STA Siuslaw Amendment 0005 with Site Visit Log.pdf
PDF 813 KB Posted
- Attached to
- DBB for Correct Shoreline Erosion at USCG Station Siuslaw in Florence, OR (NMACC III Pool 1)
- Solicitation number
- 70Z05024R43000003
About this file
This document is Amendment 0005 to a federal solicitation for a Design/Bid/Build construction project to correct shoreline erosion at the U.S. Coast Guard Station Siuslaw River in Florence, Oregon. The amendment includes:
- Updates to the bid proposal closing date, now Friday July 12, 2024 at 2:00PM PDT.
- Responses to proposers' questions, including clarification on permits, geotechnical information, site access, utility work, tieback design, sheet pile installation methods, coating requirements, and contract performance period.
- Revisions to the base contract duration, now 400 calendar days, with potential extensions for awarded options.
- Attachments providing permit applications, the geotechnical report, and additional site photos.
The original solicitation, Number 70Z05024R43000003, is limited to the successful offerors in NMACC III Pool 1. The work includes constructing a sheet pile shoreline erosion wall, upper retaining wall, utilities, bridgeway modifications, and related work.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or
(c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
2. AMENDMENT/MODIFICATION NO.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
CORRECT SHORELINE EROSION AT USCG STATION SIUSLAW, FLORENCE, OR; Task Order Announcement 70Z05024R43000003; Amendment 0005: See Continuation Pages.
The Price Proposal closing date of June 28, 2024, on Page 1 (Cover Page), Page 5, and Page 17 of the Task Order Announcement is hereby updated to Friday July 12, 2024 at 2:00PM Pacific Daylight Time
(PDT).
USCG FDCC DET SEATTLE
915 SECOND AVE, RM 2664
SEATTLE, WASHINGTON 98174-1011
9A. AMENDMENT OF SOLICITATION
NO.
70Z05024R43000003
06/27/2024
9B. DATED (SEE ITEM 11)
05/29/2024
X
X
70Z05024R43000003
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
ENCLOSED DOCUMENT: AMENDMENT 0005
ANSWERS TO PROPOSERS’ QUESTIONS:
PPI 007
Specification section 01 11 00 para 1.2.3 lists applicable permits to the project, to be obtained by USCG. Please provide these permits for contractor review. If the permits are not available, please provide applications for contractor review.
Answer: The following seven documents will be sent with this Amendment # 5 as attachments, with the exception of the IHA as noted below, which is still not available at this time. These files will be uploaded in SAM.gov also.
1. -Final JPA Application
2. -Final Biological Assessment Application
3. -CZMA Consistency Determination Application
4. -Environmental Assessment
5. -IHA Application
6. -DEQ 401 WQC Permit
7. -Section 408 No Alteration - granted
IHA is still in the process.
PPI 008
Borings taken are relatively far from location of work and are not believed to accurately depict soil conditions to be encountered on this project. Please advise if additional information is available. If not, please note that there is potential for additional costs for slowed production on piles/tie-backs due to the possible presence of rip/rap and rockier conditions at the locations of the actual work location. It is recommended that the pricing schedule be amended to include unit rate costs for drilling through harder material than shown in the boring logs.
Answer: See attached Geotechnical Report and Appendix B for more borings and other information.
PPI 009
Please provide sign-in sheet from the site walk held on 06/06/24.
Answer: The last page of this Amendment 0005 document contains the sign in sheet. (Page 17)
PPI 010
Please provide a full geotechnical report for the investigation performed as part of borings B1-B6.
Answer: See Amendment 0005 Attachment Geotechnical Report. This file will be uploaded w/ Amendment 0005 to SAM.gov also.
PPI 011
Subcontractor market is requesting additional time for bidding following the site walk. Please extend the bid proposal due date by 3 weeks to 07/19/24.
Answer: The proposal closing date has been extended by 2 weeks as result of this Amendment.
The Price Proposal due date of June 28, 2024 on Page 1 (Cover Page), Page 5, and Page 17 of the Task Order Announcement is hereby updated to Friday July 12, 2024 at 2:00PM Pacific Daylight Time (PDT).
