B01 Section J Attachment 5.8 Infection Control Risk Assessment.docx

DOCX document 38 KB Posted

Attached to
IHS Nationwide Multiple Award Task Order Contract Federal contract opportunity
Solicitation number
75H70125R00033
Issued by
Department of Health and Human Services Indian Health Service

About this file

This document is an Infection Control Risk Assessment (ICRA) template for construction and renovation projects in healthcare facilities. The comprehensive 13-step form provides a systematic approach to evaluating and mitigating infection risks during various construction activities, categorizing project types from Type A (non-invasive inspection) to Type D (major demolition and construction), and patient risk groups from low to highest risk.

The ICRA matrix details specific infection control precautions across four classes (I-IV), with increasing levels of complexity and containment requirements. Key elements include identifying construction activity types, assessing patient risk groups, establishing critical barriers, managing HVAC systems, maintaining negative air pressure, using HEPA filtration, implementing personnel protective measures, and ensuring thorough cleaning and waste management procedures. The document is designed to help healthcare facilities minimize infection transmission risks during construction and renovation projects by providing a structured, detailed framework for project planning and execution.

View the file

Other files for this federal contract opportunity

Other files attached to IHS Nationwide Multiple Award Task Order Contract, newest first.
File Type Posted
B05 75H70125R00033 Amendment 13.pdf PDF
B01 Section J Attachment 5.6 Seed Project Wage Determination dated 11-21-2025.pdf PDF
B05 75H70125R00033 Amendment 12.pdf PDF
B01 Section J Attachment 5.5 Updated Construction Drawings Amendment 11.pdf PDF
B01 Section J Attachment 5.3 Updated Seed Project SOW Amendment 11.pdf PDF
B01 Section J Attachment 5.13 Kyle EOC Modernization All Doors - Combined.pdf PDF
B01 Section J Attachment 5.7 Updated Kyle Door Schedule Amendment 11.xlsx XLSX spreadsheet
B01 Section J Attachment 5.2 Updated Seed Project Price Schedule Amendment 11.xlsx XLSX spreadsheet
B05 75H70125R00033 Amendment 11.pdf PDF
B01 Section J Attachment 5.3 Updated Seed Project SOW Amendment 10.pdf PDF
B05 75H70125R00033 Amendment 10.pdf PDF
B05 Section J Attachment 5.5 Updated Construction Drawings Amendment 09.pdf PDF
B05 75H70125R00033 Amendment 09.pdf PDF
B01 Section J Attachment 5.3 Updated Seed Project SOW Amendment 09.pdf PDF
B03 Site Visit Sign in Sheet.pdf PDF
B01 Section J Attachment 5.9 Flooring Finish.pdf PDF
B01 Section J Attachment 5.11 Pre-Construction Risk Assessment.docx DOCX document
B01 Section J Attachment 5.7 Updated Kyle Door Schedule Amendment 08.xlsx XLSX spreadsheet
B05 75H70125R00033 Amendment 08.pdf PDF
B01 Section J Attachment 5.12 Turf Area - Current Conditions.jpg JPG image
B01 Section J Attachment 5.10 Kyle Floor Plan with Room Numbers.pdf PDF
B01 Section J Attachment 5.3 Updated Seed Project SOW Amendment 08.pdf PDF
B01 Section J Attachment 5.2 Updated Seed Project Price Schedule Amendment 08.xlsx XLSX spreadsheet
B01 Section J Attachment 5.5 Updated Construction Drawings Amendment 08.pdf PDF
B05 75H70125R00033 Amendment 07.pdf PDF
B01 Section J Attachment 5.2 - Updated Seed Project Price Schedule - Amendment 06.xlsx XLSX spreadsheet
B05 75H70125R00033 Amendment 06.pdf PDF
Attachment 5.7 - Kyle Door Schedule.pdf PDF
B05 75H70125R00033 Amendment 05.pdf PDF
B01 Section J Attachment 5.3 Updated Seed Project SOW.pdf PDF
B05 75H70125R00033 Amendment 04.pdf PDF
B01 Section J Attachment 5.2 - Updated Seed Project Price Schedule.xlsx XLSX spreadsheet
B05 75H70125R00033 Amendment 03.pdf PDF
B05 75H70125R00033 Amendment 02.pdf PDF
B05 75H70125R00033 Amendment 01.pdf PDF
B01 Section J Attachment 1 - PPQ.docx DOCX document
B01 Section J Attachment 5.6 Seed Project Wage Decision SD20250017.pdf PDF
B01 Section J Attachment 5.2 - Seed Project Price Schedule.xlsx XLSX spreadsheet
B01 75H70125R00033.pdf PDF
B01 Section J Attachment 5.4 - Kyle ICRA Map.pdf PDF
B01 Section J Attachment 6 IHS IEE Representation Form.pdf PDF
B01 Section J Attachment 5.5 Construction Drawings.pdf PDF
B01 Section J Attachment 5.3 Seed Project SOW.pdf PDF
B01 Section J Attachment 5.1 - Self Performance Calculation Sheet - Seed Project.docx DOCX document
B01 Section J Attachment 4 - Financial Institution Reference Sheet.pdf PDF
B01 Section J Attachment 3 - Experience Form.docx DOCX document
B01 Section J Attachment 2 - Contractor Surety Information.docx DOCX document
Show all 47

