Price Proposal Form Rev 6.pdf

PDF 603 KB Posted

Attached to
DBB for Correct Shoreline Erosion at USCG Station Siuslaw in Florence, OR (NMACC III Pool 1)
Solicitation number
70Z05024R43000003
Issued by

About this file

This document is a Price Proposal Form for a federal Design/Bid/Build construction project to correct shoreline erosion at the U.S. Coast Guard Station Siuslaw River in Florence, Oregon. The project scope includes a base item for shore erosion wall and base site civil improvements, with four optional items: an upper retaining wall, no upper retaining wall, exterior floating dock guide pile replacement, and supplemental bridge piles. Offerors must provide fixed prices for the base item and each optional item. This opportunity is available only to the successful NMACC III Pool 1 offerors. The agency is the Department of Homeland Security U.S. Coast Guard. The solicitation number is 70Z05024R43000003.

View the file

Other files

File Type Posted
SF 30 Station Siuslaw Amendment 0010.pdf PDF
Suislaw EA_w all signatures (June 2024).pdf PDF
Draft MMPA IHA_USCG Station Siuslaw_41624.pdf PDF
SF 30 Station Siuslaw Amendment 0009 and continuation sheet.pdf PDF
Amendment 0008 with Price Proposal Rev 5 - 19JUL2024.pdf PDF
Amendment 0007 03JUL2024.pdf PDF
Amendment 0006 02JUL2024.pdf PDF
Permit 2. BA_USCG Station Siuslaw.pdf PDF
STA Siuslaw Amendment 0005 with Site Visit Log.pdf PDF
STA Siuslaw Amendment 0005 Attachment PPI 073 Fiber Box Picture.pdf PDF
Permit 5. DEQ 401 WQC USCG Station Siuslaw River Covered Moorage and Shoreline 2023-651- signed.pdf PDF
STA Siuslaw Amendment 0005 Attachment PPI 076 Fuel Picture.pdf PDF
Permit 6. Section 408 No Alteration - USCG Covered Moorage and Shoreline.pdf PDF
Permit 3. CZMA Federal Consistency Determination_USCG Station Siuslaw.pdf PDF
STA Siuslaw Amendment 0005 STA Siuslaw Additional Specifications Update 06-27-2024 (PPI 075).pdf PDF
STA Siuslaw Amendment 0005 Attachment Geotechnical Report 1-26-2024.pdf PDF
Permit 1. Final JPA_USCG Station Siuslaw_revised.pdf PDF
Permit 4. Suislaw EA_w all signatures (June 2024).pdf PDF
STA Siuslaw Amendment 0004.pdf PDF
STA Siuslaw Amendment 0004 USCG SIUSLAW GEOTECHNICAL REPORT (version 12-07-2023).pdf PDF
STA Siuslaw Amendment 0001.pdf PDF
STA Siuslaw Amendment 0003.pdf PDF
STA Siuslaw Amendment 0002.pdf PDF
Task Order Announcement Station Siuslaw Correct Shore Erosion.pdf PDF
USCG Siuslaw FINAL Dwgs 2024.04.16.pdf PDF
USCG Siuslaw Drawings 100 percent Wall Plan.pdf PDF
USCG Siuslaw RFP Specs_Final 2024.04.16.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRICE PROPOSAL FORM

Provide prices per the following structure. Project scope is divided into Base Item, and Options, as indicated. Items not noted otherwise in the drawings are contained in the Base Item. See drawings and specifications for more detail. Option 1, or Option 2 will be awarded with the Base Item for a complete and usable requirement. The Government may award Options 3 and 4 in any combination or not awarded at all.

BASE ITEM:

Provide shore erosion wall and base site civil improvements, excluding site grading and upper retaining wall area described in Option 1 and Option 2. Temporarily remove and re-install eastern span of bridge, to allow installation of shore erosion wall. See documents for more detail.

Total: $_________________

OPTION 1: UPPER RETAINING WALL

Provide upper retaining wall as shown and described as “UPPER RETAINNG WALL”.

Total: $___________________

OPTION 2: NO UPPER RETAINING WALL

Provide site grading and no upper retaining wall as shown on plans and described as “NO

UPPER RETAINING WALL”.

Total: $___________________

OPTION 3: EXTERIOR FLOATING DOCK GUIDE PILE REPLACEMENT”

Demolish exterior floating dock guide piles and provide new exterior floating dock guide piles.

Mobilization/demobilization costs are not included.

Construction: $___________________

Mobilization / Demobilization: $___________________

Total: $___________________

OPTION 4: SUPPLEMENTAL BRIDGE PILES

Provide new supplementary piles at existing-to-remain bridge. Mobilization/demobilization costs are not included.

Construction: $___________________

Mobilization / Demobilization: $___________________

Total: $___________________

COMBINED MOBILIZATION/DEMOBILIZATION FOR OPTION 3 AND OPTION 4

Provide mobilization/demobilization costs for Option 3 and Option 4.

Combined Options 3 and 4 Construction: $___________________

Combined Options 3 and 4 Mobilization / Demobilization: $___________________

Combined Options 3 and 4 Total: $___________________

OFFERORS THAT INCLUDE LANGUAGE IN THEIR PROPOSALS CONTAINING

CONDITIONS MAY BE REJECTED.

File details come from the government source that posted it. Updated .