PPI 012
Section 31 41 16 – 2.4 of the project specifications clearly states that a hydraulic press-in machine should be used for the sheet pile wall installation for this project. The rip rap and steep slope site conditions will make this extremely difficult / cumbersome. Assuming the reasoning for using the press-in method is due to concerns with resonant vibrations affecting the surrounding soils/structures, consider allowing use of a Variable-Moment Driver/Extractor for this scope. These machines are intended to be used within close proximity to existing buildings and have no amplitude, or moment (energy), when the hammer is being started and stopped. Please advise.
Answer: The hydraulic press-in method will be used as specified.
PPI 014
The “upper retaining wall” is labeled as a bid option in S-100 and S-102. Details for this retaining wall are included on S-103, but S-103 does not reference this area as a bid option. Please confirm ALL work included on S-103 is to be included in bid option 1.
Answer:
Drawing S-102 As per the Drawing S-102, the following statement is hereby deleted:
"PROVIDE UPPER RETAINING WALL" BID ALTERNATE SHOWN. SEE CG100 FOR
INFOR MATION ON "NO UPPER RETAINING WALL "BID ALTERNATE WHICH
INCLUDES NO STRUCTURAL WALL SCOPE IN THIS UPPER AREA.
The statement above is replaced by the following:
"PROVIDE UPPER RETAINING WALL" BID OPTIONS SHOWN. SEE CG100 FOR
INFORMATION ON "NO UPPER RETAINING WALL "BID OPTIONS WHICH INCLUDES
NO STRUCTURAL WALL SCOPE IN THIS UPPER AREA.
PPI 015
Bid option 2 is for “no upper retaining wall.” Base item indicates “provide shore erosion wall and base site civil improvements, excluding site grading and upper retaining wall area described in option 1 and option 2.” Grading & Drainage plan CG100 includes note 7 and 10 referring to the upper retaining wall, however there is no limits of disturbance to verify the extent of grading the should be included under option 2, and excluded under the base item. We are assuming base item excludes all work in this area, but please provide the extent to which grading should be considered for option 2 and base item.
CD100 Demo plan includes a section for clear and grub and fence removal – is this the extent that should be excluded from the base item?
Answer: The upper retaining wall bid options include the "NO UPPER RETAINING WALL" BID OPTION, and the "PROVIDE UPPER RETAINING WALL" BID OPTION. Only one will be awarded with the base bid. The limits of disturbance for both bid options are shown on CG100 as a "dash-dot-dot" line. Both bid options include the removal and replacement of the fence shown on CD100 and CS100 respectively. The limits of disturbance for the "PROVIDE UPPER RETAINING WALL" BID OPTION extend to the edge of pavement at the parking lot. The limits of disturbance for "NO UPPER RETAINING WALL" BID OPTION extend approximately 10' past the edge of pavement. The BASE BID grading extent at the southwest portion of the site goes up to approximately Elevation 30.0 where the new slopes conform to the embankment.
PPI 016
In Specification Section 31 41 16 Metal Sheet Piling, we find no mention of coating requirements. If the metal sheet piling is to be coated, please specify what the product to be used is and in what specification section this is located.
Answer: The metal sheet piling is to be uncoated. Pile sizes have been increased to account for long term corrosion.
PPI 017
In the specifications for this project, we noticed that the contract completion time period is stated as 884 calendar days from the award date. Could you confirm that this duration is correct?
Answer: Base item duration shall be amended to be 400 calendar days.
If Option 1 is awarded, add 43 calendar days to 400 calendar days.
If Option 2 is awarded, add 28 calendar days to 400 calendar days.
If Option 3 and/or 4 are awarded then POP will be extended to the end of the In Water Work Window (IWWW) Feb 15th, 2026.
The period of performance of 884 calendar days as noted on Pages 4 and 19 on the Task Order Announcement (TOA) is deleted and replaced with 400 calendar days.
PPI 018
We acknowledge Appendix B – Permits (single page table of contents) is a placeholder that indicates to the bidding contractors which Permits have been initiated, but not received/authorized yet. No anticipated dates are included on this page. Will contractors receive copies of these permits prior to the final bid submission date? If not, please confirm that constraints not identified at the time of bid, but included within future permit language, shall be considered a changed condition where the contractor’s Cost and Time impacts will be payable.