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section 2E. Infection Control Risk Assessment Project Title:

Staff/Cont. Name:

Start Date:

Supervisor Name:

Estimated Duration:

Version: September 18th, 2019

Building:
Floor(s):
Department Name(s):
Room Number(s) & Description(s)

Project Description: (include specific sites and tasks)

Infection Control Risk Assessment Matrix of Precautions for Construction & Renovation

Step 1: Using the following table, identify the Type of Construction Project Activity (Type A-D)

TYPE A
Inspection and Non-Invasive Activities.

Includes, but is not limited to:

· removal of ceiling tiles for visual inspection only, e.g., limited to 1 tile per 50 square feet

· painting (but not sanding)

· wallcovering, electrical trim work, minor plumbing, and activities which do not generate dust or require cutting of walls or access to ceilings other than for visual inspection.

TYPE B
Small scale, short duration activities which create minimal dust

Includes, but is not limited to:

· installation of telephone and computer cabling

· access to chase spaces

· cutting of walls or ceiling where dust migration can be controlled.

TYPE C
Work that generates a moderate to high level of dust or requires demolition or removal of any fixed building components or assemblies

Includes, but is not limited to:

· sanding of walls for painting or wall covering

· removal of floorcoverings, ceiling tiles and casework

· new wall construction

· minor duct work or electrical work above ceilings

· major cabling activities

· any activity which cannot be completed within a single workshift.

TYPE D
Major demolition and construction projects

Includes, but is not limited to:

· activities which require consecutive work shifts

· requires heavy demolition or removal of a complete cabling system

· new construction.

Step 2: Using the following table, identify the Patient Risk Groups that will be affected.

Low Risk
Medium Risk
Medium-High Risk
Highest Risk

· Office areas

· Nonpatient-care areas not otherwise specified (NOS)

· Cardiology

· Echocardiography

· Endoscopy

· Local Room

· Physical Therapy

· Radiology/MRI

· Respiratory Therapy

· Infusion Clinic

· Orthopedic Clinic

· Emergency Room

· Labor & Delivery

· Laboratories (specimen)

· Medical Units

· Newborn Nursery

· Outpatient Surgery

· Pediatrics

· Pharmacy

· Post Anesthesia Care Unit

· Any area caring for immunocompromised patients

· Central Sterile Supply

· Intensive Care Units

· Negative pressure isolation rooms

· Operating rooms including C-section rooms

If more than one risk group will be affected, select the higher risk group:

Step 3: Match the following;

Patient Risk Group (Low, Medium, High, Highest) with the planned … Construction Project Type (A, B, C, D) on the following matrix, to find the … Class of Precautions (I, II, III or IV) or level of infection control activities required.

Type of Construction

Patient Risk Group
Type A
Type B
Type C
Type D
Low Risk Group
I
II
II
III/IV
Medium Risk Group
I
II
III
IV
Medium-High Risk Group
I
II
III/IV
IV
Highest Risk Group
I –III

Consult ICP

III/IV
III/IV
IV
Class of IC Measures
Class I

Class II

Class III*

Class IV*

* Note Infection Preventionist approval will be required when the Construction Activity and Risk Level indicate that Class III or Class IV control procedures are necessary.

