This document is Amendment 0008 to the solicitation for the Design/Bid/Build Construction Project to Correct Shoreline Erosion at the U.S. Coast Guard Station Siuslaw River in Florence, Oregon. The amendment updates the Price Proposal Sheet, Rev 5, which includes a base item for the shore erosion wall and site civil improvements, and four optional items: upper retaining wall, no upper retaining wall, exterior floating dock guide pile replacement, and supplemental bridge piles. Offerors must provide prices for the base item and can choose to include pricing for the optional items. The total price, which includes the base item and any selected options, will be the basis for award. This opportunity is available only to the successful NMACC III Pool 1 Offerors. The Federal Agency involved is the Department of Homeland Security U.S. Coast Guard.

View the file

Other files

File Type Posted
Price Proposal Form Rev 6.pdf PDF
SF 30 Station Siuslaw Amendment 0010.pdf PDF
Suislaw EA_w all signatures (June 2024).pdf PDF
Draft MMPA IHA_USCG Station Siuslaw_41624.pdf PDF
SF 30 Station Siuslaw Amendment 0009 and continuation sheet.pdf PDF
Amendment 0007 03JUL2024.pdf PDF
Amendment 0006 02JUL2024.pdf PDF
Permit 2. BA_USCG Station Siuslaw.pdf PDF
STA Siuslaw Amendment 0005 with Site Visit Log.pdf PDF
STA Siuslaw Amendment 0005 Attachment PPI 073 Fiber Box Picture.pdf PDF
Permit 5. DEQ 401 WQC USCG Station Siuslaw River Covered Moorage and Shoreline 2023-651- signed.pdf PDF
STA Siuslaw Amendment 0005 Attachment PPI 076 Fuel Picture.pdf PDF
Permit 6. Section 408 No Alteration - USCG Covered Moorage and Shoreline.pdf PDF
Permit 3. CZMA Federal Consistency Determination_USCG Station Siuslaw.pdf PDF
STA Siuslaw Amendment 0005 STA Siuslaw Additional Specifications Update 06-27-2024 (PPI 075).pdf PDF
STA Siuslaw Amendment 0005 Attachment Geotechnical Report 1-26-2024.pdf PDF
Permit 1. Final JPA_USCG Station Siuslaw_revised.pdf PDF
Permit 4. Suislaw EA_w all signatures (June 2024).pdf PDF
STA Siuslaw Amendment 0004.pdf PDF
STA Siuslaw Amendment 0004 USCG SIUSLAW GEOTECHNICAL REPORT (version 12-07-2023).pdf PDF
STA Siuslaw Amendment 0001.pdf PDF
STA Siuslaw Amendment 0003.pdf PDF
STA Siuslaw Amendment 0002.pdf PDF
Task Order Announcement Station Siuslaw Correct Shore Erosion.pdf PDF
USCG Siuslaw FINAL Dwgs 2024.04.16.pdf PDF
USCG Siuslaw Drawings 100 percent Wall Plan.pdf PDF
USCG Siuslaw RFP Specs_Final 2024.04.16.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or

(c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

2. AMENDMENT/MODIFICATION NO.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

CORRECT SHORELINE EROSION AT USCG STATION SIUSLAW, FLORENCE, OR; Task Order Announcement 70Z05024R43000003; Amendment 0008: Updated Price Proposal Sheet Rev 5 on pages 2 and 3.

USCG FDCC DET SEATTLE

915 SECOND AVE, RM 2664

SEATTLE, WASHINGTON 98174-1011

9A. AMENDMENT OF SOLICITATION

NO.

70Z05024R43000003

1 3

07/19/2024

9B. DATED (SEE ITEM 11)

05/29/2024

X

X

Melvin Tiglao, Contracting Officer

PRICE PROPOSAL FORM

Provide prices per the following structure. Project scope is divided into Base Item, and Options, as indicated. Items not noted otherwise in the drawings are contained in the Base Item. See drawings and specifications for more detail. Option 1, or Option 2 will be awarded with the Base Item for a complete and usable requirement. The Government may award Options 3 and 4 in any combination or not awarded at all.

BASE ITEM:

Provide shore erosion wall and base site civil improvements, excluding site grading and upper retaining wall area described in Option 1 and Option 2. Temporarily remove and re-install eastern span of bridge, to allow installation of shore erosion wall. See documents for more detail.

Total: $_________________

OPTION 1: UPPER RETAINING WALL

Provide upper retaining wall as shown and described as “UPPER RETAINNG WALL”.

Total: $___________________

OPTION 2: NO UPPER RETAINING WALL

Provide site grading and no upper retaining wall as shown on plans and described as “NO

UPPER RETAINING WALL”.

Total: $___________________

OPTION 3: EXTERIOR FLOATING DOCK GUIDE PILE REPLACEMENT”

Demolish exterior floating dock guide piles and provide new exterior floating dock guide piles.

Mobilization/demobilization costs are not included.

Construction: $___________________

Mobilization / Demobilization: $___________________

Total: $___________________

OPTION 4: SUPPLEMENTAL BRIDGE PILES

Provide new supplementary piles at existing-to-remain bridge. Mobilization/demobilization costs are not included.

Construction: $___________________

Mobilization / Demobilization: $___________________

Total: $___________________

COMBINED MOBILIZATION/DEMOBILIZATION FOR OPTION 3 AND OPTION 4

Provide mobilization/demobilization costs for Option 3 and Option 4.

Combined Options 3 and 4 Construction: $___________________

Combined Options 3 and 4 Mobilization / Demobilization: $___________________

Combined Options 3 and 4 Total: $___________________

OFFERORS THAT INCLUDE LANGUAGE IN THEIR PROPOSALS CONTAINING

CONDITIONS MAY BE REJECTED.

TOTAL PRICE: The Total Price shall be deemed to include all costs required for all the specified work to be completed in accordance with the plans and specifications.

TOTAL PRICE (Base Item 1, Option 1, Option 2, Option 3, and Option 4) Options if any, will be exercised at time of award.

SF 30 Station Siuslaw Amendment 0008
Price Proposal Form Rev 5
2024-07-19T15:37:33-0700
TIGLAO.MELVIN.J A.1172808472