Answer: See PPI 007. We are confirming that if any agencies impose permit constraints which are not part of contract documents, this shall be considered a changed condition.
PPI 021
Specification Section 01 14 00 1.1.4 – “Occupied and Existing Buildings” includes a statement that describes the effort to remove and relocate government property in areas of the “site areas, bridgeway, and floating dock.” Regarding the “bridgeway,” please clarify the effort the USCG plans to perform.
See Keynote A on WD101 which indicates to “REMOVE, SALVAGE, AND REINSTALL BRIDGE SUPERSTRUCTURE.” Drawing WD-402 further clarifies the segment of the Bridge Superstructure to be removed (Bent #2 back to the Concrete Retaining Wall). Will the USCG be performing any of the removing, salvaging, and reinstalling? Or is the entirety of this effort to be performed by the contractor? If so, this instance would conflict with 01 14 00, 1.1.4. Please confirm.
Answer: Government will remove any portable equipment which may be in this area, Contractor to perform remaining.
Contractor will provide 2 weeks written advance notice to the Contracting Officer and COR prior to starting work.
PPI 022
Specification Section 01 14 00 1.1.4 – “Occupied and Existing Buildings” includes a statement that describes the effort to remove and relocate government property in areas of the “site areas, bridgeway, and floating dock.” Regarding the “floating dock,” we assume this to mean that USCG will relocate the floating dock prior to scheduled activity for removing old piles and driving and concrete filling the new steel pipe piles. Please confirm the contractor shall not include any effort to remove floating dock and shall expect the necessary surface water space to perform its work.
Answer: Government will not remove floating dock. Government will clear portable objects.
Contractor will provide 2 weeks written advance notice to the Contracting Officer and COR prior to starting work.
PPI 023
Specification Section 02 41 00, 3.1.2.1 – This paragraph indicates to not interrupt existing utilities serving occupied or used facilities. Please confirm this is limited to the Landside facilities, and that utilities shown for removal and replacement along the bridgeway are exempt from this requirement.
Please confirm no temporary utility connections are required to maintain service to marine facilities at the end of the Bridgeway.
Answer: Confirmed, no temporary utility connections to covered moorings and floating dock are required. Contractor to minimize duration of outage as much as possible.
PPI 024
Appendix A Hazardous Materials Survey – Section 4.1, 5.1 – indicates that no samples contain greater than 1% Asbestos Containing Material (ACM) by PLM. Only one item (#7 on Table 1) was identified as not sampled and assumes that Fuel Line Gaskets to be considered NESHAP Category 1 non-friable ACM’s which per section 5.1 paragraph 2 “are not required to be removed prior to demolition or renovation of the building, provided that wet-demolition practices are implemented and resulting debris from the building is properly transported to a landfill permitted for disposal of ACMs.” Based on the survey provided by USCG, please confirm contractors shall assume the effort for ACM abatement on this project is limited to the fuel line removal (specifically the gaskets), as no other samples indicate ACM’s are found within the scope of work under this contract.
Answer: Confirmed; contractors shall either assume the effort for ACM abatement for the gaskets including proper disposal; or perform analytical testing on the assumed gaskets after the fuel system is turned off and prior to demolition or renovation activities.
PPI 025
Appendix A Hazardous Materials Survey – Section 4.2, 5.2 - indicates which samples collected for Lead Based Paint contained greater than or less than 0.5% by weight. 3 Samples are identified over 0.5% as actionable and 3 painted components to be considered having detectable concentration of lead, requiring special procedures for removal, handling, and disposal. However, all locations identified are found at the covered mooring and outside of the limits of this contract. Based on the survey provided by USCG, please confirm contractors shall assume no effort for removal of Lead Based Paint on this project.
Answer: Confirmed, assume no effort for the removal of Lead Based Paint (LBP) on this project.
All LBP is outside this project scope of work. Confirmed, assume no effort for the removal of Lead Based Paint (LBP) on this project. All LBP is outside this project scope of work.
