About this file
This document is Amendment 0003 to a solicitation for a Design-Bid-Build construction project to correct shoreline erosion at the U.S. Coast Guard Station Siuslaw River in Florence, Oregon. The amendment provides answers to proposers' questions, clarifying that this is a Design-Bid-Build project, not a Design-Build project as initially indicated. It specifies a 60-calendar day proposal acceptance period and confirms there are no Controlled Unclassified Information (CUI) requirements for the project. The amendment also states that the Coast Guard does not plan to utilize any proprietary manufacturers. The solicitation number is 70Z05024R43000003, and the opportunity is only available to the successful offerors of the NMACC III Pool 1 contract.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
2. AMENDMENT/MODIFICATION NO.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
CORRECT SHORELINE EROSION AT USCG STATION SIUSLAW, FLORENCE, OR; Task Order Announcement 70Z05024R43000003; Amendment 0003: See Continuation Pages.
USCG FDCC DET SEATTLE
915 SECOND AVE, RM 2664
SEATTLE, WASHINGTON 98174-1011
9A. AMENDMENT OF SOLICITATION
NO.
70Z05024R43000003
1 2
06/03/2024
9B. DATED (SEE ITEM 11)
05/29/2024
X
X
Melvin Tiglao, Contracting Officer
70Z05024R43000003
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
ENCLOSED DOCUMENT: AMENDMENT 003 - ANSWERS TO PROPOSERS QUESTIONS:
PPI 001
Based on the project title and description of the work in the RFP, this appears to be a Design-Build project; however, it is unclear based on the drawings and specifications whether this is truly design-build. Please confirm whether this is a design-build or design-bid-build project as soon as possible so contractors can coordinate with their designer if needed.
Answer: This is a Design Bid Build (DBB) project. The references to Design Build (DB) on the Task Order Announcement on Page 1, Description of Work on Page 3, Title Are on Page 20 are hereby replaced with Design Bid Build.
PPI 002
What is the proposal acceptance period (proposal period) for this Task Order announcement? We do not see it mentioned in the RFP or on the Price Proposal Form.
Answer: 60 calendar days.
PPI 003
Are the RFP documents or any portion of them to be considered Controlled Unclassified Information (CUI) requiring protection per typical CUI restrictions?
Answer: There are no CUI requirements for this project. Please refer to the Specification document for details.
PPI 004
For Proprietary Products, please identify which items are required from a proprietary manufacturer or specific model on this project. If there are any, please provide the Justification and Approval documentation for this and identify three viable manufacturers for each of the identified proprietary items for the contractors to contact to receive competitive quotations.
Answer: USCG does not plan to utilize any proprietary manufacturers. Please refer to the Specification document for details.
PPI 005
We noticed that the Task Order Announcement indicates that this is Design/Build Construction, but it appears that TranSystems has completed the design already including stamped drawings and a complete project specification package. Please confirm that this is a Design-Bid-Build project and that no further design is required as this impacts who we may bring to the site visit.
Answer: This is a Design Bid Build (DBB) project. Also See PPI 001.
All other terms and conditions remain unchanged. The Proposal due date IS NOT EXTENDED.
Offerors are reminded to acknowledge receipt of this amendment in response to the subject RFP.
| STA Siuslaw Amendment 0003 |
| Amendment 003 Continuation Page |
| 2024-06-13T20:36:13-0700 | |
| TIGLAO.MELVIN.J A.1172808472 |
File details come from the government source that posted it. Updated .