B05 75H70125R00033 Amendment 03.pdf
PDF 326 KB Posted
- Attached to
- IHS Nationwide Multiple Award Task Order Contract Federal contract opportunity
- Solicitation number
- 75H70125R00033
About this file
This document is an Amendment of Solicitation/Modification of Contract with Questions and Answers for Solicitation Number 75H70125R00033, issued by the Division of Engineering Services in Seattle. The amendment provides clarifications for a seed project, which is not a design-build project, and addresses various contractor requirements. Key points include: contractors can have one individual fill multiple roles (superintendent, safety officer, quality manager), designers must be employees of the offeror, and past performance can be utilized by team members in a teaming arrangement. The document allows a small business to submit two proposals (one as a small business and another as a team member) and confirms that no design submission or specification book is required for this project. Wage determination and staffing details are addressed, with contractors advised to assign employees to the most appropriate labor category and submit additional classification requests if needed.
View the file
Other files for this federal contract opportunity
Show all 47
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
A000003
The reason for this amendment is to provide answers to questions.
See Summary of Changes
Division of Eng. Services Seattle 701 Fifth Avenue, Suite 1600 Seattle WA 98104
See block 6
75H70125R00033
1 4
09/25/2025
09/16/2025
QUESTIONS AND ANSWERS
75H70125R00033
Answers to the following questions are as follows:
1. Solicitation section H.18 COORDINATION OF TRADES states "The contractor shall have a competent and registered engineer to coordinate all fieldwork and shop drawings of the various trades prior to installation and for submission of coordinated shop drawings for approval" Question: Is the Government requiring a "registered engineer" to coordinate filed work and shop drawings or can this work be performed by the project superintendent?
Response: A registered engineer is only required if specified in the task order’s Statement of Work;
otherwise, the project superintendent may perform the coordination.
2. Please confirm for the seed project that one contractor individual can fill the position of the superintendent, safety officer, and quality manager.
Response: For the purposes of this seed project, a site superintendent may also fill in the positions of safety officer and quality assurance. Individual task orders will specify how key personnel positions should be filled.
3. Please confirm if the seed project is a design build project. The SOW doesn’t indicate anything about design requirements. If design‐build what are the design submission requirements?
Response: The Seed project is not a design‐build project. No design is required for this project.
4. If proposing as a teaming arrangement the solicitation indicates “teaming proposals shall clearly identify the roles and level of participation of each firm in the proposed work and shall include the Small Business Administration approval of Small Business status of the offering business entity.” The SBA doesn’t approve teaming agreements. Please advise.
Response: This is correct. The SBA does not approve teaming agreement. However, the solicitation is not requiring SBA approval of the teaming agreement; rather, it requires the offering entity to submit proof of its SBA‐approved small business status.
5. Can past performance be utilized by both team members if contemplating a teaming agreement?
Response: Yes
6. Can a business that is considered a small business provide two proposals? One as a small business and another proposal as a team member of an ISBEE teaming partner.
Response: This is allowable. Each submission will be evaluated independently, but offerors should be mindful of potential Organizational Conflict of Interest concerns.
7. Solicitation indicates “Relevant and recent experience with design‐build projects for healthcare or related facilities where the Offeror performed all Mechanical/Electrical/Plumbing (MEP) design activities in‐house.” To be considered in‐house does this mean that the designers are employees of the offeror or can outside consultants/design firms be considered in‐house if design services were subcontracted by the offeror?
Response: The designers must be employees of the offeror.
8. Should design team members be identified in the offeror’s proposal.
Response: Offerors may either identify design team members or explain how subconsultant design services will be obtained in their technical proposal; this information must be included under Factor 3(a)(5) to achieve a “Satisfactory” rating. Offerors may also identify their design team in Factor 1 when design‐ build projects were performed entirely in‐house for MEP design.
9. In the RFP – Section K – it goes from K.1, K.2 then skips to K.6. Please clarify if K.3, K.4 and K.5 was meant to be omitted.
Response: Section K.6 is renumbered to K.3.
10. And there is no listing for Reps and Certs to be inserted into the Price Proposal. If you do want them included, can I just place them in the back of the price proposal?
Response: Reps and Certs are not a required submittal for this solicitation. However, firms should ensure that their Reps and Certs are current and active in SAM.gov.
11. See attached Attachment 2 – Contractors Surety Information. Reference the below line item, copied and pasted from Section B, noted in italics.
“What is the contractors rating?_____________________”
Are you asking for the contractor’s bonding rates? Or are you asking for the surety’s rating (i.e., A.M.
Best rating of A)? Please review and clarify.
Response: Some surety companies have provided us with an overall assessment of the firm using their own rating system. Usually it’s based on the contractor’s financial strength, credit history and/or track record on bonded projects. We do not need the surety’s AM Best Rating.
12. Are project specifications (specification book) for the seed project intended to be included as part of this solicitation? None were provided.
Response: A specification book is not included; the seed project is defined by a Statement of Work and drawings, which provide the necessary information for proposal preparation and reflect the type of documentation to be expected under the MATOC.
13. Wage Determination does not include wage rates for the following required by RFP: Flooring installation, window installation, ceiling installation. Is laborer, carpenter or painter to be used in place of these trades?
Response: Contractors should assign employees to the most appropriate listed labor category based on the work performed; if no existing category is suitable, you may submit an additional classification request (conformance) through the contracting officer for Department of Labor (DOL) approval.
14. Contractors Staff requires superintendent onsite at all times, please provide staffing requirement for
QCM/SSHO.
Response: See response to question #2 in this amendment.
Additional responses to seed project technical questions will be forthcoming in an upcoming amendment.