PPI 026
Appendix A Hazardous Materials Survey – Section 4.3, 5.3 - indicates items containing Polychlorinated Biphenyl (PCB) content, requiring special procedures for removal, handling, and disposal. However, all the sample locations identified are found at the covered mooring and outside of the limits of this contract. Based on the survey provided by USCG, please confirm contractors shall assume no effort for removal of items containing PCB on this project.
Answer: Confirmed regarding PCB, no effort is to be assumed for the removal of hazardous materials.
PPI 028
If page 19 of the Task order Announcement is replaced, we assume the note at the bottom of the page will remain or be added in a future amendment. “NOTE: The period of performance for completion of all work for the Base and any Option Items awarded under the task order is 884 calendar days.”
Answer: Please refer to PPI 017.
PPI 029
REFERENCE: Section 01 11 00, Paragraph 1.2.3 Permits QUESTION: Section 01 11 00, Paragraph 1.2.3 Permits says the contractor shall comply with all regulatory permit requirements. The Government is securing permits and will provide to Contractor.
Please provide copies of all Environmental Permits.
Answer: Please refer to PPI 007.
PPI 031
REFERENCE: Page 4, Solicitation, Performance Period QUESTION: Page 4, Solicitation, Performance Period says the performance period is 884 calendar days. Please clarify what the driving factor is for this duration? Is the work expected to take place over several In-Water Work Windows?
Answer: Please refer to PPI 017.
PPI 036
REFERENCE: Section 01 35 29 Safety and Occupational Health Requirements QUESTION: Please confirm the qualifications for the Site Safety and Health Officer (SSHO) are to conform to USACE EM 385-1-1.
Answer: Yes, SSHO qualifications should conform to the reference USACE Manual.
PPI 037
REFERENCE: Section 01 35 29 Safety and Occupational Health Requirements QUESTION: Please identify whether the SSHO can also be the Project Superintendent or the Quality Manager.
Answer: SSHO may be a duty assigned to the Quality Manager but not the Project Superintendent.
PPI 038
REFERENCE: Staffing QUESTION: Please identify whether the Project Superintendent, SSHO, or Quality Manager roles can be filled by a subcontractor or if required to be an employee or consultant directly of the NMACC III Prime Contractor.
Answer: Superintendent, SSHO and QM may be filled by subcontractors who have direct contractual relation with the NMACC Prime, assuming they meet the qualifications and requirements outlined in the RFP.
PPI 039
REFERENCE: Staffing QUESTION: Please confirm that the Project Superintendent, SSHO, and Quality Manager must be onsite full time when work is being performed, but that the Project Manager is not required to be onsite full time.
Answer: Project Manager is not required to be on site full time. Superintendent, SSHO and Quality Manager will be on site for all construction activities.
PPI 041
REFERENCE: Section 01 45 00 Quality Control QUESTION: Please confirm the Quality Assurance Manager and Quality Program Manager, as referenced by the project specifications, are the same person.
Answer: Confirmed, Terms QAM and QPM are interchangeable, but are separate from the Project Manager or Superintendent.
PPI 042
CD100 shows removal/replacement of diesel and fuel lines. Additionally, notes indicate fire alarm, comms, and power lines to be pulled back to point of connection, and reconnected after bridge reconstruction. However, there is a water line shown for reference, and a specification for water piping under 33 11 00, but no specific notes/drawings on removing/replacing this line. Please advise.
Answer: See keynote 7, CD100. See general note 6, CD100. See utility keynote 4, CS100.
PPI 043
CD100 shows utilities to be removed/replaced to facilitate bridge removal/replacement. However, no notes are included regarding temporary facilities for the boathouse, or how any current functions being employed by the boathouse are being accommodated. Please confirm no temporary facilities (fuel, diesel, power, etc) are required for the boathouse during construction. Also confirm there is no maximum downtime for these utilities during construction.
Answer: Refer to PPI 032 for bridgeway restriction duration. During this three-week period temporary utilities are not required. If restricted access is required longer than 3 weeks, contractor will reestablish at a minimum electrical service to Covered Mooring/Floating Dock.
PPI 045
Spec: 01 11 00 1.2.3: 1.2.3 Permits states that the Government is securing the project’s permits and will provide them to the Contractor. Permit documents will be necessary for the contractor to determine their means and methods, work hours, in water work windows, etc. Please provide a copy of each permit, and if not yet approved, please provide draft permits and/or stipulate any conditions of those permits not otherwise covered by the specification.