Description of Required Infection Control Precautions by Class

Before Construction
During Construction Project
Upon Completion of Project
CLASS I
1. Notify Department Supervisor

1. Execute work by methods to minimize raising dust from construction operations.

2. Immediately replace a ceiling tile displaced for visual inspection

1. Clean work area upon completion of task.

CLASS II
1. Notify Department Supervisor
1. Provide active means to prevent airborne dust from dispersing into atmosphere.

2. Water mist work surfaces to control dust while cutting.

3. Seal unused doors with duct tape.

4. Block off and seal air vents.

5. Place dust mat at entrance and exit of work area

6. Remove or isolate HVAC system in areas where work is being performed.

1. Wipe work surfaces with cleaner/disinfectant.

2. Contain construction waste before transport in tightly covered containers.

3. Wet mop and/or vacuum with HEPA filtered vacuum before leaving work area.

4. Upon completion, restore HVAC system where work was performed.

CLASS III
1. Contact Housekeeping Supervisor to schedule Post-work cleaning

2. Review ICRA with Department Supervisor(s)

1. Remove or Isolate HVAC system in area where work is being done to prevent contamination of duct system.

2. Complete all critical barriers i.e. sheetrock, plywood, plastic, to seal area from non-work area or implement control cube method (cart with plastic covering and sealed connection to work site with HEPA vacuum for vacuuming prior to exit) before construction begins.

3. Maintain negative air pressure within work site utilizing HEPA equipped air filtration units.

4. Contain construction waste before transport in tightly covered containers.

5. Cover transport receptacles or carts. Tape covering unless solid lid.

1. Do not remove barriers from work area until completed project is inspected by the owner’s Safety Department and Infection Prevention & Control Department and thoroughly cleaned by the owner’s Environmental Services Department.

2. Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction.

3. Vacuum work area with HEPA filtered vacuums.

4. Wet mop area with cleaner/disinfectant.

5. Upon completion, restore HVAC system where work was performed.

CLASS IV
1. Contact Housekeeping Supervisor to schedule Post-work cleaning

2. Notify Tour Supervisor

3. Review ICRA with Department Supervisor(s)

1. Isolate HVAC system in area where work is being done to prevent contamination of duct system.

2. Complete all critical barriers i.e. sheetrock, plywood, plastic, to seal area from non-work area or implement control cube method (cart with plastic covering and sealed connection to work site with HEPA vacuum for vacuuming prior to exit) before construction begins.

3. Maintain negative air pressure within work site utilizing HEPA equipped air filtration units.

4. Seal holes, pipes, conduits, and punctures.

5. Construct anteroom and require all personnel to pass through this room so they can be vacuumed using a HEPA vacuum cleaner before leaving work site or they can wear cloth or paper coveralls that are removed each time they leave work site.

6. All personnel entering work site are required to wear shoe covers. Shoe covers must be changed each time the worker exits the work area.

1. Do not remove barriers from work area until completed project is inspected by the owner’s Safety Department and Infection Prevention & Control Department and thoroughly cleaned by the owner’s Environmental Services Dept.

2. Remove barrier material carefully to minimize spreading of dirt and debris associated with construction.

3. Contain construction waste before transport in tightly covered containers.

4. Cover transport receptacles or carts. Tape covering unless solid lid.

5. Vacuum work area with HEPA filtered vacuums.

6. Wet mop area with cleaner/disinfectant.

7. Upon completion, restore HVAC system where work was performed.

Step 4. Identify the areas surrounding the project area, assessing potential impact Adjacent Area Impacts: Identify the areas surrounding the project area, to assess potential impact

Below
Above
Lateral
Lateral
Behind
in Front

Adjacent Unit Name

Patient Risk Group (per Table 1)

Step 5. Identify specific site of activity e.g., patient rooms, medication room, etc.

Step 6. Identify containment measures, using prior assessment. What type of barriers? (E.g., solid wall barriers); Will HEPA filtration be required. Do plans allow for adequate number of isolation/negative airflow rooms?

(Note: Renovation/construction area shall be isolated from the occupied areas during construction and shall be negative with respect to surrounding areas)

Step 7. Consider potential risk of water damage. Is there a risk due to compromising structural integrity? (e.g., wall, ceiling, roof)

Step 8. Work hours: Can or will the work be done during non-patient care hours?

