Solicitation/Modification of Contract for a seed project, issued by the Division of Engineering Services in Seattle. The amendment, numbered A000013, is dated 12/01/2025 with the solicitation number 75H70125R00033. The primary purposes of this amendment are to replace the Wage Determination and provide responses to vendor questions about specific project details.
The amendment includes detailed clarifications on concrete specifications: minimum concrete strength is 3,500 psi, concrete slab thickness is 4 inches, and concrete testing is required at 7, 14, and 28 days. Additional vendor questions were addressed, including Buy American requirements for rebar (contractors must meet legal requirements, and epoxy-coated reinforcement is not required) and ADA sidewalk ramp specifications (the ramp shall include a warning pad). The wage determination attachment dated 01/03/2025 was replaced with a new version dated 11/21/2025.
View the file
Other files for this federal contract opportunity
Show all 47
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
A000013
The reason for this amendment is to replace the Wage Determination and to provide responses to vendor questions.
See Attached Summary of Changes
Division of Eng. Services Seattle 701 Fifth Avenue, Suite 1600 Seattle WA 98104
See block 6
75H70125R00033
1 2
12/01/2025
09/16/2025
SUMMARY OF CHANGES
75H70125R00033
A. Replace Section J Attachment 5.6 Seed Project Wage Determination dated 01/03/2025 with the attached Attachment 5.6 Seed Project Wage Determination dated 11/21/2025.
B. Provide the following Questions/Responses:
1. Please confirm the required concrete strength specification (e.g., 3,000 psi, 4,000 psi, 4,500 psi, M6, etc.).
Response: Minimum 3500 psi.
2. Is concrete testing required (such as cylinder tests)? If so, please clarify the required testing schedule
(e.g., at pour, 24 hours, 7 days, 14 days, and 28 days).
Response: Testing at 7, 14, 28 days. Contractors are required to perform all testing.
3. Please confirm the required concrete slab thickness.
Response: 4 inches thick
4. Does the rebar need to be U.S.‐made to meet Buy American requirements, and is epoxy‐coated reinforcement required?
Response: Contractors are required to meet all Buy American requirements as prescribed by law. Epoxy coated reinforcement is not required.
5. Please confirm whether the ADA ramps are specified as steel or plastic.
Response: There is no stand‐alone ramp. The ADA sidewalk ramp shall have a warning pad.