Answer: Please refer to PPI 017.
PPI 047
Spec: 01 30 00 1.7.5: 1.7.5 Quality Assurance Manager (QAM), please confirm the QAM must be an employee of the prime contractor.
Answer: Superintendent, SSHO, and QM may be filled by subcontractors who have direct contractual relation with the NMACC Prime, assuming they meet the qualifications and requirements as outlined in the RFP.
PPI 048
Spec: 01 30 00: Given the limited size of project, economy of combined responsibilities is in the best interest of the USCG. Please confirm that the Safety Officer may be fulfilled by either the Superintendent or the QAM.
Answer: SSHO may be a duty assigned to the Quality Manager but not the Project Superintendent.
PPI 049
The TOA for Solicitation # 70Z05024R43000003, page 4, describes a performance period of 884 calendar days after award. This POP appears to be greater than necessary for performance of the work, however, without a technical proposal, there is no means for contractor communication of its intended period of performance. Please confirm the contractor need only include in its proposal costs to support the project for the period duration the contractor has determined is necessary for adequate performance and completion of the work.
Answer: Please refer to PPI 017.
PPI 051
Spec: 31 68 13: 1.3 Site Conditions refers to an existing geotechnical report. Please provide a copy of the Geotechnical Report.
Answer: Please refer to PPI 008.
PPI 052
Would alternative sheet pile installation methods be approved if methods maintain vibration under the monitoring thresholds?
Answer: Refer to Section 5.4.4 of the Geotechnical Report for construction considerations regarding the sensitivity of the steep slope to vibrations. The hydraulic press-in method shall be used as specified.
PPI 053
Sheet: CS111: Can the limits of upland disturbance as called out on sheet CS111 be expanded to allow for access?
Answer: The upland limits may be disturbed expanded as needed for access. The upland area is roughly defined as elevation 50 and above. Upland areas that are disturbed shall be reestablished to current conditions at no additional cost to the government. The embankment area (roughly elevation 50 and below) generally cannot be disturbed beyond the limits shown as any disturbed area must be reestablished at a 2:1 maximum slope. Only existing undisturbed embankments may remain at a steeper slope.
Contractors will stay within the USCG property boundary unless they have written agreement with other property owners and the USCG operations will not be impacted during construction.
The government will not be providing any property use agreements outside of our owned property.
PPI 054
Spec: 31 62 16.13: 3.2.1 states that "A pile shall be considered as driven to refusal when five blows of the hammer (with an energy per blow equal or exceeding that specified) produces a total penetration of 1/4 inch or less". Please provide the specified energy per blow referred to in this spec.
Answer: Piles must be driven to the elevations shown on the Contract Drawings.
PPI 055
Please provide information on the coating system that has been applied to the existing 18" piles so that we may determine touch-up procedures.
Answer: The existing steel walkway, including piles, W-sections, angles, and plates, is coated with a marine grade polyurea coating.
PPI 056
Do the permits allow for temporary piles to be installed in the water and on land for temporary access?
Can these piles be vibrated and impacted?
Answer:
The permit application(s) requested approval for permanent installation of up to 79 steel pilings (16" to 20" diameter) in the water (i.e., below Hightest Measured Tide (HMT)); and up to 3 temporary spud piles for a barge; no additional temporary pilings were requested. This count is intended to cover the present project as well as the reconstruction of the covered moorings and walkway in a separate project.
Pipe pilings in water can be installed with a vibratory hammer and with some use of an impact hammer if needed to seat the pilings. Please see JPA for project description and activities requested. If additional temporary pilings are needed below HMT, then a permit modification request would be required after permits are issued. No permits are required for installation of pilings on land above HMT.
PPI 057
Of note, in section 11 of the SF30, the “is not extended” box is checked, however in PPI 011 and PPI 050 the responses confirm that the proposal due date of 28 June 2024 is now updated to 9 July 2024.
There’s no mention of an updated closing time so does that remain at 5:00p PDT?