Step 9. Do plans allow for adequate number of isolation/negative airflow rooms?

Step 10. Do the plans allow for the required number & type of handwashing sinks?

Step 11. Does the infection prevention & control staff agree with the minimum number of sinks for this project?

Step 12. Does the infection prevention & control staff agree with the plans relative to clean and soiled utility rooms?

Step 13. Plan to discuss the following containment issues with the project team. (E.g., traffic flow, housekeeping, debris removal [how and when])

Appendix: Identify and communicate the responsibility for project monitoring that includes infection prevention & control concerns and risks. The ICRA will be modified throughout the project.

Revisions must be communicated to the Project Manager.

Infection Control Construction Permit Project Title:

Location of Construction:
Project Start Date:
Project Coordinator:
Estimated Duration:
Contractor Performing Work
Permit Expiration Date:
Supervisor:
Telephone:
YES
NO
CONSTRUCTION ACTIVITY
YES
NO
INFECTION CONTROL RISK GROUP

TYPE A: Inspection, non-invasive activity

GROUP 1: Low Risk

TYPE B: Small scale, short duration, moderate to high levels

GROUP 2: Medium Risk

TYPE C: Activity generates moderate to high levels of dust, requires greater 1 work shift for completion

GROUP 3: Medium/High Risk

TYPE D: Major duration and construction activities Requiring consecutive work shifts

GROUP 4: Highest Risk

CLASS I
1. Execute work by methods to minimize raising dust from construction operations.

2. Immediately replace any ceiling tile displaced for visual inspection.

3. Minor Demolition for Remodeling

CLASS II
1. Provides active means to prevent air-borne dust from dispersing into atmosphere

2. Water mist work surfaces to control dust while cutting.

3. Seal unused doors with duct tape.

4. Block off and seal air vents.

5. Wipe surfaces with cleaner/disinfectant.

6. Contain construction waste before transport in tightly covered containers.

7. Wet mop and/or vacuum with HEPA filtered vacuum before leaving work area.

8. Place dust mat at entrance and exit of work area.

9. Isolate HVAC system in areas where work is being performed; restore when work completed.

CLASS III

1. Obtain infection control permit before construction begins.

2. Isolate HVAC system in area where work is being done to prevent contamination of the duct system.

3. Complete all critical barriers or implement control cube method before construction begins.

4. Maintain negative air pressure within work site utilizing HEPA equipped air filtration units.

5. Do not remove barriers from work area until complete project is checked by Infection Prevention & Control and thoroughly cleaned by Environmental Services.

6. Vacuum work with HEPA filtered vacuums.

7. Wet mop with cleaner/disinfectant

8. Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction.

9. Contain construction waste before transport in tightly covered containers.

10. Cover transport receptacles or carts. Tape covering.

11. Upon completion, restore HVAC system where work was performed.

Date
6.
12.

Initial

CLASS IV

1. Obtain infection control permit before construction begins.

2. Isolate HVAC system in area where work is being done to prevent contamination of duct system.

3. Complete all critical barriers or implement control cube method before construction begins.

4. Maintain negative air pressure within work site utilizing HEPA equipped air filtration units.

5. Seal holes, pipes, conduits, and punctures appropriately.

6. Construct anteroom and require all personnel to pass through this room so they can be vacuumed using a HEPA vacuum cleaner before leaving work site or they can wear cloth or paper coveralls that are removed each time they leave the work site.

7. All personnel entering work site are required to wear shoe covers.

8. Do not remove barriers from work area until completed project is checked by Infection Prevention & Control and thoroughly cleaned by Environmental. Services.

9. Vacuum work area with HEPA filtered vacuums.

10. Wet mop with disinfectant.

11. Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction.

12. Contain construction waste before transport in tightly covered containers.

13. Cover transport receptacles or carts. Tape covering.

14. Upon completion, restore HVAC system where work was performed.

Date
15.

Initial

16.

Additional Requirements:

Date Initials
Exceptions/Additions to this permit Date.
Permit Request By:
Permit Authorized By:
Date:
Date:

***Post Completed and Signed ICRA at worksite

File details come from the government source that posted it. Updated .