Answer: In reference to PPI 011 and Amendment #4 the extended due date to submit proposals is July 9, 2024 at 5:00 PM Pacific Daylight Time (PDT).
PPI 058
REFERENCE: Drawing S-001 Drawing S-001 Note 3 under Steel Sheet Piles states that Steel Sheet Piles shall be installed using a Pressure Machine using static load. Section 31 41 16, paragraph 2.4.1 states press-in machine shall utilize pile installation techniques by means of static load along with Augering shall be used to reduce the penetration resistance during pile installation by the Press-in method for hard ground conditions.
Please confirm that no other installation methods will be allowed for installing the sheet pile other than the Press-In Method and that Pre-Drilling along the entire sheet pile wall will be required.
Answer: Please refer to PPI 052.
PPI 059
REFERENCE: Task Order Announcement Per Task Order Announcement, the Performance Period is 884 Calendar Days after award of Task Order. Please clarify when the Task Order is expected to be awarded and when the Civil work on site is expected to take place or begin.
Answer: Task Order is expected to be awarded no later than 30 September 2024. See PPI 017.
The specific dates will be clarified during the after award scoping meeting.
PPI 060
After Contractor review of the forthcoming permits, there may be questions that will need to be submitted. As a result, we respectfully request that the "Questions Due" period be revised to "10 days before the bid due date" in place of "June 18, 2024".
Answer: There will no longer be an extension of the due date for questions. Questions submitted after the June 18, 2024, due date may or may not be answered.
PPI 061
Sheet: C5501 Detail: 1 Is the temporary fence to be installed per detail 1 on CS501?
Answer: No, this detail pertains to permanent fencing.
PPI 062
Are there any coating requirements for the sheet piling?
Answer: Please refer to PPI 016.
PPI 063
Are Soldier Piles (W14x61) to be galvanized? If so how far below ground line is this coating required?
Answer: The soldier piles are to be uncoated. Pile sizes have been increased to account for long term corrosion.
PPI 064
Sheet: WS402 Detail: F1 Are the top plates per detail F1 on sheet WS 402 coated? Please provide desired coating system.
Answer:
Top plates must be hot dipped galvanized per WS001 Coating System Notes #3.
PPI 065
Utility Key Notes #1 and #2 on Drawing CS100 state to remove and replace double-walled diesel line and gasoline line with 4-inch fiberglass outer pipe and 2-1/2 inch schedule 40SS pipe. Please confirm whether the carrier pipe is carbon steel or stainless steel. Specification Section 33 52 10 does not provide the specifications for such double-walled piping with 4-inch fiberglass outer pipe and 2-1/2 inch schedule 40SS inner pipe. Please provide the specifications for the double-walled diesel line and gasoline line.
Answer: Existing carrier pipe is stainless steel per 2013 as-builts. Use 2-1/2 inch schedule 40 SS pipe and 4" fiberglass reinforced plastic to match existing.
PPI 066
For the removal and replacement of the double-walled diesel line and gasoline line, is the contractor also required to remove and replace the existing pipe supports? Please confirm if any valves and/or fueling equipment needs to be replaced between the reconnection points at fuel dispensers and at structure under the existing bridge.
Answer: The intent is to remove the lines as shown on the plan and restore the fueling lines in kind including pipe supports. No valves exist and no fueling equipment replacement is part of the scope.
PPI 067
Please provide detailed drawings or schematics for the replacement of the double-walled diesel line and gasoline line. From the existing photos on Drawing WD002, it is very difficult to see any details for replacing these existing fuel lines. Can we assume that only pipe and fittings need to be replaced for these lines?
Answer: No detailed drawings of fueling lines exist. Please see additional pictures showing existing fuel lines. See also response to PPI 066.
PPI 068
Utility Key Note #4 on Drawing CS100 states to remove and replace the 1-1/2 inch water line with insulation. Based on the pipe size, please confirm that the water line material is PVC piping. Please provide additional information for the insulation type and thickness required. Specification Section 33 11 00 does not provide any specifications for the insulation.
Answer: The existing water line is PVC piping. Use outdoor rated, UV resistant insulation with a minimum R-value of 3.1.
PPI 069
For the removal and replacement of the 1-1/2 inch water line, is the contractor also required to remove and replace the existing pipe supports? Please confirm if any valves and/or equipment needs to be replaced between the two reconnection points shown on CS100.
Answer: The intent is to remove the water line in conflict during construction and restore in kind including any impacted pipe supports. No valves exist in the short section.
PPI 070
After replacing the double-walled diesel and gasoline lines, will the contractor have to perform a full startup and commissioning for the entire diesel fuel and gasoline systems? Specification Section 33 52 10 calls for pneumatic testing, hydrostatic testing, containment piping testing, and system performance testing.
Answer: As specified in 33 52 10 3.3, Contractor to perform testing of reconnected systems including piping and to demonstrate that each system is operational.
In addition, Contractor is to also demonstrate entire system functionality by performing the following commissioning: demonstrate that each fuel pump has the capability to deliver the indicated flow of fuel, the alarm and control panels are operational, each fuel meter is operating accurately, vent piping is clear of debris and each pressure/vacuum relief vent is operating properly, dispenser and nozzles are operational and performing as designed, and each safety device works properly and is tested per NFPA requirements as necessary.
In section 33 52 10, article 3.4, page 28, before first sentence, INSERT this paragraph:
“Contractor is to also demonstrate entire system functionality by performing the following commissioning: demonstrate that each fuel pump has the capability to deliver the indicated flow of fuel, the alarm and control panels are operational, each fuel meter is operating accurately, vent piping is clear of debris and each pressure/vacuum relief vent is operating properly, dispenser and nozzles are operational and performing as designed, and each safety device works properly and is tested per NFPA requirements.”
PPI 071
We would like to respectfully request that the Due Date for PPI’s be extended to sometime after the last RFI responses are provided to allow for potential follow-up questions to be submitted. Preferably this future date leaves the contractors 10 days to disseminate information and receive updated pricing from Subcontractors and Vendors before bid submission.
Answer: Please refer to PPI 011.
PPI 072
REF: Drawing CD-100; Question: Note 20 on Drawing CD-100 indicates to “PULL EXISTING FIBER
OPTIC, COPPER CABLES, AND FIRE ALARM CABLES BACK TO EXISTING STAINLESS STEEL
JUNCTION BOX AT THE TOP OF THE GANGWAY.” We would like to request the size (number of strands) for the fiber optic cable to determine the appropriate splice kit and effort for this work.
Answer: 6 strand fiber.
PPI 073
REF: Drawing CD-100, WS-103; Question: Note 20 on Drawing CD-100 indicates to “PULL
EXISTING FIBER OPTIC, COPPER CABLES, AND FIRE ALARM CABLES BACK TO EXISTING
STAINLESS STEEL JUNCTION BOX AT THE TOP OF THE GANGWAY.” We would like to request clarification on the location of this “Stainless Steel Junction Box.” We assume the location is at one of the following: Location Option 1.) on the bridge between Bent 3 and Bent 4 just beyond the yellow life ring cabinet. Location Option 2.) on the bridge at the top of the Gangway that runs down to the Exterior Floating Dock between Bent 5 and the Boathouse Plumb Piles as shown on WS103. Please confirm which location the cables shall be pulled back to.
Answer: As indicated in the attached photographs of box exterior, it is located on the eastern sloped portion of the bridge, attached to the railing on north side. Note that box material is not stainless steel, it is plastic. See also photo of box interior, showing cable. See attached picture for the fiber box (Amendment 0005 Attachment PPI 073 Fiber Box Picture).
PPI 075
REFERENCE: Section 05 12 00, page 4 Sect 05 12 00 pg 4 says to provide the system in accordance with AISC 341 which is the Seismic Provisions for Structural Steel Buildings that requires welding and inspection per AWS D1.8 which we are not qualified for. AISC 341 specs can be found at https://www.aisc.org/globalassets/aisc/publications/standards/seismic-provisions-for-structural-steel-buildings-ansi-aisc-341-16.pdf it is full of QA/QC requirements. I’m surprised that they refer to AISC 341 since they do not require D1.8 welding in the General Notes on Sheets S-001 & S-101. Please Advise.
Answer: For the shoreline wall, welding to conform to AWS D1.1 per the General Notes on Sheets S-001.
See also Attachment Amendment 0005 STA Siuslaw Additional Specifications Update June 27, 2024 (PPI 075)
PPI 076
Installation of tiebacks 52, 50, and 49 will require access to adjacent property. Is there access available and if so, how much area is available?
Answer: There is approximately 3-4 feet between the sheet pile wall and the adjacent property.
Tiebacks may be installed behind the wall and utilize couplers as required to extend them to the front face of the wall.
See also Attachment Amendment 0005 Attachment PPI 076 Fuel Picture.
PPI 077
For alternate tieback designs, please confirm what level of corrosion protection is required to meet the 70 year design life and what amount of sacrificial steel is required.
Answer: The sacrificial steel for the tieback corrosion protection is based on an anticipated corrosion loss of 80μm/year.
PPI 078
REFERENCE: Drawing Sheet S-101 As shown on drawing sheet S-101, Installation of tiebacks 49, 50, 51 & 52 will require access to adjacent property. Is there access available and if so, how much area is available? Has permission been obtained by Owner to use adjacent property?
Answer: There is approximately 3-4 feet between the sheet pile wall and the adjacent property.
Tiebacks may be installed behind the wall and utilize couplers as required to extend them to the front face of the wall.
PPI 079
REFERENCE: Tie-Back Note on Drawing Sheet S-402 Per Tie Back Note 3 on drawing sheet S-402, Contractor may propose an Alternate Tie Back Type. For alternate tieback designs, please confirm what level of corrosion protection is required to meet the 70-year design life and what amount of sacrificial steel is required.
Answer: Please refer to PPI 077.
PPI 080
Document: Specs Page: 206 Section: 31 41 16 Paragraph: 2.4.1 Section 31 41 16 Metal Sheet Piling requires the use of "Press-In Machine" for installation of sheet piling. This is not a practical solution as it will drive the cost of the project well above the Government's allowance. Paragraph 3.9 requires vibration monitoring, contradicting the requirement for press-in piles. Please confirm that sheet piles can be installed using traditional methods (i.e. sheet pile template, vibratory hammer, and impact hammer if needed). (Note: Section 31 62 16.13 Steel Pipe Piles allows for traditional methods for the pipe piles).
Answer: Please refer to PPI 052.
PPI 081
Document: Plans Section: WS001 WS001 includes notes for "Structural Steel Notes" and Coating System Notes". The Coating System Notes state "All steel except for piles to be hot dipped galvanized…" and the Structural Steel Notes stated "All structural Steel shall be coated in accordance with the specifications." Does this mean the sheet pile should be galvanized? If so, what would the limits be for galvanizing? If just a coating what would the coating limits be? Galvanizing the sheet piles would add significant cost to the project.
Answer: The sheet piles do not need to be coated or galvanized. Refer to sheet S-001 for notes on the sheet pile wall and the S drawing series.
The notes on sheet WS001 apply to the WS drawing series. For work that is depicted in the WS series: 1) the pipe piles shall be coated with a FBE system per the specifications, and 2) all other steel elements shall be hot dip galvanized per the project specifications.
PPI 082
Document: Plans Section: S103 Please provide the grade for the W14x61. Are these coated or galvanized? If so, please provide coating or galvanizing requirements.
Answer: W14x61 shall be Gr. 50. Regarding coating, reference PPI #63, see previous response.
PPI 083
Document: General Please confirm that sheet piling work can be performed from the water outside of the In-Water Work window.
Answer: Confirmed. Sheet piling work can be performed from the water outside of the In-Water Work Window.
PPI 085
Document: Plans Section: CD100 Note 18 on Sheet CD100 references a "Fire Alarm Contractor". Is the Fire Alarm Contractor being provided by USCG or the Contractor? If by Contractor can you provide the name and contact information of the Fire Alarm company that maintains the system?
Answer: Fire Alarm contractor to be provided by Contractor.
All other terms and conditions remain unchanged. Offerors are reminded to acknowledge receipt of this amendment in response to the subject RFP.
| SF 30 Station Siuslaw Amendment 0005 |
| Amendment 5 |
| Siuslaw site visit log 06062024 |